MONTHYEARML0334213542003-12-0303 December 2003 Amendment Application No. 219 - Unit 1 Gantry Crane Additional Information Project stage: Other ML0335301762003-12-18018 December 2003 Amendment 162 Approving Single Failure Proof Use of Modified Turbine Building Gantry Crane and Support Structure at a Rated Capacity of 105 Tons Project stage: Other 2003-12-18
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000361/20240052024-10-0404 October 2024 NRC Inspection Report 05000361/2024005 and 05000362/2024005 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 07200041/20244012024-08-16016 August 2024 San Onofe Nuclear Generating Station, Security Baseline Inspection Report 07200041/2024401 IR 05000361/20240042024-08-0909 August 2024 NRC Inspection Report 05000361/2024004 and 05000362/2024004 ML24191A2472024-07-0202 July 2024 (Songs), Units 1, 2, and 3, and the Independent Spent Fuel Storage Installation - Revision to the ISFSI-Only Emergency Plan and Associated Changes to Emergency Plan Implementing Procedures ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24141A0802024-05-15015 May 2024 (Songs), Units 1, 2 and 3 and Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Operating Report IR 05000361/20240022024-04-0101 April 2024 – NRC Inspection Report 050-00361/2024-002 and 050-00362/2024-002 ML24094A0642024-03-27027 March 2024 Independent Spent Fuel Storage Installation, Decommissioning Funding Status Report 2023 ML24065A0152024-02-28028 February 2024 Generation Station Units 1, 2 and 3, Annual Radioactive Effluent Release Report for Independent Spent Fuel Storage Installation 2023 ML24044A0812024-02-14014 February 2024 LTR-24-0008: NRC Response to Paul Blanch Email Safety of Spent Nuclear Fuel at SONGS ISFSI IR 05000361/20240012024-02-13013 February 2024 NRC Inspection Report 050-00361/2024-001 and 050-00362/2024-001 (1) ML24037A0542024-01-30030 January 2024 (Songs), Units 2 and 3, Submittal of Annual Corporate Financial Reports ML24022A1492024-01-17017 January 2024 Independent Spent Fuel Storage Installation, Revision 4 to the Physical Security Plan ML24017A2432024-01-15015 January 2024 LTR-24-0008 Paul Blanch, E-mails Request for Formal Response to Requests for Meeting to Discuss Safety Issues with NRC Staff IR 05000361/20230062023-11-29029 November 2023 NRC Inspection Report 05000361/2023-006 and 05000362/2023-006 ML23333A0682023-11-22022 November 2023 (SONGS) Units 1, 2, 3 and Independent Spent Fuel Storage Installation - Notification of Change in Nuclear Officer IR 05000361/20230052023-10-11011 October 2023 NRC Inspection Report 05000361/2023005 and 05000362/2023005 ML23276A5942023-09-28028 September 2023 And Independent Spent Fuel Storage Installation - Supplement to Decommissioning Funding Status Reports ML23268A0922023-09-20020 September 2023 Generation Station, Units 1, 2 and 3, and the Independent Spent Fuel Storage Facility (ISFSI) - Re-Registration of Dry Fuel Storage Casks for Amended Certificate of Compliance No. 1040 IR 05000361/20230012023-09-13013 September 2023 NRC Inspection Report 05000361 2023-001 and 05000362 2023-004 ML23240A5372023-08-18018 August 2023 Confirmatory Survey Activities Summary and Results for the Unit 2 and 3 Intake Structures at the San Onofre Nuclear Generating Station San Clemente CA ML23129A1802023-06-14014 June 2023 Cover Letter to State of CA on Draft EA Regarding San Onofre ISFSI Updated DFPs IR 05000361/20230032023-05-31031 May 2023 NRC Inspection Report 05000361/2023003 and 05000362/2023003 IR 05000361/20230022023-05-23023 May 2023 NRC Inspection Report 05000361/2023-002 and 05000362/2023-002 ML23137A1032023-05-11011 May 2023 (Songs), Units 1, 2 and 3, and Independent Spent Fuel Storage Installation - 2022 Annual Radiological Environmental Operating Report ML23123A0932023-04-28028 April 2023 (Songs), Units 1, 2 and 3, Submittal of Annual Radioactive Effluent Release Report - 2022 ML23230A0882023-04-10010 April 2023 Independent Spent Fuel Storage Installation - Decommissioning Quality Assurance Plan ML23094A1272023-03-29029 March 2023 Independent Spent Fuel