ML16174A027: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 21: | Line 21: | ||
Reasons for Schedule Change FPRA Peer Review completed April 2016 -Additional tasks remain to resolve facts and observations -Refine FPRA model Add recent and future planned plant modifications -Requires additional time for development and implementation FLEX modifications Degraded Grid Voltage Protection modifications Safe Shutdown Analysis re-baseline compliance analysis completed December 2015 -SSA subsequent evaluations still in progress [Potential risk for additional VFDRs] Information Notice 92-18 mechanical evaluation - in progress Control Building HVAC heat up analysis updates - in progress Additional Activities -FP Code Deviations -FP System Hydraulic Calculations -Engineering Equivalency Evaluations FPRA Peer Review FPRA F&O Resolution / Model Refinement Additional Fire Protection Engineering Evaluations Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2016 2017 Fire Risk Evaluations Transition Report Apr 25 - 29 LAR Submittal 2018 Transition Report Review Risk Reduction SNC Final Review NSCA Transition Hatch NFPA 805 Transition Schedule 18 Month Project Status - Fire PRA Satisfactory FPRA Peer Review completed in April 2016 -CDF is in the E-04 range -Additional tasks remaining Facts and Observations resolution Reduce CDF and LERF to meet RG 1.174 criteria for total risk via model refinement (e.g., take credit for installed FLEX, Degraded Grid Voltage Protection modifications) and planned plant modification identification Perform Fire Risk Evaluations Project Status - Traditional FP Fundamental FP Program and Design Elements -NFPA 805 Chapter 3 Requirements - review completed -NFPA Code Compliance Evaluation - review completed -Existing Engineering Equivalency Evaluations for adequacy -review completed -GL 86-10s -Licensing Actions - no exemptions will be retained NFPA-805 Status LAR/TR Reference Topic % Complete N/A Safe shutdown Analysis Update (pre-requisite task) 90% 4.1, Attachment A Fundamental FP Program Elements and Minimum Design Requirements (Table B-1) 75% 4.2.1, Attachment B Nuclear Safety Capability Assessment - Methodology (Table B-2) 70% Section 4.2.2, Attachment C Nuclear Safety Capability Assessment - Fire Area - by - Fire Area Review (Table B-3) 50% Section 4.3, Attachment D Non Power Operational Modes (Table F-1) 60% Section 4.4, Attachment E Radioactive Release (Table G-1) 90% Section 4.1.3, Attachment I Definition of Power Block and Plant 100% Section 4.2.2 Existing Engineering Equivalency Evaluation Transition 30% Section 4.2.3, Attachment K Licensing Action Transition 90% Section 4.1.2.3, Attachment L NFPA 805 Chapter 3 Requirements Not Met and Not Previously Approved by NRC 55% N/A Fire PRA Peer Review 100% N/A Fire PRA Peer Review F&O Closure 25% Section 4.5.2.2 Fire Risk Evaluations 0% Section 4.6 Monitoring Program 0% Section 4.7 Program Documentation, Configuration Control, and Quality Assurance 0% Transition Report 5% | Reasons for Schedule Change FPRA Peer Review completed April 2016 -Additional tasks remain to resolve facts and observations -Refine FPRA model Add recent and future planned plant modifications -Requires additional time for development and implementation FLEX modifications Degraded Grid Voltage Protection modifications Safe Shutdown Analysis re-baseline compliance analysis completed December 2015 -SSA subsequent evaluations still in progress [Potential risk for additional VFDRs] Information Notice 92-18 mechanical evaluation - in progress Control Building HVAC heat up analysis updates - in progress Additional Activities -FP Code Deviations -FP System Hydraulic Calculations -Engineering Equivalency Evaluations FPRA Peer Review FPRA F&O Resolution / Model Refinement Additional Fire Protection Engineering Evaluations Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2016 2017 Fire Risk Evaluations Transition Report Apr 25 - 29 LAR Submittal 2018 Transition Report Review Risk Reduction SNC Final Review NSCA Transition Hatch NFPA 805 Transition Schedule 18 Month Project