{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 10, 2018 LICENSEES:         Entergy Nuclear Operations, Inc.
FACILITIES:  
FACILITIES:         Palisades Nuclear Plant


==SUBJECT:==
==SUBJECT:==
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 10, 2018 Entergy Nuclear Operations, Inc. Palisades Nuclear Plant


==SUMMARY==
==SUMMARY==
OF JANUARY 4, 2018, PUBLIC TELECONFERENCE MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC., REGARDING REQUEST TO EXTEND ENFORCEMENT DISCRETION FOR GENERATED MISSILE NON-CONFORMANCES AT PALISADES NUCLEAR PLANT (EPID L-2017-LLL-0037)
OF JANUARY 4, 2018, PUBLIC TELECONFERENCE MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC., REGARDING REQUEST TO EXTEND ENFORCEMENT DISCRETION FOR TORNADO-GENERATED MISSILE NON-CONFORMANCES AT PALISADES NUCLEAR PLANT (EPID L-2017-LLL-0037)
On January 4, 2018, a Category 1 public teleconference meeting was held between the U.S. Nuclear Regulatory Commission (NRG) staff and representatives of Entergy Nuclear Operations, Inc. (ENO or licensee).
On January 4, 2018, a Category 1 public teleconference meeting was held between the U.S.
The purpose of the meeting was to discuss a December 7, 2017, request to extend the enforcement discretion for tornado-generated missile conformances at Palisades Nuclear Plant (PNP). By letter dated December 7, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17341A415), the licensee requested to extend the expiration date for the period of enforcement discretion for tornado-generated missile non-conformances at PNP from June 10, 2018, to June 10, 2020, in accordance with the guidance in Enforcement Guidance Memorandum 2015-002, Revision 1, "Enforcement Discretion for Tornado-Generated Missile Protection Non-Compliance" (ADAMS Accession No. ML16355A286).
Nuclear Regulatory Commission (NRG) staff and representatives of Entergy Nuclear Operations, Inc. (ENO or licensee). The purpose of the meeting was to discuss a December 7, 2017, request to extend the enforcement discretion for tornado-generated missile non-conformances at Palisades Nuclear Plant (PNP).
The NRG staff periormed an initial review of the request and determined that supplemental information regarding prompt and long-term compensatory actions implemented and/or planned in the event of a tornado would be needed. The staff discussed its guidance for compensatory measures and requesting an extension to the discretion period, which is provided in NRG Interim Staff Guidance DSS-ISG-2016-01, "Clarification of Licensee Actions in Receipt of Enforcement Discretion per Enforcement Guidance Memorandum EGM 15-002, 'Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance"' (ADAMS Accession No. ML17128A344).
By letter dated December 7, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17341A415), the licensee requested to extend the expiration date for the period of enforcement discretion for tornado-generated missile non-conformances at PNP from June 10, 2018, to June 10, 2020, in accordance with the guidance in Enforcement Guidance Memorandum 2015-002, Revision 1, "Enforcement Discretion for Tornado-Generated Missile Protection Non-Compliance" (ADAMS Accession No. ML16355A286).
Specifically, Appendix B to DSS-ISG-2016-01 lists six items that should be included in an extension request letter. The staff discussed each of the six items and how ENO addressed the item in its December 7, 2017, letter, and for which items additional details would be needed for the staff to complete its review. For items the NRG staff identified as needing additional information, ENO verbally provided a summary of information that is contained in its Abnormal Operating Procedure (AOP) 38, "Acts of Nature," and in other sources of information.
The NRG staff periormed an initial review of the request and determined that supplemental information regarding prompt and long-term compensatory actions implemented and/or planned in the event of a tornado would be needed. The staff discussed its guidance for compensatory measures and requesting an extension to the discretion period, which is provided in NRG Interim Staff Guidance DSS-ISG-2016-01, "Clarification of Licensee Actions in Receipt of Enforcement Discretion per Enforcement Guidance Memorandum EGM 15-002, 'Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance"' (ADAMS Accession No. ML17128A344). Specifically, Appendix B to DSS-ISG-2016-01 lists six items that should be included in an extension request letter. The staff discussed each of the six items and how ENO addressed the item in its December 7, 2017, letter, and for which items additional details would be needed for the staff to complete its review. For items the NRG staff identified as needing additional information, ENO verbally provided a summary of information that is contained in its Abnormal Operating Procedure (AOP) 38, "Acts of Nature," and in other sources of information.
The NRG staff indicated that the information that ENO had summarized during the teleconference meeting was the type and level of detailed information the NRG staff would need to have docketed so that it could complete its review of the extension request. ENO stated that it plans to submit supplemental information to the NRC in support of its request within 2 weeks of the public teleconference meeting. The public was invited to listen to the meeting and was given an opportunity to communicate with the NRG after the business portion, but before the meeting was adjourned.
The NRG staff indicated that the information that ENO had summarized during the teleconference meeting was the type and level of detailed information the NRG staff would need to have docketed so that it could complete its review of the extension request. ENO stated that it plans to submit supplemental information to the NRC in support of its request within 2 weeks of the public teleconference meeting.
Members of the public attended the teleconference meeting and provided comments to the NRC staff. No regulatory decisions or commitments were made during the meeting. No public meeting feedback comments were received.
 
