ML18033B732

From kanterella
Revision as of 00:34, 18 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Responds to NRC 910510 Ltr Re Violations Noted in Insp Repts 50-259/91-10,50-260/91-10 & 50-296/9-10.Corrective Actions: Mod Closure Process for Vacuum Breakers Revised & New Nuclear Power Std on Equipment Clearances Issued
ML18033B732
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 06/21/1991
From: Medford M
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9106260164
Download: ML18033B732 (17)


See also: IR 05000259/1991010

Text

D SUBTECT: Responds to NRC 910510 ltr re violations

noted in Insp Repts<50-259/91-10

>50-260/91-10

&50-296/9-10.Corrective

actions: mod closure process for vacuum breakers revised&new nuclear power std on equipment clearances

issued.DISTRIBUTION

CODE: IEOID COPIES RECEIVED:LTR

J ENCL Q SIZE:/0 TITLE: General (50 Dkt)-Insp Rept/Notice

of Violation Response A 05000259 D 05000260 05000296 NOTES:1 Copy each to: B.Wilson,S.

BLACK 1 Copy each to: S.Black,B.WILSON

1 Copy each to: S.Black,B.WILSON

REGULATORY

INFORMATION

DISTRIBUTION

SYSTEM (RIDS)ESSION NBR:9106260164

DOC.DATE: 91/06/21 NOTARIZED:

NO DOCKET g CIL:50-259

Browns Ferry Nuclear Power Station, Unit 1, Tennessee 05000259 50-260 Browns Ferry Nuclear Power Station, Unit 2, Tennessee 05000260 50-296 Browns Ferry Nuclear Power Station, Unit 3, Tennessee 05000296 AUTH.NAME AUTHOR AFFILIATION

MEDFORD,M.O.

Tennessee Valley Authority RECIP.NAME

RECIPIENT AFFILIATION

Document Control Branch (Document Control Desk)RECIPIENT I D CODE/NAME HEBDON,F WILLIAMS,J.

RNAL: ACRS AEOD/DEIIB

DEDRO NRR SHANKMAN,S

NRR/DOEA/OEAB

NRR/DRIS/DIR

NRR/PMAS/ILRB12

0 EG F L 02 EXTERNAL: EG&G/BRYCE, J.H.NSIC NOTES: COPIES LTTR ENCL 1 1 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5 5 RECIPIENT ID CODE/NAME ROSS,T.AEOD AEOD/TPAB NRR MORISSEAU,D

NRR/DLPQ/LPEB10

NRR/DREP/PEPB9H

NRR/DST/DIR

8E2 NUDOCS-ABSTRACT

OGC/HDS3 RGN2 FILE 01 NRC PDR.COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 D NOTE TO ALL"RIDS" RECIPIENTS:

D D PLEASE HELP US TO REDUCE WASTEI CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT.20079)TO ELIMINATE YOUR NAME FROM DISTRIBUTION

LISTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 30 ENCL 30

TenneSSee Valley AuthOrity.

t t01 Market Street.ChattanOOga, TenneSSee 37402 Mark O.Medford Vice P~esident.

Nuclear Assurance, Licensing and Fuels JUN 211991 U.S.Nuclear Regulatory

Commission

ATTN: Document Control Desk Washington, D.C.20555 Gentlemen:

In the Matter of Tennessee Valley Authority Docket Nos.50-259 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN)-NRC INSPECTION

REPORT 50-259, 260, 296/91-10-REPLY TO NOTICE OF VIOLATION (NOV)This letter provides TVA's reply to the NOV transmitted

by letter from B.A.Wilson to Dan A.Nauman, dated May 10, 1991.NRC cited TVA with two violations.

The first violation contains two examples for failure to implement test control measures for returning components

to service, The second violation addresses two examples of failure to comply with Technical Specification

requirements

for not obtaining required compensatory

samples.TVA agrees that the violations

noted in the NOV violated regulatory

requirements.

Enclosure 1 to this letter is TVA's"Reply to the Notice of Violation" in accordance

with 10 CFR 2.201.A listing of commitments

made in this letter is provided in Enclosure 2.As agreed with your Staff, the submittal date for this reply was extended to June 24, 1991.9106260164

910621 PDR ADDCK 0 0t.t025'e 9 PDFi

U.S.Nuclear Regulatory

Commission

JUN 21 1991 If you have any questions regarding this response, please telephone Patrick P.Carier at (205)729-3570.Very truly yours, TENNESSEE VALLEY AUTHORITY Mark O.Medford Enclosures

cc (Enclosures):

Ms.S.C.Black, Deputy Director Project Directorate

11-4 U.S.Nuclear Regulatory

Commission

One White Flint, North 11555 Rockville Pike, Rockville, Maryland 20852 NRC Resident Inspector Browns Ferry Nuclear Plant Route 12, Box 637 Athens, Alabama 35609-2000

Mr.Thierry M.Ross, Project Manager U.S, Nuclear Regulatory

Commission

One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852 Mr.B.A.Wilson, Project Chief U.S.Nuclear Regulatory

Commission

Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323

,

Enclosure 1 Tennessee Valley Authority (TVA)Browns Ferry Nuclear Plant (BFN)Reply to Notice of Violation (NOV)Inspection

Report Number 50-259 260 296/91-10 NRC cites TVA with two violations.

