Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000346/2017010 (Jvb)
ML17135A361
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/12/2017
From: John Bozga
NRC/RGN-III/DRS/EB1
To: Boles B
FirstEnergy Nuclear Operating Co
References
IR 2017010
Download: ML17135A361 (6)


See also: IR 05000346/2017010

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

May 12, 2017

Mr. Brian D. Boles

Site Vice President

FirstEnergy Nuclear Operating Co.

Davis-Besse Nuclear Power Station

5501 N. State Rte. 2, Mail Stop A-DB-3080

Oak Harbor, OH 43449-9760

SUBJECT: DAVIS BESSE NUCLEAR POWER STATION, UNIT 1 - INFORMATION

REQUEST FOR NRC TRIENNIAL EVALUATIONS OF CHANGES, TESTS,

AND EXPERIMENTS (50.59) BASELINE INSPECTION 05000346/2017010

Dear Mr. Boles:

On September 18, 2017, the U.S. Nuclear Regulatory Commission (NRC) will begin a 50.59

Baseline Inspection at the Davis Besse Nuclear Power Station, Unit 1. This inspection will be

performed in accordance with the NRC Baseline Inspection Procedure 71111.17T. The onsite

portion of the inspection will take place on September 18-22, 2017.

Experience has shown that these baseline inspections are extremely resource intensive, both

for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on

the site and to ensure a productive inspection for both parties, we have enclosed a request for

documents needed for the inspection. These documents have been divided into three groups.

The first group of information is necessary to ensure that the inspection team is

adequately prepared for the inspection. This information should be made available via

compact disc and delivered to the regional office no later than August 7, 2017. The

inspection team will review this information and, by August 21, 2017, will request specific

items that should be provided for review in the regional office by September 5, 2017.

The second group of requested documents contains additional items that the team will

review, or need access to, during the inspection. Certain documents contained within

Group II (i.e., Item (1)), will be requested for review in the regional office prior to the

inspection by September 5, 2017, as identified above. The remaining documents should

be available by the first day of the onsite inspection, September 18, 2017.

The third group lists information necessary to aid the inspection team in tracking issues

identified as a result of the inspection. It is requested that this information be provided to

the lead inspector as the information is generated during the inspection. It is important

that all of these documents are up to date and complete in order to minimize the number

of additional documents requested during the preparation and/or the onsite portions of

the inspection.

B. Boles -2-

The lead inspector for this inspection is Mr. John V. Bozga. We understand that our regulatory

contact for this inspection is Ms. Vicki Schultz, 419-321-7690 of your organization. If there are

any questions about the inspection or the material requested, please contact the lead inspector

at 630-829-9613.

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,

a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget Control Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA James Neurauter Acting for/

John V. Bozga, Senior Reactor Inspector

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-346

License No. NPF-3

Enclosure:

50.59 Inspection Document Request

cc: Distribution via LISTSERV

B. Boles -3-

Letter to Brian D. Boles from John V. Bozga dated May 12, 2017

SUBJECT: DAVIS BESSE NUCLEAR POWER STATION, UNIT 1 - INFORMATION

REQUEST FOR NRC TRIENNIAL EVALUATIONS OF CHANGES, TESTS,

AND EXPERIMENTS (50.59) BASELINE INSPECTION 05000346/2017010

DISTRIBUTION:

Jeremy Bowen

RidsNrrDorlLpl3

RidsNrrPMDavisBesse Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

ADAMS Accession Number ML17135A361

OFFICE RIII RIII RIII RIII

NAME JNeaurauter for

JBozga:cl

DATE 05/12/17

OFFICIAL RECORD COPY

50.59 INSPECTION DOCUMENT REQUEST

Inspection Report: 05000346/2017010

Inspection Dates: September 18 - 22, 2017

Inspection Procedure: IP 71111.17T, Evaluations of Changes, Tests, and Experiments

Lead Inspector: John V. Bozga

630-829-9613

John.Bozga@nrc.gov

I. Information Requested for In-Office Preparation Week

The following information is requested by August 7, 2017, or sooner, to facilitate the

selection of specific items that will be reviewed during the onsite inspection week. The

inspection team will select specific items from the information requested below and

submit a list to your staff by August 21, 2017. We will request that certain items be

made available to the regional office prior to the inspection by September 5, 2017. We

request that the remaining items selected from the lists be available and ready for review

on the first day of inspection. All requested information should identify the associated

system and cover the time frame from the receipt of information for the last MOD/50.59

inspection to the present.

The required information identified below should be provided on compact disc (CD).

Please provide three copies of each CD submitted (i.e., one for each inspector). The

preferred file format is a searchable pdf file. The CDs should be indexed and hyper-

linked to facilitate ease of use, if possible. If you have any questions regarding this

information, please call the inspection team leader as soon as possible.

