ML18036A845: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 10
| page count = 10
}}
}}
See also: [[followed by::IR 05000259/1992024]]


=Text=
=Text=
{{#Wiki_filter:i.A V~@%0 I~i W'''~vl'i'~.I ACCELERATED
{{#Wiki_filter:i.A V~@%0 I~i W'''~vl'i'~.I ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEN (RIDS)CESSION.NBR: 9209040100 DOC.DATE: 92/08/31 NOTARIZED:
DISTRIBUTION
NO DOCKET 0 CIL: 50-259'roens Ferry Nuclear Poeer Station, Unit 1, Tennessee 05000259 , 50-260 Broens FerrM Nuclear Power Stationi Unit 2i Tennessee 05000260 50-296 Broens Ferry Nuclear Power Stationi Unit 3i Tennessee 05000296 AUTH.NAME AUTHOR AFFILIATION ZERINGUEI O.J.Tennessee Valley Authority RECIP.NAME RECIPIENT AFFILIATION R Document Control Branch (Document Control Desk)
DEMONSTRATION
 
SYSTEM REGULATORY
==SUBJECT:==
INFORMATION
Provides respo'nse to 920803 ltr re violations noted fn Insps Rep ts 50-259/92-24'5-260/92-24 5 50-296/'P2-24.
DISTRIBUTION
Corr ec tive actions:mod criteria for corrosion monitors DCN h valve data sheet conta'ining erroneous info corrected.
SYSTEN (RIDS)CESSION.NBR: 9209040100
I DISTRIBUTION CODE: IEDID COPIES RECEIVED: LTR ENCL+SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES: A REC IP IENT ID CODE/NAME HEBDONI F MILLIAMSI J.INTERNAL: ACRB t AEOD/DEIB*EOD/TTC NRR MORISSEAUI D NRR/DLPG/LPEB10 NRR/DREP/PEPBVH NUDOCB-ABSTRACT OGC/HDS3 RGN2 F ILE 01 EXTERNAL: EGZcG/BRYCEI J.H.NSIC COPIES LTTR ENCL 1 1 1 1 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 REC IP IENT ID CODE/NAME ROSSI T.AEOD AEOD/DSP/TPAB DEDRO NRR/DLPQ/LHFBPT NRR/DOEA/OEAB NRR/PMAS/ILRB12.E REG FILE 02 NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 NOTE TO ALL"RIDS RECIPIENTS PLEASE HELI" US TO R" DUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK.ROOM pi-".7 (EXT.504-2065)TO ELIMIINATE YOUR NAME FROM DISTRIBUTION LiSTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 25 ENCL 25 0'
DOC.DATE: 92/08/31 NOTARIZED:
0 Tennessee Valley Authority, Post Office Box 2000, Decatur,'Alabama 35609 O.J.'Ike'eringue Vice President, Browns Ferry Operatfons AUG 3i>99Z U.S.Nuclear Regulatory Commission ATTN: Document Control'Desk Washington, D.C.20555 Gentlemen:
NO DOCKET 0 CIL: 50-259'roens
In the Matter of Tennessee Valley Authority Docket Nos.50-259 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN)-NRC INSPECTION REPORT 50-259, 260, 296/92-24-REPLY TO A NOTICE OF VIOLATION (NOV)This letter provides TVA's reply to the NOV transmitted by letter from B.A.Wilson'ated August 3, 1992.In this letter, NRC cited TVA with a violation for failure to use the correct hydrostatic test pressures to adequately test component welds of a safety system.TVA shares the Staff's concern that a system was tested improperly.
Ferry Nuclear Poeer Station, Unit 1, Tennessee 05000259 , 50-260 Broens FerrM Nuclear Power Stationi Unit 2i Tennessee 05000260 50-296 Broens Ferry Nuclear Power Stationi Unit 3i Tennessee 05000296 AUTH.NAME AUTHOR AFFILIATION
However, TVA notes that although one loop of the Residual Heat Removal system was conservatively declared inoperable, the system was subse'quently confirmed capable of performing its design function.Furthermore, TVA is encouraged that this condition was discovered because plant personnel had a questioning attitude during the performance of their routine activities.
ZERINGUEI O.J.Tennessee Valley Authority RECIP.NAME RECIPIENT AFFILIATION
In this case, a supervisor had identifie'd a problem during the processing of a routine workplan change;In response to that discovery, an engineer initiated a review of other workplans for similar errors.It was during that expanded review that the condition cited in the violation was identified.
R Document Control Branch (Document Control Desk)SUBJECT: Provides respo'nse to 920803 ltr re violations
noted fn Insps Rep ts 50-259/92-24'5-260/92-24
5 50-296/'P2-24.
Corr ec tive actions:mod
criteria for corrosion monitors DCN h valve data sheet conta'ining
erroneous info corrected.
I DISTRIBUTION
CODE: IEDID COPIES RECEIVED: LTR ENCL+SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice
of Violation Response NOTES: A REC IP IENT ID CODE/NAME HEBDONI F MILLIAMSI J.INTERNAL: ACRB t AEOD/DEIB*EOD/TTC NRR MORISSEAUI
D NRR/DLPG/LPEB10
NRR/DREP/PEPBVH
NUDOCB-ABSTRACT
OGC/HDS3 RGN2 F ILE 01 EXTERNAL: EGZcG/BRYCEI
J.H.NSIC COPIES LTTR ENCL 1 1 1 1 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 REC IP IENT ID CODE/NAME ROSSI T.AEOD AEOD/DSP/TPAB
DEDRO NRR/DLPQ/LHFBPT
NRR/DOEA/OEAB
NRR/PMAS/ILRB12.E REG FILE 02 NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 NOTE TO ALL"RIDS RECIPIENTS
PLEASE HELI" US TO R" DUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK.ROOM pi-".7 (EXT.504-2065)TO ELIMIINATE
YOUR NAME FROM DISTRIBUTION
LiSTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 25 ENCL 25  
0'  
0 Tennessee Valley Authority, Post Office Box 2000, Decatur,'Alabama
35609 O.J.'Ike'eringue
Vice President, Browns Ferry Operatfons
AUG 3i>99Z U.S.Nuclear Regulatory
Commission
ATTN: Document Control'Desk
Washington, D.C.20555 Gentlemen:
In the Matter of Tennessee Valley Authority Docket Nos.50-259 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN)-NRC INSPECTION
REPORT 50-259, 260, 296/92-24-REPLY TO A NOTICE OF VIOLATION (NOV)This letter provides TVA's reply to the NOV transmitted
by letter from B.A.Wilson'ated
August 3, 1992.In this letter, NRC cited TVA with a violation for failure to use the correct hydrostatic
test pressures to adequately
test component welds of a safety system.TVA shares the Staff's concern that a system was tested improperly.
However, TVA notes that although one loop of the Residual Heat Removal system was conservatively
declared inoperable, the system was subse'quently
confirmed capable of performing
its design function.Furthermore, TVA is encouraged
that this condition was discovered
because plant personnel had a questioning
attitude during the performance
of their routine activities.
In this case, a supervisor
had identifie'd
a problem during the processing
of a routine workplan change;In response to that discovery, an engineer initiated a review of other workplans for similar errors.It was during that expanded review that the condition cited in the violation was identified.
/1 n P1~pp83f o c()~PPPa5~.
/1 n P1~pp83f o c()~PPPa5~.
6  
6 U.S.Nuclear Regulatory Commission NB 31 1992 TVA's"Reply to the Notice of Violation" (10 CFR 2.201)is contained in the enclosure to this letter.If you have any questions regarding this response, please telephone Raul R.Baron at (205)729-7566.Sincerely, J.Zering e Enclosure cc (Enclosure):
U.S.Nuclear Regulatory
.NRC Resident Inspector Browns Ferry Nuclear Plant Route 12, Box 637 Athens, Alabama 35611 Mr.Thierry M.Ross, Project Manager U.S.Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852'r.B.A.Wilson, Project Chief U.S.Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 0  
Commission
'0 ENCLOSURE Tennessee Valley Authority Browns Ferry Nuclear Plant (BFN)Reply to Notice of Violation (NOV)Inspection Report Number 2-24"During the Nuclear Regulatory Commission (NRC)inspection conducted on June 17-July 17, 1992, a violation of NRC requirements was identified.
NB 31 1992 TVA's"Reply to the Notice of Violation" (10 CFR 2.201)is contained in the enclosure to this letter.If you have any questions regarding this response, please telephone Raul R.Baron at (205)729-7566.Sincerely, J.Zering e Enclosure cc (Enclosure):
In accordance with the'General Statement of Policy and Procedure for NRC Enforcement Actions,'0 CFR Part 2, Appendix C, the violation is listed below: 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings of a type appropriate to the circumstances, and shall be accomplished in accordance with these instructions, procedures, or drawings.Instructions, procedures, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.
.NRC Resident Inspector Browns Ferry Nuclear Plant Route 12, Box 637 Athens, Alabama 35611 Mr.Thierry M.Ross, Project Manager U.S.Nuclear Regulatory
Contrary to the above these requirements were~ot met in that hydrostatic test pressures used after installation of corrosion monitors in the residual heat removal service water (RHRSW)system were incorrect.
Commission
The RHRSW heat exchanger piping components were tested to 185 psi instead of the actual design pressure of 450 psi.This was discovered by the licensee on June 19, 1992, and a limiting condition for operation was entered that resulted in Loop II Containment Cooling Mode of the RHR System being inoperable.
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852'r.B.A.Wilson, Project Chief U.S.Nuclear Regulatory
This condition had existed undetected for 17 days.During that time other activities associated with redundant equipment resulted in plant conditions that required the plant to be placed in a cold shutdown within 24 hours.This is an example of a Severity Level IV Violation (Supplement I)applicable to all three units."
Commission
0 This violation was a result of ineffective procedural contxols.for hydrostatic testing.Hydrostatic testing instruction, Modification Addition Instruction (MAI)4.7A, instructed the user to calculate test pressure based on the design pressure of the RHRSW piping, but did not stipulate where (or from what document)to obtain the design pressure.This latitude resulted in an error made at the design development stage propagating through the design process to installation.
Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323  
In January 1'991, TVA initiated a workplan to install corrosion monitors at various locations in the RHRSW system.The installation was completed and tested on June 4, 1992.This ,installation, which included welding sockolets and acc'ess fittings'f the monitors in place, was hydrostatic tested at the monitors'ampling valves at a design pressure of 185 psig.During subsequent review on a corxosion monitors workplan change, TVA discovered that the system should have been hydrostatically tested at a pressure of 450 psig.'hat is, the corrosion monitor sampling valves were underpressurized when tested.This event occurred when the engineering personnel that generated the RHRSW modification criteria for the corrosion monitors design.change notice (DON)incorrectly listed the system mechanical requirement (i.e., 185 psig instead of 450 psig).This requirement was then transferred to the valve-data sheet as the design pressure.This error led the modification personnel responsible for workplan development to improperly use the erroneous valve data sheet (as opposed to using the latest available configuration control diagram)to calculate the test pressure.The Staff noted in the NOV that during the time of this event other activities associated with redundant equipment resulted in plant conditions which required the plant to be placed in a cold shutdown condition within 24 hours.TVA recognizes that the RHRSW system, as tested, did not-conform to all aspects of the current licensing basis.However, the sockolets and access fittings of the corrosion monitors were visually inspected and penetrant tested, and the system was successfully retested at the corxect design pressuxe.Accordingly, plant conditions did not exist which would have required the plant to be placed in a cold shutdown condition.
0  
t v t k The immediate corrective steps were to retest the corrosion monitor valves at the correct design pressure of 450 psig, (minimum test pressure 562.5 psig, maximum test pressure 596.25 psig).This retest was successfully performed on June 20, 1992.
'0 ENCLOSURE Tennessee Valley Authority Browns Ferry Nuclear Plant (BFN)Reply to Notice of Violation (NOV)Inspection
NAI 4.7A has been revised to clarify which source document is required to determine system design pressures for hydrostatic testing.Also, the modification criteria for the corrosion monitors DCN and the valve data sheet containing the erroneous information were corrected.
Report Number 2-24"During the Nuclear Regulatory
t v t t Xia~tma k t th Both the appropriate engineering and modification personnel have reviewed the incident investigation report for this event.Also, the modifications personnel responsible for using the incorrect test pressure document in the development of the workplan have been counselled.
Commission (NRC)inspection
B v TVA believes that full compliance has been achieved.
conducted on June 17-July 17, 1992, a violation of NRC requirements
0}}
was identified.
In accordance
with the'General Statement of Policy and Procedure for NRC Enforcement
Actions,'0
CFR Part 2, Appendix C, the violation is listed below: 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires that activities
affecting quality shall be prescribed
by documented
instructions, procedures, or drawings of a type appropriate
to the circumstances, and shall be accomplished
in accordance
with these instructions, procedures, or drawings.Instructions, procedures, or drawings shall include appropriate
quantitative
or qualitative
acceptance
criteria for determining
that important activities
have been satisfactorily
accomplished.
Contrary to the above these requirements
were~ot met in that hydrostatic
test pressures used after installation
of corrosion monitors in the residual heat removal service water (RHRSW)system were incorrect.
The RHRSW heat exchanger piping components
were tested to 185 psi instead of the actual design pressure of 450 psi.This was discovered
by the licensee on June 19, 1992, and a limiting condition for operation was entered that resulted in Loop II Containment
Cooling Mode of the RHR System being inoperable.
This condition had existed undetected
for 17 days.During that time other activities
associated
with redundant equipment resulted in plant conditions
that required the plant to be placed in a cold shutdown within 24 hours.This is an example of a Severity Level IV Violation (Supplement
I)applicable
to all three units."  
0  
This violation was a result of ineffective
procedural
contxols.for hydrostatic
testing.Hydrostatic
testing instruction, Modification
Addition Instruction (MAI)4.7A, instructed
the user to calculate test pressure based on the design pressure of the RHRSW piping, but did not stipulate where (or from what document)to obtain the design pressure.This latitude resulted in an error made at the design development
stage propagating
through the design process to installation.
In January 1'991, TVA initiated a workplan to install corrosion monitors at various locations in the RHRSW system.The installation
was completed and tested on June 4, 1992.This ,installation, which included welding sockolets and acc'ess fittings'f
the monitors in place, was hydrostatic
tested at the monitors'ampling
valves at a design pressure of 185 psig.During subsequent
review on a corxosion monitors workplan change, TVA discovered
that the system should have been hydrostatically
tested at a pressure of 450 psig.'hat is, the corrosion monitor sampling valves were underpressurized
when tested.This event occurred when the engineering
personnel that generated the RHRSW modification
criteria for the corrosion monitors design.change notice (DON)incorrectly
listed the system mechanical
requirement (i.e., 185 psig instead of 450 psig).This requirement
was then transferred
to the valve-data sheet as the design pressure.This error led the modification
personnel responsible
for workplan development
to improperly
use the erroneous valve data sheet (as opposed to using the latest available configuration
control diagram)to calculate the test pressure.The Staff noted in the NOV that during the time of this event other activities
associated
with redundant equipment resulted in plant conditions
which required the plant to be placed in a cold shutdown condition within 24 hours.TVA recognizes
that the RHRSW system, as tested, did not-conform to all aspects of the current licensing basis.However, the sockolets and access fittings of the corrosion monitors were visually inspected and penetrant tested, and the system was successfully
retested at the corxect design pressuxe.Accordingly, plant conditions
did not exist which would have required the plant to be placed in a cold shutdown condition.
t v t k The immediate corrective
steps were to retest the corrosion monitor valves at the correct design pressure of 450 psig, (minimum test pressure 562.5 psig, maximum test pressure 596.25 psig).This retest was successfully
performed on June 20, 1992.  
NAI 4.7A has been revised to clarify which source document is required to determine system design pressures for hydrostatic
testing.Also, the modification
criteria for the corrosion monitors DCN and the valve data sheet containing
the erroneous information
were corrected.
t v t t Xia~tma k t th Both the appropriate
engineering
and modification
personnel have reviewed the incident investigation
report for this event.Also, the modifications
personnel responsible
for using the incorrect test pressure document in the development
of the workplan have been counselled.
B v TVA believes that full compliance
has been achieved.  
0
}}

Revision as of 03:12, 17 August 2019

Provides Response to 920803 Ltr Re Violations Noted in Insps Repts 50-259/92-24,05-260/92-24 & 50-296/92-24.Corrective Actions:Mod Criteria for Corrosion Monitors Dcn & Valve Data Sheet Containing Erroneous Info Corrected
ML18036A845
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 08/31/1992
From: Zeringue O
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9209040100
Download: ML18036A845 (10)


Text

i.A V~@%0 I~i W~vl'i'~.I ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEN (RIDS)CESSION.NBR: 9209040100 DOC.DATE: 92/08/31 NOTARIZED:

NO DOCKET 0 CIL: 50-259'roens Ferry Nuclear Poeer Station, Unit 1, Tennessee 05000259 , 50-260 Broens FerrM Nuclear Power Stationi Unit 2i Tennessee 05000260 50-296 Broens Ferry Nuclear Power Stationi Unit 3i Tennessee 05000296 AUTH.NAME AUTHOR AFFILIATION ZERINGUEI O.J.Tennessee Valley Authority RECIP.NAME RECIPIENT AFFILIATION R Document Control Branch (Document Control Desk)

SUBJECT:

Provides respo'nse to 920803 ltr re violations noted fn Insps Rep ts 50-259/92-24'5-260/92-24 5 50-296/'P2-24.

Corr ec tive actions:mod criteria for corrosion monitors DCN h valve data sheet conta'ining erroneous info corrected.

I DISTRIBUTION CODE: IEDID COPIES RECEIVED: LTR ENCL+SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES: A REC IP IENT ID CODE/NAME HEBDONI F MILLIAMSI J.INTERNAL: ACRB t AEOD/DEIB*EOD/TTC NRR MORISSEAUI D NRR/DLPG/LPEB10 NRR/DREP/PEPBVH NUDOCB-ABSTRACT OGC/HDS3 RGN2 F ILE 01 EXTERNAL: EGZcG/BRYCEI J.H.NSIC COPIES LTTR ENCL 1 1 1 1 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 REC IP IENT ID CODE/NAME ROSSI T.AEOD AEOD/DSP/TPAB DEDRO NRR/DLPQ/LHFBPT NRR/DOEA/OEAB NRR/PMAS/ILRB12.E REG FILE 02 NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 NOTE TO ALL"RIDS RECIPIENTS PLEASE HELI" US TO R" DUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK.ROOM pi-".7 (EXT.504-2065)TO ELIMIINATE YOUR NAME FROM DISTRIBUTION LiSTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 25 ENCL 25 0'

0 Tennessee Valley Authority, Post Office Box 2000, Decatur,'Alabama 35609 O.J.'Ike'eringue Vice President, Browns Ferry Operatfons AUG 3i>99Z U.S.Nuclear Regulatory Commission ATTN: Document Control'Desk Washington, D.C.20555 Gentlemen:

In the Matter of Tennessee Valley Authority Docket Nos.50-259 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN)-NRC INSPECTION REPORT 50-259, 260, 296/92-24-REPLY TO A NOTICE OF VIOLATION (NOV)This letter provides TVA's reply to the NOV transmitted by letter from B.A.Wilson'ated August 3, 1992.In this letter, NRC cited TVA with a violation for failure to use the correct hydrostatic test pressures to adequately test component welds of a safety system.TVA shares the Staff's concern that a system was tested improperly.

However, TVA notes that although one loop of the Residual Heat Removal system was conservatively declared inoperable, the system was subse'quently confirmed capable of performing its design function.Furthermore, TVA is encouraged that this condition was discovered because plant personnel had a questioning attitude during the performance of their routine activities.

In this case, a supervisor had identifie'd a problem during the processing of a routine workplan change;In response to that discovery, an engineer initiated a review of other workplans for similar errors.It was during that expanded review that the condition cited in the violation was identified.

/1 n P1~pp83f o c()~PPPa5~.

6 U.S.Nuclear Regulatory Commission NB 31 1992 TVA's"Reply to the Notice of Violation" (10 CFR 2.201)is contained in the enclosure to this letter.If you have any questions regarding this response, please telephone Raul R.Baron at (205)729-7566.Sincerely, J.Zering e Enclosure cc (Enclosure):

.NRC Resident Inspector Browns Ferry Nuclear Plant Route 12, Box 637 Athens, Alabama 35611 Mr.Thierry M.Ross, Project Manager U.S.Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852'r.B.A.Wilson, Project Chief U.S.Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 0

'0 ENCLOSURE Tennessee Valley Authority Browns Ferry Nuclear Plant (BFN)Reply to Notice of Violation (NOV)Inspection Report Number 2-24"During the Nuclear Regulatory Commission (NRC)inspection conducted on June 17-July 17, 1992, a violation of NRC requirements was identified.

In accordance with the'General Statement of Policy and Procedure for NRC Enforcement Actions,'0 CFR Part 2, Appendix C, the violation is listed below: 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings of a type appropriate to the circumstances, and shall be accomplished in accordance with these instructions, procedures, or drawings.Instructions, procedures, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

Contrary to the above these requirements were~ot met in that hydrostatic test pressures used after installation of corrosion monitors in the residual heat removal service water (RHRSW)system were incorrect.

The RHRSW heat exchanger piping components were tested to 185 psi instead of the actual design pressure of 450 psi.This was discovered by the licensee on June 19, 1992, and a limiting condition for operation was entered that resulted in Loop II Containment Cooling Mode of the RHR System being inoperable.

This condition had existed undetected for 17 days.During that time other activities associated with redundant equipment resulted in plant conditions that required the plant to be placed in a cold shutdown within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.This is an example of a Severity Level IV Violation (Supplement I)applicable to all three units."

0 This violation was a result of ineffective procedural contxols.for hydrostatic testing.Hydrostatic testing instruction, Modification Addition Instruction (MAI)4.7A, instructed the user to calculate test pressure based on the design pressure of the RHRSW piping, but did not stipulate where (or from what document)to obtain the design pressure.This latitude resulted in an error made at the design development stage propagating through the design process to installation.

In January 1'991, TVA initiated a workplan to install corrosion monitors at various locations in the RHRSW system.The installation was completed and tested on June 4, 1992.This ,installation, which included welding sockolets and acc'ess fittings'f the monitors in place, was hydrostatic tested at the monitors'ampling valves at a design pressure of 185 psig.During subsequent review on a corxosion monitors workplan change, TVA discovered that the system should have been hydrostatically tested at a pressure of 450 psig.'hat is, the corrosion monitor sampling valves were underpressurized when tested.This event occurred when the engineering personnel that generated the RHRSW modification criteria for the corrosion monitors design.change notice (DON)incorrectly listed the system mechanical requirement (i.e., 185 psig instead of 450 psig).This requirement was then transferred to the valve-data sheet as the design pressure.This error led the modification personnel responsible for workplan development to improperly use the erroneous valve data sheet (as opposed to using the latest available configuration control diagram)to calculate the test pressure.The Staff noted in the NOV that during the time of this event other activities associated with redundant equipment resulted in plant conditions which required the plant to be placed in a cold shutdown condition within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.TVA recognizes that the RHRSW system, as tested, did not-conform to all aspects of the current licensing basis.However, the sockolets and access fittings of the corrosion monitors were visually inspected and penetrant tested, and the system was successfully retested at the corxect design pressuxe.Accordingly, plant conditions did not exist which would have required the plant to be placed in a cold shutdown condition.

t v t k The immediate corrective steps were to retest the corrosion monitor valves at the correct design pressure of 450 psig, (minimum test pressure 562.5 psig, maximum test pressure 596.25 psig).This retest was successfully performed on June 20, 1992.

NAI 4.7A has been revised to clarify which source document is required to determine system design pressures for hydrostatic testing.Also, the modification criteria for the corrosion monitors DCN and the valve data sheet containing the erroneous information were corrected.

t v t t Xia~tma k t th Both the appropriate engineering and modification personnel have reviewed the incident investigation report for this event.Also, the modifications personnel responsible for using the incorrect test pressure document in the development of the workplan have been counselled.

B v TVA believes that full compliance has been achieved.

0