The first violation involved two examples for failure to implement testing program requirements.

TVA agrees that a violation occurred in both examples.In example 1, adequate post modification

testing (PMT)requirements

were not performed due to a lack of administrative

control.This resulted in a field change request (FCR)not being reviewed prior to testing.In example 2, the residual heat removal service water (RHRSW)pump was not caution tagged due to personnel error.The second violation was for failure to maintain Technical Specification (TS)requirements

for compensatory

sampling.TVA agrees that a violation of regulatory

requirements

on compensatory

sampling occurred.The violation was due to poor work practices which resulted in two compensatory

activities

being signed off as complete when they were not performed.

VIOLATION A During the Nuclear Regulatory

Commission (NRC)inspection

conducted on March 16-April 19, 1991, a violation of NRC requirements

was identified.

The violation involved examples of failure to implement testing program requirements.

In accordance

with the'General Statement of Policy and Procedure for NRC Enforcement

Actions,'0

CFR Part 2, Appendix C (1990), the violation is listed below: "10 CFR50 Appendix B, Criterion XI, Test Control, requires that a test program shall be established

to assure that all testing required to demonstrate

that structures, systems, and components

will perform satisfactorily

in service is identified

and performed in accordance

with written test procedures

which incorporate

the requirements

and acceptance

limits contained in applicable

design documents.

Test results shall be documented

and evaluated to assure that test requirements

have been satisfied.

Page 2 of 7 Contrary to the above, activities

involving test control were not correctly implemented

in accordance

with requirements

for the following examples: Adequate post modification

testing (PNT)requirements

were not stipulated

following completion

of design change P3051.The reactor building to torus vacuum breakers opened unexpectedly

when torus pressure was greater than reactor building pressure during the integrated

leak rate test on March 18, 1991.The vacuum breakers are designed to vent air from the reactor building to the torus when reactor building pressure exceeds torus pressure by 0.5 psig.2.During the return to service activities

for the A3 residual heat removal service water pump, PMT was not completed.

The pump was not caution tagged as required by procedure SDSP 14.9, for components

awaiting PNT.The pump failed to start on October 4, 1990, when aligned to start for testing the 3D diesel generator.

The cause was later determined

to be a wiring error during implementation

of DCN W4515A.The same pump failed to autostart on September 27, 1990, during diesel generator testing and the cause had not been determined

as of October 4, 1990.This is a Severity Level IV Violation (Supplement

I)applicable

to all three uni ts~VIOLATION B"TS Section 3.2.D requires that radioactive

liquid effluent monitoring

instrumentation

listed in Table 3.2.D to be operable when effluent releases are in progress via the instrument

pathway.Table 3.2.D includes Raw Cooling Water (RCW)monitor 2-RN-90-132.

TS 3.2.D also requires that grab samples be collected and analyzed at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> when the RCW monitor is inoperable

and effluent releases are continued.

TS Section 3.2.K requires the radioactive

gaseous effluent monitoring

instruments

listed in Table 3.2.K to be operable.Table 3.2.K includes Reactor/Turbine

Building Ventilation

monitors 1-RM-90-250, 2-RM-90-250, and 3-RM-90-250

and Radwaste Building Ventilation

monitor 0-RN-90-252.

TS 3.2.K also requires that actions be taken whenever the instruments

are declared inoperable

and effluent releases are being conducted through an affected pathway.The required actions include a flow rate estimate at least once every four hours.Contrary to the above, on March 1, 1991, the licensee determined

that surveillance

instruction

data was not valid for the following two examples: 1.Flow rate estimates taken on December 5, 1990, at 4:00 a.m., for inoperable

monitors 1-RN-90-250, 2-RN-90-250, 3-RN-90-250, and O-RN-90-252.

Page 3 of 7 2.A compensatory

grab sample taken on December 11, 1990, at 10:03 a.m., for inoperable

RCW monitor 2-RM-90-132.