There were no meeting materials provided by the licensee.
The public was invited to listen to the meeting and was given an opportunity to communicate with the NRG after the business portion, but before the meeting was adjourned. Members of the public attended the teleconference meeting and provided comments to the NRC staff.
No regulatory decisions or commitments were made during the meeting. No public meeting feedback comments were received. There were no meeting materials provided by the licensee.
A list of meeting attendees is enclosed.
A list of meeting attendees is enclosed.
Please direct any inquiries to me at 301-415-1627, or Kimberly.Green@nrc.gov.
Please direct any inquiries to me at 301-415-1627, or Kimberly.Green@nrc.gov.
Docket No. 50-255  
:::::o:~ect Plant Licensing Branch Ill Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255


==Enclosure:==
==Enclosure:==


List of Attendees cc w/encl: Listserv :::::o:~ect Manager Plant Licensing Branch Ill Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF ATTENDEES JANUARY 4, 2018, PUBLIC TELECONFERENCE MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC. PALISADES NUCLEAR PLANT NAME ORGANIZATION Kim Green NRC/NRR/DORL Greg Casto NRC/NRR/DORL James Hickey NRC/NRR/DSS Rob Kuntz NRC/NRR/DORL Eric Duncan NRG/Region Ill Bruce Bartlett NRG/Region Ill Julie Boettcher NRG/Region Ill April Nguyen NRG/Region Ill Jeff Hardy Entergy/Palisades Jim Miksa Entergy/Palisades Jeff Erickson Entergy/Palisades Bob Whi1e Entergy/Palisades Greg Hubers Entergy/Palisades Jeff Voskuil Entergy/Palisades Ken Lowery Southern Nuclear Operating Company Justin Hiller Ameren Missouri Jack Grobe Exelon Generation Company, LLC Christopher Riedl Tennessee Valley Authority Michael Keegan Don't Waste Michigan Kevin Kamps Beyond Nuclear Enclosure 
List of Attendees cc w/encl: Listserv


==SUBJECT:==
LIST OF ATTENDEES JANUARY 4, 2018, PUBLIC TELECONFERENCE MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC.
PALISADES NUCLEAR PLANT NAME                                ORGANIZATION Kim Green                        NRC/NRR/DORL Greg Casto                        NRC/NRR/DORL James Hickey                      NRC/NRR/DSS Rob Kuntz                        NRC/NRR/DORL Eric Duncan                      NRG/Region Ill Bruce Bartlett                    NRG/Region Ill Julie Boettcher                  NRG/Region Ill April Nguyen                      NRG/Region Ill Jeff Hardy                        Entergy/Palisades Jim Miksa                        Entergy/Palisades Jeff Erickson                    Entergy/Palisades Bob Whi1e                        Entergy/Palisades Greg Hubers                      Entergy/Palisades Jeff Voskuil                      Entergy/Palisades Ken Lowery                        Southern Nuclear Operating Company Justin Hiller                    Ameren Missouri Jack Grobe                        Exelon Generation Company, LLC Christopher Riedl                Tennessee Valley Authority Michael Keegan                    Don't Waste Michigan Kevin Kamps                      Beyond Nuclear Enclosure


==SUMMARY==
Meeting Notice ML17353A694 5 umma ML18008A230 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3           NRR/DORL/LPL3/PM NAME KGreen                  SRohrer               DWrona         KGreen DATE    01/09/18           01/09/18             01/09/18      01/10/18}}
OF JANUARY 4, 2018, PUBLIC TELECONFERENCE MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC., REGARDING REQUEST TO EXTEND ENFORCEMENT DISCRETION FOR GENERATED MISSILE NON-CONFORMANCES AT PALISADES NUCLEAR PLANT (EPID L-2017-LLL-0037)
DATED JANUARY 10, 2018 DISTRIBUTION:
PUBLIC PM Reading File RidsACRS_MailCTR Resource RidsNrrDorl Resource RidsNrrDorllpl3 Resource RidsNrrDraAplb Resource RidsNrrLASRohrer Resource RidsNrrPMPalisades Resource RidsRgn3MailCenter Resource ADAMS Accession Nos.: Meeting Notice ML17353A694 5 ML18008A230 umma OFFICE NRR/DORL/LPL3/PM NAME KGreen DATE 01/09/18 TWertz, NRR Tlnverso, EDO GCasto, NRR JHickey, NRR MReisi-Fard, NRR MPatterson, NRR NRR/DORL/LPL3/LA NRR/DORL/LPL3 SRohrer DWrona 01/09/18 01/09/18 OFFICIAL RECORD COPY NRR/DORL/LPL3/PM KGreen 01/10/18}}

Revision as of 06:44, 22 October 2019

01/04/2018 Summary of Public Teleconference Meeting with Entergy Nuclear Operations, Inc., Regarding Request to Extend Enforcement Discretion for Tornado-Generated Missile Non-Conformances at Palisades Nuclear Plant
ML18008A230
Person / Time
Site: Palisades Entergy icon.png
Issue date: 01/10/2018
From: Kimberly Green
Plant Licensing Branch III
To:
Entergy Nuclear Operations
Green K, NRR/DORL/LPL3, 415-1627
References
EPID L-2017-LLL-0037
Download: ML18008A230 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 10, 2018 LICENSEES: Entergy Nuclear Operations, Inc.

FACILITIES: Palisades Nuclear Plant

SUBJECT:

SUMMARY

OF JANUARY 4, 2018, PUBLIC TELECONFERENCE MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC., REGARDING REQUEST TO EXTEND ENFORCEMENT DISCRETION FOR TORNADO-GENERATED MISSILE NON-CONFORMANCES AT PALISADES NUCLEAR PLANT (EPID L-2017-LLL-0037)

On January 4, 2018, a Category 1 public teleconference meeting was held between the U.S.

Nuclear Regulatory Commission (NRG) staff and representatives of Entergy Nuclear Operations, Inc. (ENO or licensee). The purpose of the meeting was to discuss a December 7, 2017, request to extend the enforcement discretion for tornado-generated missile non-conformances at Palisades Nuclear Plant (PNP).

By letter dated December 7, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17341A415), the licensee requested to extend the expiration date for the period of enforcement discretion for tornado-generated missile non-conformances at PNP from June 10, 2018, to June 10, 2020, in accordance with the guidance in Enforcement Guidance Memorandum 2015-002, Revision 1, "Enforcement Discretion for Tornado-Generated Missile Protection Non-Compliance" (ADAMS Accession No. ML16355A286).

The NRG staff periormed an initial review of the request and determined that supplemental information regarding prompt and long-term compensatory actions implemented and/or planned in the event of a tornado would be needed. The staff discussed its guidance for compensatory measures and requesting an extension to the discretion period, which is provided in NRG Interim Staff Guidance DSS-ISG-2016-01, "Clarification of Licensee Actions in Receipt of Enforcement Discretion per Enforcement Guidance Memorandum EGM 15-002, 'Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance"' (ADAMS Accession No. ML17128A344). Specifically, Appendix B to DSS-ISG-2016-01 lists six items that should be included in an extension request letter. The staff discussed each of the six items and how ENO addressed the item in its December 7, 2017, letter, and for which items additional details would be needed for the staff to complete its review. For items the NRG staff identified as needing additional information, ENO verbally provided a summary of information that is contained in its Abnormal Operating Procedure (AOP) 38, "Acts of Nature," and in other sources of information.

The NRG staff indicated that the information that ENO had summarized during the teleconference meeting was the type and level of detailed information the NRG staff would need to have docketed so that it could complete its review of the extension request. ENO stated that it plans to submit supplemental information to the NRC in support of its request within 2 weeks of the public teleconference meeting.

The public was invited to listen to the meeting and was given an opportunity to communicate with the NRG after the business portion, but before the meeting was adjourned. Members of the public attended the teleconference meeting and provided comments to the NRC staff.

No regulatory decisions or commitments were made during the meeting. No public meeting feedback comments were received. There were no meeting materials provided by the licensee.

A list of meeting attendees is enclosed.

Please direct any inquiries to me at 301-415-1627, or Kimberly.Green@nrc.gov.

o:~ect Plant Licensing Branch Ill Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosure:

List of Attendees cc w/encl: Listserv

LIST OF ATTENDEES JANUARY 4, 2018, PUBLIC TELECONFERENCE MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC.

PALISADES NUCLEAR PLANT NAME ORGANIZATION Kim Green NRC/NRR/DORL Greg Casto NRC/NRR/DORL James Hickey NRC/NRR/DSS Rob Kuntz NRC/NRR/DORL Eric Duncan NRG/Region Ill Bruce Bartlett NRG/Region Ill Julie Boettcher NRG/Region Ill April Nguyen NRG/Region Ill Jeff Hardy Entergy/Palisades Jim Miksa Entergy/Palisades Jeff Erickson Entergy/Palisades Bob Whi1e Entergy/Palisades Greg Hubers Entergy/Palisades Jeff Voskuil Entergy/Palisades Ken Lowery Southern Nuclear Operating Company Justin Hiller Ameren Missouri Jack Grobe Exelon Generation Company, LLC Christopher Riedl Tennessee Valley Authority Michael Keegan Don't Waste Michigan Kevin Kamps Beyond Nuclear Enclosure

Meeting Notice ML17353A694 5 umma ML18008A230 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3 NRR/DORL/LPL3/PM NAME KGreen SRohrer DWrona KGreen DATE 01/09/18 01/09/18 01/09/18 01/10/18