{{#Wiki_filter:SOUTHERN CALIFORNIA I EDISON?An EDISON INTERNATIONALS Company Dwight E. Nunn Vice President December 3, 2003 U. S. Nuclear Regulatory Commission Attention:
{{#Wiki_filter:SOUTHERN CALIFORNIA I       EDISON?                                                             Dwight E. Nunn Vice President An EDISON INTERNATIONALS Company December 3, 2003 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555
Document Control Desk Washington, DC 20555  


==Subject:==
==Subject:==
Docket No. 50-206 Amendment Application No. 219 San Onofre Nuclear Generating Station, Unit I Gentlemen:
Docket No. 50-206 Amendment Application No. 219 San Onofre Nuclear Generating Station, Unit I Gentlemen:
By letter dated July 25, 2003, Southern California Edison (SCE) submitted Amendment Application No. 219 to the NRC. The amendment is a request to revise sections of the San Onofre Unit 1 Defueled Safety Analysis Report (DSAR) concerning modifications to the turbine gantry crane and turbine building and movement of spent fuel to the Independent Spent Fuel Storage Installation (ISFSI). Subsequently, an NRC reviewer raised questions regarding cold proof load testing as discussed in NUREG-0554, Section 2.4 and travel stops described in NUREG-0612 Appendix C. Provided as an enclosure is additional information on SCE's plans for the Unit 1 gantry crane.If you have any questions regarding this matter, please contact Dave Pilmer at (949) 368-1486.Sincerely, Enclosure cc: B. S. Mallett, Regional Administrator, NRC Region D. B. Spitzberg, NRC Region IV, San Onofre Unit 1 W. C. Huffman, NRC Project Manager, San Onofre Unit I C. C. Osterholtz, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P.O. Box 128 San Clemcnte, CA 92674-0128 949-368-1480 Fax 949-368-1490 UI''/ SE (
By letter dated July 25, 2003, Southern California Edison (SCE) submitted Amendment Application No. 219 to the NRC. The amendment is a request to revise sections of the San Onofre Unit 1 Defueled Safety Analysis Report (DSAR) concerning modifications to the turbine gantry crane and turbine building and movement of spent fuel to the Independent Spent Fuel Storage Installation (ISFSI). Subsequently, an NRC reviewer raised questions regarding cold proof load testing as discussed in NUREG-0554, Section 2.4 and travel stops described in NUREG-0612 Appendix C. Provided as an enclosure is additional information on SCE's plans for the Unit 1 gantry crane.
Enclosure Unit I Gantry Crane Additional Information QUESTION: The proposed revision to the DSAR (page 3.2-1 3j) states: 'The minimum operating temperature of the crane is 32 F, per the DSAR." I searched the previous DSAR revisions available in ADAMS, but I didn't find any reference to crane operating temperature.
If you have any questions regarding this matter, please contact Dave Pilmer at (949) 368-1486.
I would like to understand the basis for the crane operating temperature limit. If there is no adequate basis, I need to understand how their commitments to load testing relate to "cold proof' testing.RESPONSE: The statement, 'The minimum operating temperature of the crane is 32 F, per the DSAR", is based upon the minimum ambient temperatures recorded at the San Onofre site for the months of October thru March. In Appendix A, Historical Information, on page A-11 of the DSAR is Table A2-2 titled "Monthly Temperatures and Precipitation at Camp Pendleton Surf and Weather Station." Clarification is provided below to address the Unit I gantry crane's minimum operating temperature and cold proof" testing as discussed in NUREG-0554 section 2.4.The Unit 1 Gantry Crane will undergo a 125% "cold proof load test at completion of all structural modifications to the crane. The load test will be performed at a ime when the ambient atmospheric temperature, measured in the vicinity of the crane, is relatively cold, although likely to be well above 32 F. The ambient temperature at the time of load testing will be recorded and established as the minimum operating temperature of the crane for all spent fuel transfer cask lifts. Operation of the crane will be in accordance with the requirements of NUREG-0554 section 2.4.Prior to conducting the cold proof load test, a visual inspection at critical structural locations of the gantry crane will be performed.
Sincerely, Enclosure cc:     B. S. Mallett, Regional Administrator, NRC Region D. B. Spitzberg, NRC Region IV, San Onofre Unit 1 W. C. Huffman, NRC Project Manager, San Onofre Unit I C. C. Osterholtz, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P.O. Box 128 San Clemcnte, CA 92674-0128 949-368-1480 Fax 949-368-1490 UI''/ SE (
Critical locations are at member welds essential to the structural integrity of the crane handling system. Upon completion of load testing, these same locations will be inspected again to ensure that no structural damage or non-conformance with design requirements were introduced as a result of performing the load test. Qualified and certified personnel in accordance with the San Onofre Quality Assurance Program will conduct VT-1 type inspections.
 