(1) List of all Title 10 of the Code of Federal Regulations (CFR), Part 50.59

completed evaluations involving: (a) calculations, (b) procedure revisions,

(c) changes to the facility (modifications), (d) non-routine operating

configurations, or (e) departures in methods of analyses. This list should include

50.59 evaluations for the following:

a. Changes that have been made under the provisions of 10 CFR 50.59 that

have been updated in accordance with 10 CFR 50.71(e)(4) since the last

MOD/50.59 inspection;

b. Modifications that are field work complete; and

c. Changes to calculations (or initiation of new calculations) that have been

issued. The list should contain the number and title of each document, a

brief description of the change, and the corresponding number and type of

the affected document (i.e., the modification or procedure to which the

evaluation applies). The list should NOT include any evaluations in

which prior U.S. Nuclear Regulatory Commission approval was sought

and obtained.

Enclosure

50.59 INSPECTION DOCUMENT REQUEST

(2) A list of all 10 CFR 50.59 changes that have been screened out as not requiring

a full evaluation involving: (a) calculations; (b) procedure revisions; (c) changes

to the facility (modifications); (d) non-routine operating configurations; or

(e) departures in methods of analyses.

The list should contain the number and title of each document, and the

corresponding number and type of the affected document (i.e., the modification

or procedure to which the evaluation applies).

(3) A list of any modifications, procedure revisions, or UFSAR changes where it was

determined that 10 CFR 50.59 did not apply.

(4) A list of calculation changes that have been issued for use.

(5) A list of corrective action documents (open and closed) that address

10 CFR 50.59 issues, concerns, or processes. These documents should also

include the corrective action documents associated with the modification and the

50.59 change implementation.

The list should contain the number, title and revision (or date) of each document,

the affected system and corresponding documentation (if applicable), and should

be sorted in order of significance.

(6) Copies of procedures addressing the following: modifications, design changes,

set point changes, equivalency evaluations or suitability analyses, commercial

grade dedications, post-modification testing, 10 CFR 50.59 evaluations and

screenings, and UFSAR updates.

(7) UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide

copies of the complete submittal.

(8) Copy of the UFSAR change log or a synopsis of the changes. This should

include all of the changes made to the UFSAR that were incorporated in the last

10 CFR 50.71(e)(4) submittal.

(9) Electronic copy of the UFSAR and technical specifications, if available. This

should include all of the changes made to the UFSAR that were incorporated in

the last 10 CFR 50.71(e)(4) submittal.

(10) Name(s) and phone numbers for the regulatory and technical contacts.

(11) Current management and engineering organizational chart.

II. Information Requested to be Available Prior to Inspection. Requests will be Made

for Specific Item (1) Documents by August 21, 2017, for Availability of Requested

Item (1) Documents in Regional Office by September 5, 2017, and Items (2), (3) and

(4) Documents on First Day of Inspection September 18, 2017.

(1) Copies of all selected items from Section I. This includes copies of

associated documents such as calculations, post-modification test packages,

10 CFR 50.59 evaluations or screenings, and any corrective action documents.

2

50.59 INSPECTION DOCUMENT REQUEST

(2) Copies of these documents do not need to be solely available to the inspection

team as long as the inspectors have easy and unrestrained access to them.

a. Updated Final Safety Analysis Report, if not previously provided;

b. Original Final Safety Analysis Report Volumes;

c. Original Safety Evaluation Report and Supplements;

d. Final Safety Analysis Report Question and Answers;

e. Quality Assurance Plan;

f. Technical Specifications, if not previously provided;

g. Latest Individual Plant Examination/Probabilistic Risk Assessment Report;

h. Vendor Manuals; and

i. The latest 10 CFR 50.59 Updated Final Safety Analysis Report Update

Submittal.

(3) Please ensure that other supporting documents for the selected items have been

located and are readily retrievable as the inspection team will likely be requesting

these documents during the inspection. Examples of supporting documents are:

a. Drawings supporting the modifications;

b. Procedures affected by the modifications; and

c. Updated Final Safety Analysis Report change papers generated due to a

10 CFR 50.59 evaluation.

(4) Assessment and Corrective Actions:

a. The most recent 50.59 Quality Assurance audit and/or self-assessment; and

b. Corrective action documents (e.g., condition reports, including status of

corrective actions) generate as a result of the most recent 50.59 Quality

Assurance audit and/or self-assessment.

III. Information Requested to be provided throughout the inspection

(1) Copies of any corrective action documents generated as a result of the

inspection teams questions or queries during this inspection.

(2) Copies of the list of questions submitted by the inspection team members and

the status/resolution of the information requested (provide daily during the

inspection to each inspection team member).

If you have any questions regarding the information requested, please contact the inspection

team leader.

3