Status - Fire PRA Satisfactory FPRA Peer Review completed in April 2016 -CDF is in the E-04 range -Additional tasks remaining Facts and Observations resolution Reduce CDF and LERF to meet RG 1.174 criteria for total risk via model refinement (e.g., take credit for installed FLEX, Degraded Grid Voltage Protection modifications) and planned plant modification identification Perform Fire Risk Evaluations Project Status - Traditional FP Fundamental FP Program and Design Elements -NFPA 805 Chapter 3 Requirements - review completed -NFPA Code Compliance Evaluation - review completed -Existing Engineering Equivalency Evaluations for adequacy -review completed -GL 86-10s -Licensing Actions - no exemptions will be retained NFPA-805 Status LAR/TR Reference Topic % Complete N/A Safe shutdown Analysis Update (pre-requisite task) 90% 4.1, Attachment A Fundamental FP Program Elements and Minimum Design Requirements (Table B-1) 75% 4.2.1, Attachment B Nuclear Safety Capability Assessment - Methodology (Table B-2) 70% Section 4.2.2, Attachment C Nuclear Safety Capability Assessment - Fire Area - by - Fire Area Review (Table B-3) 50% Section 4.3, Attachment D Non Power Operational Modes (Table F-1) 60% Section 4.4, Attachment E Radioactive Release (Table G-1) 90% Section 4.1.3, Attachment I Definition of Power Block and Plant 100% Section 4.2.2 Existing Engineering Equivalency Evaluation Transition 30% Section 4.2.3, Attachment K Licensing Action Transition 90% Section 4.1.2.3, Attachment L NFPA 805 Chapter 3 Requirements Not Met and Not Previously Approved by NRC 55% N/A Fire PRA Peer Review 100% N/A Fire PRA Peer Review F&O Closure 25% Section 4.5.2.2 Fire Risk Evaluations 0% Section 4.6 Monitoring Program 0% Section 4.7 Program Documentation, Configuration Control, and Quality Assurance 0% Transition Report 5% | ||
Non-conformances & Compensatory Measures Existing Non- conformances -NFPA code deviations -NSCA cable separation issues Compensatory Measures: -Fire watches for code deviations -Combination of fire watches and Alternative Compensatory Measures -NRC review of alternate comp measures during TFPI found program to be in conformance with RIS 2005-07 Summary / Questions Additional time is needed to submit the NFPA-805 LAR -incorporate scope of currently planned plant modifications -Refine FPRA model and conduct Fire Risk Evaluations -Perform conceptual design studies for any other necessary modifications Propose request for 18 month extension to submit the LAR -Use NFPA-805 template to document project status -Submit request to NRC by July 15, 2016 | Non-conformances & Compensatory Measures Existing Non- conformances -NFPA code deviations -NSCA cable separation issues Compensatory Measures: -Fire watches for code deviations -Combination of fire watches and Alternative Compensatory Measures -NRC review of alternate comp measures during TFPI found program to be in conformance with RIS 2005-07 Summary / Questions Additional time is needed to submit the NFPA-805 LAR -incorporate scope of currently planned plant modifications -Refine FPRA model and conduct Fire Risk Evaluations -Perform conceptual design studies for any other necessary modifications Propose request for 18 month extension to submit the LAR -Use NFPA-805 template to document project status -Submit request to NRC by July 15, 2016}} | ||
}} |
Revision as of 07:34, 19 May 2018
ML16174A027 | |
Person / Time | |
---|---|
Site: | Hatch |
Issue date: | 06/21/2016 |
From: | Southern Nuclear Operating Co |
To: | Orenak M D Plant Licensing Branch II |
Orenak M D, NRR/DORL/LPLII-1, 415-3229 | |
References | |
CAC MF7736, CAC MF7737 | |
Download: ML16174A027 (10) | |
Text