Storage Installation - 10 CFR 50.82(a)(8)(v and VII) and 10 CFR 72.30(c) Decommissioning Funding Status Report 2021 ML23094A1332023-03-29029 March 2023 Nuclear Property Insurance ML23062A1172023-02-28028 February 2023 Generation Station Units 1, 2 and 3, Annual Radioactive Effluent Release Report for Independent Spent Fuel Storage Installation - 2022 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23059A2812023-02-22022 February 2023 (Songs), Units 1, 2 and 3, 2022 Annual Turtle Incidental Take Report ML23046A3792023-02-22022 February 2023 NRC Inspection Report 050-00361/2023-001 and 050-00362/2023-001 ML23045A2022023-02-0909 February 2023 Submittal of Annual Corporate Financial Reports for San Onofre Nuclear Generating Station (SONGS) Units 2 and 3 for Fy Ending June 30, 2022 ML22287A1352023-01-0505 January 2023 Issuance of Exemption from Title 10 of the Code of Federal Regulations Part 72.106(B), Independent Spent Fuel Storage Installation Controlled Area Boundary (L-2021-LLE-0056) ML22348A0622023-01-0404 January 2023 NRC to SCE, Transmittal of the National Marine Fisheries Services December 12, 2022, Letter of Concurrence for Decommissioning of San Onofre Nuclear Generating Statiion, Units 2 and 3 IR 05000206/20220062022-12-15015 December 2022 NRC Inspection Report 05000206/2022006, 05000361/2022-006, and 05000362/2022-006 ML22347A2122022-12-12012 December 2022 NMFS to NRC, Endangered Species Act Section 7(a)(2) Concurrence Letter for Decommissioning of the San Onofre Nuclear Generating Station ML22340A6652022-12-0505 December 2022 Letter from John Fassell, Chief; Re., State of California Department of Public Health Review and Comments on SONGS Draft Environmental Assessment ML22333A8192022-11-21021 November 2022 Submittal of San Onofre Nuclear Generating Station, Units 2 and 3, Defueled Safety Analysis Report, Revised November 2022 IR 05000361/20220052022-11-17017 November 2022 – NRC Inspection Report 05000361/2022-005 and 05000362/2022-005 ML22301A1462022-10-20020 October 2022 Report of Violations of the National Pollutant Discharge Elimination System Permit San Onofre Nuclear Generating Station (Songs), Units 2 and 3 ML22277A0162022-09-29029 September 2022 Independent Spent Fuel Storage Installation Response to Request for Additional Information Regarding Request for Exemption from 10 CFR 72.106(b) IR 05000361/20220042022-09-26026 September 2022 NRC Inspection Report 05000361/2022-004 and 05000362/2022-004 ML22238A0552022-08-29029 August 2022 U.S. Nuclear Regulatory Commissions Analysis of Southern California Edisons Decommissioning Funding Status Report for San Onofre Nuclear Generating Station, Units 1, 2, and 3 ML22234A1602022-07-31031 July 2022 Final Report Per 10 CFR Part 21, Degraded Snubber SF1154 Hydraulic Fluid Batch No. 18CLVS431 ML22207B8612022-07-26026 July 2022 NRC (Public) Inspection Report 05000361/2022003; 05000362/2022003 IR 05000361/20220032022-07-26026 July 2022 NRC Inspection Report (Public) 05000361-2022003 and 05000362-2022003 (002) IR 05000361/20220022022-05-12012 May 2022 NRC Inspection Report 05000361/2022-002 and 05000362/2022-002 2024-09-18
[Table view] |
Text
SOUTHERN CALIFORNIA I EDISON? Dwight E. Nunn Vice President An EDISON INTERNATIONALS Company December 3, 2003 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555
Subject:
Docket No. 50-206 Amendment Application No. 219 San Onofre Nuclear Generating Station, Unit I Gentlemen:
By letter dated July 25, 2003, Southern California Edison (SCE) submitted Amendment Application No. 219 to the NRC. The amendment is a request to revise sections of the San Onofre Unit 1 Defueled Safety Analysis Report (DSAR) concerning modifications to the turbine gantry crane and turbine building and movement of spent fuel to the Independent Spent Fuel Storage Installation (ISFSI). Subsequently, an NRC reviewer raised questions regarding cold proof load testing as discussed in NUREG-0554, Section 2.4 and travel stops described in NUREG-0612 Appendix C. Provided as an enclosure is additional information on SCE's plans for the Unit 1 gantry crane.
