L-PI-16-076, Supplement to the Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report

From kanterella
Jump to navigation Jump to search

Supplement to the Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report
ML16273A556
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 09/29/2016
From: Northard S
Northern States Power Company, Minnesota, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-PI-16-076
Download: ML16273A556 (5)


Text

1717 Wakonade Drive East Welch, MN 55089 (l Xcel Energy*

IIIE I P 8 N II I l l I Y N A Hill E*

800.895.4999 xcelenergy.com L-PI-16-076 SEP 2 9 2016 10 CFR 50.54(f)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant Units 1 and 2 Docket Numbers 50-282 and 50-306 Renewed Facility Operating License Nos. DPR-42 and DPR-60 Prairie Island Nuclear Generating Plant. Units 1 and 2 - Supplement to the Response to March 12, 2012. Request for Information Enclosure 2. Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report

References:

1. NRC Letter, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident,"

dated March 12, 2012 (ADAMS Accession No. ML12056A046)

2. NSPM Letter L-PI-16-039 from S. Northard to Document Control Desk (NRC),

"Prairie Island Nuclear Generating Plant, Units 1 and 2, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report," dated May 9, 2016 (ADAMS Accession No. ML16133A030)

3. NRC electronic mail from Lauren Gibson to Lynne Gunderson, "QUO: Additional Information Needs for Prairie Island and Monticello FHRR Audits," dated August 30, 2016 (Non-public ADAMS Accession No. ML16244A684)

On March 12, 2012, the NRC issued Reference 1, which included a request for information associated with Near-Term Task Force (NTTF) Recommendation 2.1 for flooding. Enclosure 2 of Reference 1 addresses the Requested Information and Required Response. The NRC Staff requested licensees to perform a flood hazard reevaluation (Requested Information Item 1) and to provide a final report documenting the results in accordance with the NRC's prioritization plan (Required Response Item 2).

Document Control Desk Page2 By the Reference 2 letter, Northern States Power Company, a Minnesota corporation (NSPM), d/b/a Xcel Energy, provided the Flood Hazard Reevaluation Report (FHRR) for Prairie Island Nuclear Generating Plant (PINGP), Units 1 and 2. Direct responses to the Reference 1, Enclosure 2, Requested Information Item 1, were included in Appendix 1 of the PINGP FHRR.

During an audit call with NRC Staff on August 18, 2016, NSPM provided information regarding doorways that were evaluated in the Local Intense Precipitation (LIP) analysis but had not been translated into Table 2 of the FHRR (Reference 2). NSPM also noted a discrepancy between the reach #21 0 HEC-HMS output hydrograph and the HEC-RAS hydrograph. The NRC requested additional information on August 30, 2016 (Reference 3), which included a request to provide, by letter, an addendum document to the FHRR that explained the correction for the missing doors.

The purpose of this supplement is to provide an addendum to the PINGP FHRR that updates Table 2 in the Enclosures of the FHRR based on the omitted doorways and the updated hydrograph. The addendum also updates text from FHRR sections that were affected. For the doors that were not translated to the FHRR, no interim actions were necessary. The overall conclusion of the FHRR does not change.

Please contact Lynne Gunderson, Licensing Engineer, at 651-267-7421, if additional information or clarification is required.

Summary of Commitments This letter makes no new commitments and no revisions to existing commitments.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on Septembercf_~ 2016.