A record will be made of the inspection and testing results.Page 1 of 2 Enclosure QUESTION: How is NUREG-0612, Appendix C item # 9 (travel stops) addressed by the design?RESPONSE: Safety devices are included in the handling system design to ensure that the X-SAM trolley and the gantry crane are located within the analyzed limits of the North Extension Structure.
Enclosure Unit I Gantry Crane Additional Information QUESTION:
The gantry bridge design includes end of travel limit switches and mechanical end stops for the X-SAM trolley. Gantry crane movement in the north direction is restricted by an exisfing mechanical end stop at column line AN. Gantry movement in the south direction is restricted by a seismic bumper attached above the equalizer pin which will impact with a support member on the seismic restraint structure.
The proposed revision to the DSAR (page 3.2-1 3j) states: 'The minimum operating temperature of the crane is 32 F, per the DSAR." I searched the previous DSAR revisions available in ADAMS, but I didn't find any reference to crane operating temperature. I would like to understand the basis for the crane operating temperature limit. If there is no adequate basis, I need to understand how their commitments to load testing relate to "cold proof' testing.
 
===RESPONSE===
The statement, 'The minimum operating temperature of the crane is 32 F, per the DSAR", is based upon the minimum ambient temperatures recorded at the San Onofre site for the months of October thru March. InAppendix A, Historical Information, on page A-11 of the DSAR is Table A2-2 titled "Monthly Temperatures and Precipitation at Camp Pendleton Surf and Weather Station."
Clarification is provided below to address the Unit I gantry crane's minimum operating temperature and cold proof" testing as discussed in NUREG-0554 section 2.4.
The Unit 1 Gantry Crane will undergo a 125% "cold proof load test at completion of all structural modifications to the crane. The load test will be performed at a ime when the ambient atmospheric temperature, measured in the vicinity of the crane, is relatively cold, although likely to be well above 32 F. The ambient temperature at the time of load testing will be recorded and established as the minimum operating temperature of the crane for all spent fuel transfer cask lifts. Operation of the crane will be in accordance with the requirements of NUREG-0554 section 2.4.
Prior to conducting the cold proof load test, a visual inspection at critical structural locations of the gantry crane will be performed. Critical locations are at member welds essential to the structural integrity of the crane handling system. Upon completion of load testing, these same locations will be inspected again to ensure that no structural damage or non-conformance with design requirements were introduced as a result of performing the load test. Qualified and certified personnel in accordance with the San Onofre Quality Assurance Program will conduct VT-1 type inspections. A record will be made of the inspection and testing results.
Page 1 of 2
 
Enclosure QUESTION:
How is NUREG-0612, Appendix C item # 9 (travel stops) addressed by the design?
 
===RESPONSE===
Safety devices are included in the handling system design to ensure that the X-SAM trolley and the gantry crane are located within the analyzed limits of the North Extension Structure. The gantry bridge design includes end of travel limit switches and mechanical end stops for the X-SAM trolley. Gantry crane movement in the north direction is restricted by an exisfing mechanical end stop at column line AN. Gantry movement in the south direction is restricted by a seismic bumper attached above the equalizer pin which will impact with a support member on the seismic restraint structure.
Page 2 of 2}}
Page 2 of 2}}