NRC/SNC Meeting June 21, 2016 Plant Hatch NFPA 805 LAR Submittal Extension Request Agenda Meeting Purpose and Schedule Request Reason for Schedule Extension NFPA-805 Transition Schedule Current Status of NFPA-805 Project -Fire PRA -Traditional FP Scope Summary / Questions / Actions Summary & Purpose NRC Granted Enforcement Discretion for 10 CFR 50.48(b) for Plant Hatch based on an NFPA-805 LAR submittal date of October 4, 2016 Fire PRA development and plant modifications have delayed the fire protection transition project SNC intends to request an 18-month extension to the LAR submittal date -Demonstrate progress toward transition (SECY 12-0031) -Use NEI/Industry Template Purpose -Detail needed for extension request -Describe content and schedule of formal submittal -Discuss Hatch NFPA-805 Status to Date
Reasons for Schedule Change FPRA Peer Review completed April 2016 -Additional tasks remain to resolve facts and observations -Refine FPRA model Add recent and future planned plant modifications -Requires additional time for development and implementation FLEX modifications Degraded Grid Voltage Protection modifications Safe Shutdown Analysis re-baseline compliance analysis completed December 2015 -SSA subsequent evaluations still in progress [Potential risk for additional VFDRs] Information Notice 92-18 mechanical evaluation - in progress Control Building HVAC heat up analysis updates - in progress Additional Activities -FP Code Deviations -FP System Hydraulic Calculations -Engineering Equivalency Evaluations FPRA Peer Review FPRA F&O Resolution / Model Refinement Additional Fire Protection Engineering Evaluations Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2016 2017 Fire Risk Evaluations Transition Report Apr 25 - 29 LAR Submittal 2018 Transition Report Review Risk Reduction SNC Final Review NSCA Transition Hatch NFPA 805 Transition Schedule 18 Month Project Status - Fire PRA Satisfactory FPRA Peer Review completed in April 2016 -CDF is in the E-04 range -Additional tasks remaining Facts and Observations resolution Reduce CDF and LERF to meet RG 1.174 criteria for total risk via model refinement (e.g., take credit for installed FLEX, Degraded Grid Voltage Protection modifications) and planned plant modification identification Perform Fire Risk Evaluations Project Status - Traditional FP Fundamental FP Program and Design Elements -NFPA 805 Chapter 3 Requirements - review completed -NFPA Code Compliance Evaluation - review completed -Existing Engineering Equivalency Evaluations for adequacy -review completed -GL 86-10s -Licensing Actions - no exemptions will be retained NFPA-805 Status LAR/TR Reference Topic % Complete N/A Safe shutdown Analysis Update (pre-requisite task) 90% 4.1, Attachment A Fundamental FP Program Elements and Minimum Design Requirements (Table B-1) 75% 4.2.1, Attachment B Nuclear Safety Capability Assessment - Methodology (Table B-2) 70% Section 4.2.2, Attachment C Nuclear Safety Capability Assessment - Fire Area - by - Fire Area Review (Table B-3) 50% Section 4.3, Attachment D Non Power Operational Modes (Table F-1) 60% Section 4.4, Attachment E Radioactive Release (Table G-1) 90% Section 4.1.3, Attachment I Definition of Power Block and Plant 100% Section 4.2.2 Existing Engineering Equivalency Evaluation Transition 30% Section 4.2.3, Attachment K Licensing Action Transition 90% Section 4.1.2.3, Attachment L NFPA 805 Chapter 3 Requirements Not Met and Not Previously Approved by NRC 55% N/A Fire PRA Peer Review 100% N/A Fire PRA Peer Review F&O Closure 25% Section 4.5.2.2 Fire Risk Evaluations 0% Section 4.6 Monitoring Program 0% Section 4.7 Program Documentation, Configuration Control, and Quality Assurance 0% Transition Report 5%
Non-conformances & Compensatory Measures Existing Non- conformances -NFPA code deviations -NSCA cable separation issues Compensatory Measures: -Fire watches for code deviations -Combination of fire watches and Alternative Compensatory Measures -NRC review of alternate comp measures during TFPI found program to be in conformance with RIS 2005-07 Summary / Questions Additional time is needed to submit the NFPA-805 LAR -incorporate scope of currently planned plant modifications -Refine FPRA model and conduct Fire Risk Evaluations -Perform conceptual design studies for any other necessary modifications Propose request for 18 month extension to submit the LAR -Use NFPA-805 template to document project status -Submit request to NRC by July 15, 2016