MONTHYEARL-16-034, Distribution Notice for License Amendment Request to Adopt NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition)2016-02-0202 February 2016 Distribution Notice for License Amendment Request to Adopt NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) Project stage: Request ML14177A5782016-02-22022 February 2016 November 13, 2013, Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Delay in Submittal of Fire Risk Reduction Amendment Request Project stage: Meeting ML16047A1452016-02-22022 February 2016 Supplemental Information Needed for Acceptance of License Amendment Request to Adopt National Fire Protection Associated Standard 805 Project stage: Acceptance Review L-16-079, Supplemental Information for License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052016-03-0707 March 2016 Supplemental Information for License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 Project stage: Supplement ML16074A1232016-03-15015 March 2016 Acceptance of License Amendment Request to Adopt National Fire Protection Associated Standard 805 Project stage: Acceptance Review ML16075A1112016-03-23023 March 2016 Online Reference Portal for License Amendment Request to Adopt National Fire Protection Associated Standard 805 Project stage: Other ML16126A2362016-05-0505 May 2016 NRR E-mail Capture - Davis-Besse NFPA 805 Portal Project stage: Other ML16130A7182016-05-0909 May 2016 NRR E-mail Capture - Davis-Besse NFPA 805 Portal Project stage: Other L-16-170, Online Reference Portal for Review of National Fire Protection Association (NFPA) Standard 805 License Amendment Request2016-05-31031 May 2016 Online Reference Portal for Review of National Fire Protection Association (NFPA) Standard 805 License Amendment Request Project stage: Request ML16172A0312016-06-20020 June 2016 NRR E-mail Capture - Davis-Besse NFPA 805 Portal Project stage: Other ML16190A0752016-07-0808 July 2016 NRR E-mail Capture - Davis-Besse NFPA 805 Portal Project stage: Other ML16201A0172016-07-20020 July 2016 Regulatory Audit in Support of the License Amendment Request to Implement Risk-Informed, Performance-Based, Fire Protection Program as Allowed by Title 10 CFR, Paragraph 50.48(c) Project stage: Other L-16-232, Correction of Fire Probabilistic Risk Analysis (PRA) Results2016-07-28028 July 2016 Correction of Fire Probabilistic Risk Analysis (PRA) Results Project stage: Other ML16256A0662016-10-18018 October 2016 Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Associated Standard 805 Project stage: RAI L-16-345, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Cnfpa) Standard 8052016-12-16016 December 2016 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Cnfpa) Standard 805 Project stage: Response to RAI L-16-371, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052017-01-17017 January 2017 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 Project stage: Response to RAI ML17100A1732017-04-19019 April 2017 Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Associated Standard 805 Project stage: RAI L-17-189, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052017-06-16016 June 2017 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 Project stage: Response to RAI ML17257A1402017-09-14014 September 2017 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Project stage: RAI ML17258A1462017-09-20020 September 2017 Summary of September 12, 2017, Meeting with Firstenergy Nuclear Operating Company Regarding Its Licensing Amendment Request to Adopt National Fire Protection Association Standard 805 at Davis-Besse Nuclear Power Station, Unit No. 1 Project stage: Meeting L-17-253, Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052017-10-0909 October 2017 Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 Project stage: Supplement ML17355A3722017-12-21021 December 2017 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Project stage: RAI L-18-085, Response to Request for Additional Information and Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052018-04-0202 April 2018 Response to Request for Additional Information and Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 Project stage: Supplement ML18201A4122018-07-19019 July 2018 NRR E-mail Capture - Davis-Besse - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Project stage: RAI L-18-249, Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052018-11-20020 November 2018 Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 Project stage: Supplement ML19106A2512019-04-16016 April 2019 NRR E-mail Capture - Davis-Besse - Proposed License Condition and Draft Safety Evaluation for the License Amendment Request to Adopt NFPA 805 Project stage: Draft Approval ML19100A3062019-06-21021 June 2019 Issuance of Amendment No. 298 to Adopt National Fire Protection Association Standard 805 Project stage: Approval 2016-07-28
[Table View] |
Text
1 NRR-DMPSPEm Resource From:
Purnell, Blake Sent:
Thursday, December 21, 2017 11:21 AM To:
Lashley, Phil H.