If you have any questions regarding this matter, please contact Dave Pilmer at (949) 368-1486.
Sincerely, Enclosure cc: B. S. Mallett, Regional Administrator, NRC Region D. B. Spitzberg, NRC Region IV, San Onofre Unit 1 W. C. Huffman, NRC Project Manager, San Onofre Unit I C. C. Osterholtz, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P.O. Box 128 San Clemcnte, CA 92674-0128 949-368-1480 Fax 949-368-1490 UI/ SE (
Enclosure Unit I Gantry Crane Additional Information QUESTION:
The proposed revision to the DSAR (page 3.2-1 3j) states: 'The minimum operating temperature of the crane is 32 F, per the DSAR." I searched the previous DSAR revisions available in ADAMS, but I didn't find any reference to crane operating temperature. I would like to understand the basis for the crane operating temperature limit. If there is no adequate basis, I need to understand how their commitments to load testing relate to "cold proof' testing.
RESPONSE
The statement, 'The minimum operating temperature of the crane is 32 F, per the DSAR", is based upon the minimum ambient temperatures recorded at the San Onofre site for the months of October thru March. InAppendix A, Historical Information, on page A-11 of the DSAR is Table A2-2 titled "Monthly Temperatures and Precipitation at Camp Pendleton Surf and Weather Station."
Clarification is provided below to address the Unit I gantry crane's minimum operating temperature and cold proof" testing as discussed in NUREG-0554 section 2.4.
The Unit 1 Gantry Crane will undergo a 125% "cold proof load test at completion of all structural modifications to the crane. The load test will be performed at a ime when the ambient atmospheric temperature, measured in the vicinity of the crane, is relatively cold, although likely to be well above 32 F. The ambient temperature at the time of load testing will be recorded and established as the minimum operating temperature of the crane for all spent fuel transfer cask lifts. Operation of the crane will be in accordance with the requirements of NUREG-0554 section 2.4.
Prior to conducting the cold proof load test, a visual inspection at critical structural locations of the gantry crane will be performed. Critical locations are at member welds essential to the structural integrity of the crane handling system. Upon completion of load testing, these same locations will be inspected again to ensure that no structural damage or non-conformance with design requirements were introduced as a result of performing the load test. Qualified and certified personnel in accordance with the San Onofre Quality Assurance Program will conduct VT-1 type inspections. A record will be made of the inspection and testing results.
Page 1 of 2
Enclosure QUESTION:
How is NUREG-0612, Appendix C item # 9 (travel stops) addressed by the design?
RESPONSE
Safety devices are included in the handling system design to ensure that the X-SAM trolley and the gantry crane are located within the analyzed limits of the North Extension Structure. The gantry bridge design includes end of travel limit switches and mechanical end stops for the X-SAM trolley. Gantry crane movement in the north direction is restricted by an exisfing mechanical end stop at column line AN. Gantry movement in the south direction is restricted by a seismic bumper attached above the equalizer pin which will impact with a support member on the seismic restraint structure.
Page 2 of 2