Scott Northard Site Vice President, Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota Enclosure cc: Administrator, Region Ill, USNRC Project Manager, Prairie Island Nuclear Generating Plant, USNRC Resident Inspector, Prairie Island Nuclear Generating Plant, USNRC

Prairie Island Nuclear Generating Plant, Units 1 and 2 -Supplement to the Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report FLOOD HAZARD REEVALUATION REPORT, ADDENDUM In Response to the 50.54(f) Information Request Regarding Recommendation 2.1:

Flooding of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident for the Prairie Island Nuclear Generating Plant, Units 1 and 2 Page 1 of 3

L-PI-16-076 NSPM Enclosure Discussion This addendum updates information in the Flood Hazard Reevaluation Report (FHRR) submitted May 9, 2016 (Reference 1) pertaining to the Local Intense Precipitation (LIP) flooding mechanism. Specifically:

  • three doors that were omitted from Table 2 of the FHRR are included (Doors 420, 423, and 437), along with discussions of the effect of LIP on the doors,
  • results are updated to show the slight impact of changing the lag time used for reach 210 in the hydraulic model (Doors 46, 45, 44, and 73), and
  • Door 164 condition is updated to reflect that the door opening is protected by concrete block wall.

Results of Local Intense Precipitation Table 2 in PINGP's FHRR is replaced with the table below. The maximum predicted flood water elevation could exceed the finished floor elevations at eight door openings.

Of these eight doors, Door 4 7 is not maintained as normally closed while Doors 164 and 437 have installed features that protect the openings from water intrusion.

Table 2- Local Intense Preci itation Flood Levels 237 694.82 694.90 0.08 257 house 694.82 694.90 0.08 258 Screen house 694.82 694.90 0.08 238 Screen house 694.82 694.90 Old Administration Bu 694.82 695.00 0.18 47 694.90 0.27 46 694.90 45 694.90 44 694.90 73 694.90 104 694.90 ** 0.45 100 694.90 ** 0.45 164 694.90 0.34

  • FFE = Finished Floor Elevation
    • No survey FFE point available at the door, closest FFE survey point was used Note: Changes in Table 2 noted in italicized and underlined text.

Page 2 of 3

L-P 1-16-076 NSPM Enclosure The addition of the three doors affects the text in Sections 2.1.3, 2.1 0.1, 2.1 0.2 and 4.0 of Reference 1. The following notes the corrections to the text.

In Section 2.1.3, the first two sentences under the first bullet are updated as follows:

"The maximum predicted flood water elevation could exceed the finished floor elevations at five eight of the 44-17 doors. However, feill.-five of the five-eight doors are normally closed- Doors 100, 102, 104, 420, and 494-423. Doors 164 and 437 have permanently-installed features that will protect the openings from water intrusion: Door 164 has a block wall enclosing it and Door 437 has a design basis flood protection panel installed over the opening."

In Section 2.1 0.1, the first sentence is changed to state:

" ... the LIP flood levels exceed finished floor elevation at fiveeight critical doors ... "

In Section 2.10.2, the sixth through eighth sentences are changed to read:

"However, there are five-six doors that will be subjected to water loading without flood protection that is only installed prior to the PMF event. Doors 4 7, 102, and 104 are designed to withstand 40 psf (due to wind), which bounds the pressure resulting from LIP flood level of 0.45 ft of 28.08 psf. The remaining two dDoors 100 is an and 164 are Overly Blast Doors that are designed to withstand a total static loading in the seated direction of 576 psf and the associated supporting structures are designed to withstand design basis flood levels. Doors 420 and 423 and their associated structures have been analyzed to withstand the hydrostatic forces of the design basis flood. Review of the door analysis is sufficient to conclude there would be no impact as a result of LIP conditions."

In Section 4.0, Reference 15 changes from Revision 0 to Revision 1 for Calculation 180461.51.1005.

==

Conclusions:==

The overall results and conclusions of the FHRR remain unchanged. The LIP flooding mechanism is not bounded by the current design basis for PINGP. An initial evaluation of the LIP mechanism has found that no interim actions are deemed necessary in response to the reevaluated flood hazard.

References:

1. NSPM Letter L-PI-16-039 from S. Northard to Document Control Desk (NRC),

"Prairie Island Nuclear Generating Plant, Units 1 and 2, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report," dated May 9, 2016 (ADAMS Accession No. ML16133A030)

Page 3 of 3