This is a Severity Level IV Violation (Supplement

I)applicable

to all three Units." TVA'S REPLY TO VIOLATION A EXAMPLE 1 l.Admission of Violation TVA agrees that a violation occurred.2.Reason for Violation This violation was caused by a lack of administrative

control.An adequate PMT was not performed because a FCR was not reviewed for impact on the PMT.The FCR modified pressure differential

transmitters (PDTs)for the vacuum breakers.At the time of this modification

there were no procedural

requirements

for the FCR to be reviewed for PMT requirements.

Engineering

Change Notice P3051 installed PDTs for the vacuum breaker valves (2-FCV-64-20

and 21).The modification

of the sensing lines to the PDTs was implemented

by WP 2036-84.The high and low side of the PDTs were connected to the process sensing lines in January 1987, and a walkdown of the PDTs was completed in July 1987.This walkdown was required to ensure that the instrument

lines were not reversed.PMT of the PDTs was started in August 1987 prior to the completion

of WP 2036-84.However, before the PMT of the PDTs was completed, WP 2036-84 was revised by a FCR to incorporate

vendor recommendations

on the PDTs.This involved rotating and reinstalling

the PDTs with the high side vent located on the top of the transmitters.

After the transmitters

were rotated, the sensing lines were incorrectly

attached to the PDTs.The revised WP was not reviewed again to ensure adequate PMT was performed on the PDTs.Other factors contributed

to the incorrect installation

of the sensing lines and the WP not being reviewed.These factors included the extended duration of the modification

and testing, and several changes in test directors and modifications

personnel resulting in the loss of continuity.

Page 4 of 7 Corrective

Ste s Taken and Results Achieved In this event, the FCR incorporating

the vendor recommendations

was not reviewed for impact on PMT.To address this weakness, the procedure governing modification

closure, Site Director's

Standard Practice (SDSP)12.4, now requires relevant FCRs, final design change notices (F-DCNs)and other safety design or testing changes (e.g., 10 CFR 50.59 review revisions)

be formally reviewed against the final as-built condition and final design requirements.

SDSP 12.4 also requires copies of F-DCNs to be distributed

to plant organizations

to inform them of minor changes to a modification

during implementation.

Additionally, this SDSP includes piping reroute modifications

as an item to be considered

by the system engineer during the field survey conducted just prior to plant acceptance

of a modification.

In addition, plant procedures

have been revised as part of the procedure upgrade program since the modification

of the PDTs.The PMT program now has its own governing document, SDSP-17.2.

This SDSP requires that each PMT instruction

have a prerequisite

addressing

review of the modification

installation

status.This delineates

review of any field change completion

status, and the impact of incomplete

or partially complete modification

status on initial testing.Also, configuration

control is maintained

in the test record drawings and these test record drawings require concurrence

signatures

by the implementing

organization, a Nuclear Engineering

representative, and the test director.This combined drawing review prior to the beginning of the test will detect any unincorporated

field changes affecting the test performance.

Finally, since the modification

of the PDTs of the vacuum breakers, the modification

closure process has been refined.This closure process now includes a revised modification

work completion

statement (SDSP-133)

form that lists the affected drawings and field changes.System engineers are required to review the SDSP-133 forms and are responsible

for system testing.This minimizes breaks in continuity.

Corrective

Ste s Which Will Be Taken No further corrective

steps are required.Date When Full Com liance Will Be Achieved TVA has achieved full compliance.

Page 5 of 7 EXANPLE 2 , Admission of Violation TVA agrees that a violation occurred.2.Reason for Violation This violation was caused by personnel error.In this event, a caution tag was not placed on the control switch for the A3 RHRSW pump as required by SDSP 14.9, Equipment Clearance Procedure, for components

awaiting PMT.Additionally, an inadequate

review of open corrective

action documents (i.e.test deficiency

and work order)from the diesel generator testing on September 27, 1990, permitted the incorrect assignment

of the A3 RHRSW pump to autostart on October 4, 1990.This inadequate

review is due to failure to adhere to Plant Managers Instruction (PMI)17.1, Conduct of Testing.Both conditions

were the result of personnel errors and indicate a lack of awareness of procedural

requirements.

A contributing

factor to this event was the inconsistent

personnel interpretation

of the word"immediately" as used in SDSP-14.9.

SDSP-14.9 states,"If maintenance

is performed...but the specified Post Maintenance

Testing cannot be completed immediately

following the maintenance, a caution order will be issued..." Interviews

with plant personnel indicated that the term"immediately" was interpreted

to mean a time frame that could extend up to several hours.3.Corrective

Ste s Taken and Results Achieved The October 4, 1990 event has been investigated, and the incident investigation (II)report of this event was reviewed with operations

personnel to emphasize the importance

of attention to detail and adherence to plant procedures.