Cc:
Wrona, David; talentz@firstenergycorp.com; Davisbesse.regulatory.affairs@firstenergycorp.com; Fenoc.regulatory.affairs@firstenergycorp.com
Subject:
RE: Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 (CAC No. MF7190)
- Phil, On December 20, 2017, you requested a 90-day extension to the request for additional information for the Davis-Besse NFPA 805 application that was due on January 10, 2018 (see e-mail below). You indicated that an extension was needed because (1) your technical staff is addressing a higher priority issue and (2) the scope of the changes to the PRA model is greater than anticipated. Your request was discussed with Joseph Giitter, Director of the Division of Risk Assessment, and Greg Casto, Acting Deputy Director of the Division of Operating Reactor Licensing.
The NRC staff finds your request for a 90-day extension acceptable. The NRC staff requests that a response to PRA RAI 03 be provided by April 10, 2018.
Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission ph: 301-415-1380 From: Purnell, Blake Sent: Thursday, September 14, 2017 9:39 AM To: Lashley, Phil H.
Cc: Wrona, David ; talentz@firstenergycorp.com; 'Davisbesse.regulatory.affairs@firstenergycorp.com' ;
'Fenoc.regulatory.affairs@firstenergycorp.com'
Subject:
Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 (CAC No. MF7190)
- Phil, By application dated December 16, 2015 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML15350A314), as supplemented by letters dated February 2, March 7, July 28, and December 16, 2016, and January 17 and June 16, 2017 (ADAMS Accession Nos. ML16033A085, ML16067A195, ML16210A422, ML16351A330, ML17017A504, and ML17170A000, respectively), FirstEnergy Nuclear Operating Company (the licensee), submitted a license amendment request (LAR) for Davis-Besse Nuclear Power Station, Unit No. 1 (DBNPS). The proposed amendment would change the current fire protection program at DBNPS to one based on the National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition, as incorporated into Title 10 of the Code of Federal Regulations Section 50.48(c).
2 By letter dated October 18, 2016 (ADAMS Accession No. ML16256A066), the U.S. Nuclear Regulatory Commission (NRC) staff issued a request for additional information (RAI) regarding the LAR. The letter stated, in part, that the due date for probabilistic risk assessment (PRA) RAI 03 will be provided after the staff has reviewed the licensees response to the other RAIs. The staff has completed its review of the licensees RAI responses provided in the supplemental letters. The staff requests that a response to PRA RAI 03 be provided by January 10, 2018. This due date was discussed with you on September 12, 2017.
If you have any questions, please contact me at (301) 415-1380 or by email.
Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Docket No. 50-346
Hearing Identifier:
NRR_DMPS Email Number:
67 Mail Envelope Properties (DM5PR09MB1193AB5DC0624396AAA0DD9EE60D0)
Subject:
RE: Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 (CAC No. MF7190)
Sent Date:
12/21/2017 11:21:22 AM Received Date:
12/21/2017 11:21:00 AM From:
Purnell, Blake Created By:
Blake.Purnell@nrc.gov Recipients:
"Wrona, David" <David.Wrona@nrc.gov>
Tracking Status: None "talentz@firstenergycorp.com" <talentz@firstenergycorp.com>
Tracking Status: None "Davisbesse.regulatory.affairs@firstenergycorp.com"
<Davisbesse.regulatory.affairs@firstenergycorp.com>
Tracking Status: None "Fenoc.regulatory.affairs@firstenergycorp.com" <Fenoc.regulatory.affairs@firstenergycorp.com>
Tracking Status: None "Lashley, Phil H." <phlashley@firstenergycorp.com>
Tracking Status: None Post Office:
DM5PR09MB1193.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3159 12/21/2017 11:21:00 AM Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received: