ML17263A433: Difference between revisions
From kanterella
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 13: | Line 13: | ||
| document type = Letter, Response to Request for Additional Information (RAI) | | document type = Letter, Response to Request for Additional Information (RAI) | ||
| page count = 24 | | page count = 24 | ||
| project = CAC: | | project = CAC:MF9345, CAC:MF9346 | ||
| stage = Response to RAI | | stage = Response to RAI | ||
}} | }} |
Revision as of 02:35, 25 April 2018
Letter Sequence Response to RAI | |
---|---|
Initiation Administration | |
MONTHYEARML17055C3592017-02-23023 February 2017
[Table View]License Amendment Request: Revision to Emergency Plan Staff Augmentation Response Times Project stage: Request ML17066A3612017-03-0707 March 2017 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Revise Emergency Plan Staff Augmentation Response Times Project stage: Acceptance Review L-PI-17-032, Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Response Times2017-09-20020 September 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Response Times Project stage: Response to RAI ML17362A2022018-03-0505 March 2018 Issuance of Amendment Concerning Revision to the Prairie Island Nuclear Generating Plant, Units 1 and 2 Emergency Plan (CAC Nos. MF9345 and MF9346; EPID L-2017-LLA-0175) Project stage: Approval 2017-03-07 |
ML17263A433 | |
Person / Time | |
---|---|
Site: | Prairie Island |
Issue date: | 09/20/2017 |
From: | Northard S Northern States Power Company, Minnesota, Xcel Energy |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
CAC MF9345, CAC MF9346, L-PI-17-032 | |
Download: ML17263A433 (24) | |
Similar Documents at Prairie Island | |
---|---|
Category:Letter
MONTHYEARIR 05000282/20244032024-10-25025 October 2024
[Table view]– Security Baseline Inspection Report 05000282/2024403 and 05000306/2024403 05000282/LER-2024-001-01, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-10-22022 October 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies L-PI-24-044, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-10-21021 October 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML24277A1012024-10-0303 October 2024 Closure of Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software ML24241A1682024-09-23023 September 2024 Transmittal Letter Amendment No. 13 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation 05000282/LER-2024-001, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-09-16016 September 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies IR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) L-PI-24-040, Post-Submittal Package Letter2024-08-23023 August 2024 Post-Submittal Package Letter IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 ML24213A1592024-07-31031 July 2024 Operator Licensing Examination Approval - Prairie Island Nuclear Generating Plant IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 L-PI-24-036, – Preparation and Scheduling of Operator Licensing Examinations2024-06-28028 June 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24158A5912024-06-0606 June 2024 CFR 50.46 LOCA Annual Report L-PI-24-031, Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-06-0505 June 2024 Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption ML24155A1952024-05-31031 May 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24155A1922024-05-31031 May 2024 Refueling Outage Unit 2 R33 Owners Activity Report for Class 1, 2, 3 and Mc Inservice Inspections ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML24262A1992024-05-29029 May 2024 L-PI-24-018 PINGP 75 Day Letter ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information L-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24128A2572024-05-16016 May 2024 ISFSI A13 Acceptance Letter IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 ML24130A2362024-05-0909 May 2024 Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Monitoring Program Report ML24130A2392024-05-0909 May 2024 2023 Annual Radioactive Effluent Report ML24071A1162024-05-0101 May 2024 Issuance of Amendment Nos. 244 and 232 Revise TS 3.7.8, Cooling Water (Cl) System ML24128A0882024-04-30030 April 2024 Submittal of Updated Safety Analysis Report (Usar), Revision 38 ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance ML24121A0432024-04-29029 April 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump IR 05000282/20244012024-04-25025 April 2024 – Security Baseline Inspection Report 05000282/2024401 and 05000306/2024401 ML24100A8042024-04-24024 April 2024 – Alternative Request RR-09 for Safety Injection and Volume Control System Category C Check Valve Inservice Testing ML24114A0882024-04-23023 April 2024 Annual Report of Individual Monitoring for the Prairie Island Nuclear Generating Plant (PINGP) ML24113A1182024-04-12012 April 2024 NRC Letter Re NRC Office of Investigations Report No. 3-2023-004 ML24100A1212024-04-0909 April 2024 Submittal of Revised Pressure and Temperature Limits Report L-PI-24-012, Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-04-0202 April 2024 Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) ML24093A2832024-04-0202 April 2024 Nuclear Material Transaction Report ML24089A2402024-03-29029 March 2024 Guarantee of Payment of Deferred Premiums ML24060A1232024-03-27027 March 2024 to Request 1-RR-5-10 and 2-RR-5-10 Regarding Reactor Pressure Vessel Welds and Nozzle Welds ML24081A1532024-03-21021 March 2024 Reactor Trip, Auxiliary Feedwater and Emergency Service Water System Actuation Due to Electrical Transient in DC Control Power Cables ML24262A1512024-03-15015 March 2024 L-PI-24-011 150 Day Letter 2024 PINGP ILT NRC Exam ML24010A0582024-03-0505 March 2024 Amendment No. 12 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation L-PI-24-004, Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 20232024-02-29029 February 2024 Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 2023 IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) ML24088A1102024-02-25025 February 2024 Fairbanks Morse (Fm) Part 21 Notification Report Number 23-01 Re Asco Stainless Steel Solenoid Valves L-PI-24-009, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing2024-02-13013 February 2024 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing 2024-09-23 Category:Response to Request for Additional Information (RAI) MONTHYEARL-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024
[Table view]Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 L-PI-24-009, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing2024-02-13013 February 2024 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing L-PI-23-034, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System,2024-01-0202 January 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System, L-PI-23-035, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2023-12-20020 December 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report L-PI-23-033, Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-12-0505 December 2023 Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports L-PI-22-034, Response to RAI, Alternative RR-08 Related to Pressure Isolation Valve Monitoring and Testing2022-07-14014 July 2022 Response to RAI, Alternative RR-08 Related to Pressure Isolation Valve Monitoring and Testing L-PI-22-033, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles2022-06-10010 June 2022 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles ML22161A9152022-06-10010 June 2022 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Response to a Request for Additional Information Xcel Energy Amendment Request to Create a Common Emergency Plan and Emergency Operations. L-PI-21-047, Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 22021-12-0707 December 2021 Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 2 L-PI-21-045, Response to Request for Additional Information Cooling Water System License Amendment Request2021-11-0404 November 2021 Response to Request for Additional Information Cooling Water System License Amendment Request L-PI-21-032, Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island2021-09-30030 September 2021 Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island L-PI-20-026, Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiativ2020-09-0101 September 2020 Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 L-PI-20-023, Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI)2020-06-10010 June 2020 Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI) ML20045E8942020-02-14014 February 2020 Response to a Request for Additional Information for Proposed 10 CFR 50.55a(z)(2) Alternatives to Utilize ASME Code Case N-786-3, Alternative Requirements for Sleeve Reinforcement of Class 2 and 3 Moderate-Energy Carbon Steel Piping, and AS ML20127J0002019-11-0707 November 2019 Xcel Reply to PIIC Expansion Application L-PI-19-037, Response to Request for Additional Information: 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals2019-09-16016 September 2019 Response to Request for Additional Information: 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals L-PI-19-029, Supplement to Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components For...2019-08-0505 August 2019 Supplement to Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components For... L-PI-19-014, Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2019-04-29029 April 2019 Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-PI-18-063, Response to Request for Additional Information: Revise License Condition Associated with Implementation of NFPA 8052018-12-0606 December 2018 Response to Request for Additional Information: Revise License Condition Associated with Implementation of NFPA 805 L-PI-18-051, Response to Request for Additional Information: Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program2018-09-17017 September 2018 Response to Request for Additional Information: Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program L-PI-18-038, Supplement to License Amendment Request to Revise License Condition Associated with Implementation of NFPA 8052018-07-10010 July 2018 Supplement to License Amendment Request to Revise License Condition Associated with Implementation of NFPA 805 ML18131A2232018-05-11011 May 2018 Prairie and Monticello - Response to Request for Additional Information Regarding Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Di L-PI-17-042, Response to Request for Additional Information Regarding License Amendment Request to Revise the NDE Inspection Interval for Special Lifting Devices2017-11-0606 November 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise the NDE Inspection Interval for Special Lifting Devices ML17279A1212017-10-0404 October 2017 Enclosure 2 to L-PI-17-041, Westinghouse-Prepared RAI Responses CE-17-3, Rev. 1, Attachment 2 and Enclosure 3, Marked-Up Technical Specification Page 4.0-7 L-PI-17-035, License Amendment Request to Revise the Emergency Action Level (EAL) Scheme - Supplement and Response to Requests for Additional Information2017-09-27027 September 2017 License Amendment Request to Revise the Emergency Action Level (EAL) Scheme - Supplement and Response to Requests for Additional Information L-PI-17-032, Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Response Times2017-09-20020 September 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Response Times L-PI-17-007, Response to Request for Additional Information on License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors2017-03-0606 March 2017 Response to Request for Additional Information on License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors L-PI-17-002, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action2017-02-16016 February 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action L-PI-16-100, Response to NRC Request for Information - License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes2017-02-16016 February 2017 Response to NRC Request for Information - License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes L-PI-16-090, Response to Request for Additional Information on License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors2016-12-14014 December 2016 Response to Request for Additional Information on License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors ML16351A2102016-12-13013 December 2016 External Flooding Assessment Focused Evaluation. (Redacted) ML16288A0972016-10-14014 October 2016 and Monticello - Response to Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools ML16279A4792016-09-29029 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information L-PI-16-076, Supplement to the Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report2016-09-29029 September 2016 Supplement to the Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report L-PI-16-067, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors- Response to Request for Additional Information2016-08-17017 August 2016 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors- Response to Request for Additional Information L-PI-16-063, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-17017 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events L-PI-16-005, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors - Response to Request for Additional Information2016-05-24024 May 2016 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors - Response to Request for Additional Information L-PI-16-040, Supplement to License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes: Westinghouse-Prepared Response to RAI, CE-16-237, Attachment 2 (Enclosure 4)2016-05-23023 May 2016 Supplement to License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes: Westinghouse-Prepared Response to RAI, CE-16-237, Attachment 2 (Enclosure 4) ML16144A8062016-05-23023 May 2016 Supplement to License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes: Response to RAI-2 (Enclosure 1) & Marked-Up Technical Specification Page (Enclosure 2) ML16133A0412016-05-0909 May 2016 Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report L-08-001, Response to Requests for Additional Information - License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2, Using the Consolidated..2016-04-14014 April 2016 Response to Requests for Additional Information - License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2, Using the Consolidated.. L-PI-16-029, Response to Requests for Additional Information - License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2,,Using the Consolidated..2016-03-31031 March 2016 Response to Requests for Additional Information - License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2,,Using the Consolidated.. L-PI-16-004, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors- Response to Request for Additional Information2016-01-20020 January 2016 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors- Response to Request for Additional Information L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report2016-01-14014 January 2016 Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report L-PI-15-105, License Amendment Request (LAR) to Revise Technical Specifications (TS) to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process - Response to Request..2015-12-30030 December 2015 License Amendment Request (LAR) to Revise Technical Specifications (TS) to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process - Response to Request.. L-PI-15-052, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors - Response to Request for Additional Information - 90-Day Responses2015-06-19019 June 2015 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors - Response to Request for Additional Information - 90-Day Responses L-PI-14-113, Updated Final Response to NRC Request for Information Per 10CFR50.54(f) Re Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2015-01-16016 January 2015 Updated Final Response to NRC Request for Information Per 10CFR50.54(f) Re Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident 2024-05-22 |
Text
Document Control Desk Page 2 Summary of Commitments This letter makes no new commitments and no revisions to existing commitments. I declare under penalty of perjury, that the foregoing is true and correct. Exec ed o ber ZQ_, 2017. orthard Site Vice President, Prairie Island Nuclear Generating Plant Northern States Power Company-Minnesota Enclosure cc: Administrator, Region Ill, USNRC Project Manager, Prairie Island, USNRC Resident Inspector, Prairie Island, USNRC State of Minnesota
Retrieved from "https://kanterella.com/w/index.php?title=ML17263A433&oldid=598671"