Additionally, TVA has performed a Human Performance

Enhancement

System (HPES)evaluation

on the personnel involved, and the results of this HPES have been incorporated

as part of the II to prevent recurrence.

Subsequent

to this event, an additional

II (II-B-91-074)

was performed to review caution orders issued for equipment awaiting PMT.This investigation

revealed that prior to October 4, 1990, very few caution orders were written that denoted a PMT which had not been completed.

However, in the last quarter of 1990 and in the first quarter of 1991, the number of PMT-related

caution orders has substantially

increased.

TVA considers the increased number of PMT-related

caution orders can be credited to the current level of awareness resulting from review of the October 4, 1990 event.

Page 6 of 7 To prevent recurrences

on PMT-related

caution orders, the operator requalification

training lesson plan for the equipment clearance procedure has been revised to include the requirement

for caution orders to be placed for equipment awaiting PMT.Additionally, a computerized

clearance tracking system has been implemented

at BFN.This system will automatically

generate the caution tags which are required after maintenance.

4.Corrective

Ste s Which Will Be Taken Licensed and non-licensed

operators will review the II (II-B-91-074)

during their required reading, and this investigation

will be discussed with licensed operators by the Operations

Superintendent.

During this discussion

the Operations

Superintendent

will counsel each group on adherence to procedures, and reinforce Operations'olicies

concerning

equipment awaiting PMT.On April 4, 1991, a new TVA Nuclear Power Standard on equipment clearances

was issued.The standard has been reviewed by Operations

and defines the process by which caution tags are placed on equipment following maintenance.

The standard will be fully implemented

at BFN as a Site Standard Practice (SSP).This SSP will use the Technical Specification (TS)definition

of immediate, which means"the required action will be initiated as soon as practicable

considering

the safe operation of the unit and the importance

of the required action." Also, steps will be included in the practice that require equipment subject to automatic starts to have the caution order place the electrical

power sources in the non-operating

position.5.Date When Full Com liance Will Be Achieved Full compliance

will be achieved by September 15, 1991.TVA'S REPLY TO VIOLATION B EXAMPLES 1 AND 2 1.Admission of Violation TVA agrees that a violation occurred.2.Reason for the Violation This violation was caused by poor work practices.

The poor work practices resulted in two compensatory

activities

being signed off as complete when they were, in fact, not performed.

Page 7 of 7 As a result of a previous occurrence

involving missed compensatory

samples TVA reviewed Reactor Building entry data, refuel floor entry logs, Surveillance

Instruction (SI)data sheets, and conducted personnel interviews.

Based on the results of this review, TVA discovered

that Radiochemical

Laboratory

Analysts (RLAs)did not always sign off SI steps as they were performed, RLAs sometimes signed off steps that other RLAs performed, RLAs on occasion contacted other plant personnel for compensatory

flow readings, and the Chemistry Shift Supervisors (CSSs)did not always ensure SIs were completed when performed.

3.Corrective

Ste s Taken and Results Achieved Chemistry management

administered

personnel corrective

action to the employees involved in accordance

with TVA policy.In addition, Chemistry personnel were issued a memorandum

providing retraining

on the significance

of signatures/initials

in procedures.

This memorandum

clearly outlined management's

expectations

and the consequences

of non-compliance.

A similar site-wide memorandum

was issued discussing

the same subject.These actions should heighten the awareness level of chemistry personnel to the significance

of signatures.

For recurrence

control, chemistry management

is requiring the CSS to take a more active role in monitoring

shift activities.

Sign-offs for the CSS have been added to all the chemistry compensatory

SIs so that the CSS verifies completion

of each individual

compensatory

measure.Additionally, Chemistry management

conducted a two-week assessment

of laboratory

practices;

their observations

concluded that programmatic

deficiencies

did not exist.Finally, this event was referred to TVA's Office of Inspector General (OIG).The OIG confirmed that the incident was adequately

addressed and considers this matter closed.4.Corrective

Ste s Which Mill be Taken No further corrective

steps are required.5.Date When Full Com liance Will be Achieved TVA has achieved full compliance.

Enclosure 2 Listin of Commitments

for Violation A l.Operators will review Incident Investigation

II-B-91-074, and this investigation

will be discussed with licensed operators by the Operations

Superintendent.

The Operations

Superintendent

will counsel each group on adherence to procedures, and reinforce Operation's

policies concerning

equipment'awaiting PNT.This review will be completed by September 15, 1991.2.TVA's Nuclear Power Standard on equipment clearances

will be fully implemented

at Browns Ferry as a Site Standard Practice (SSP).This SSP.will use the technical specification

definition

of immediate and will include steps that require equipment subject to automatic starts to have the caution order place the electrical

power sources in the non-operating

position.This action will be completed by September 15, 1991.

h