Latest revision as of 01:28, 24 November 2019

Amendment Application No. 219 - Unit 1 Gantry Crane Additional Information
ML033421354
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 12/03/2003
From: Nunn D
Southern California Edison Co
To:
Document Control Desk, NRC/FSME
References
+kBR1SISP20060320, -RFPFR
Download: ML033421354 (3)


Text

SOUTHERN CALIFORNIA I EDISON? Dwight E. Nunn Vice President An EDISON INTERNATIONALS Company December 3, 2003 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

Subject:

Docket No. 50-206 Amendment Application No. 219 San Onofre Nuclear Generating Station, Unit I Gentlemen:

By letter dated July 25, 2003, Southern California Edison (SCE) submitted Amendment Application No. 219 to the NRC. The amendment is a request to revise sections of the San Onofre Unit 1 Defueled Safety Analysis Report (DSAR) concerning modifications to the turbine gantry crane and turbine building and movement of spent fuel to the Independent Spent Fuel Storage Installation (ISFSI). Subsequently, an NRC reviewer raised questions regarding cold proof load testing as discussed in NUREG-0554, Section 2.4 and travel stops described in NUREG-0612 Appendix C. Provided as an enclosure is additional information on SCE's plans for the Unit 1 gantry crane.

If you have any questions regarding this matter, please contact Dave Pilmer at (949) 368-1486.

Sincerely, Enclosure cc: B. S. Mallett, Regional Administrator, NRC Region D. B. Spitzberg, NRC Region IV, San Onofre Unit 1 W. C. Huffman, NRC Project Manager, San Onofre Unit I C. C. Osterholtz, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P.O. Box 128 San Clemcnte, CA 92674-0128 949-368-1480 Fax 949-368-1490 UI/ SE (

Enclosure Unit I Gantry Crane Additional Information QUESTION:

The proposed revision to the DSAR (page 3.2-1 3j) states: 'The minimum operating temperature of the crane is 32 F, per the DSAR." I searched the previous DSAR revisions available in ADAMS, but I didn't find any reference to crane operating temperature. I would like to understand the basis for the crane operating temperature limit. If there is no adequate basis, I need to understand how their commitments to load testing relate to "cold proof' testing.

RESPONSE

The statement, 'The minimum operating temperature of the crane is 32 F, per the DSAR", is based upon the minimum ambient temperatures recorded at the San Onofre site for the months of October thru March. InAppendix A, Historical Information, on page A-11 of the DSAR is Table A2-2 titled "Monthly Temperatures and Precipitation at Camp Pendleton Surf and Weather Station."

Clarification is provided below to address the Unit I gantry crane's minimum operating temperature and cold proof" testing as discussed in NUREG-0554 section 2.4.

The Unit 1 Gantry Crane will undergo a 125% "cold proof load test at completion of all structural modifications to the crane. The load test will be performed at a ime when the ambient atmospheric temperature, measured in the vicinity of the crane, is relatively cold, although likely to be well above 32 F. The ambient temperature at the time of load testing will be recorded and established as the minimum operating temperature of the crane for all spent fuel transfer cask lifts. Operation of the crane will be in accordance with the requirements of NUREG-0554 section 2.4.

Prior to conducting the cold proof load test, a visual inspection at critical structural locations of the gantry crane will be performed. Critical locations are at member welds essential to the structural integrity of the crane handling system. Upon completion of load testing, these same locations will be inspected again to ensure that no structural damage or non-conformance with design requirements were introduced as a result of performing the load test. Qualified and certified personnel in accordance with the San Onofre Quality Assurance Program will conduct VT-1 type inspections. A record will be made of the inspection and testing results.

Page 1 of 2

Enclosure QUESTION:

How is NUREG-0612, Appendix C item # 9 (travel stops) addressed by the design?

RESPONSE

Safety devices are included in the handling system design to ensure that the X-SAM trolley and the gantry crane are located within the analyzed limits of the North Extension Structure. The gantry bridge design includes end of travel limit switches and mechanical end stops for the X-SAM trolley. Gantry crane movement in the north direction is restricted by an exisfing mechanical end stop at column line AN. Gantry movement in the south direction is restricted by a seismic bumper attached above the equalizer pin which will impact with a support member on the seismic restraint structure.

Page 2 of 2