Line 3: |
Line 3: |
| | issue date = 06/05/2012 | | | issue date = 06/05/2012 |
| | title = Emergency Preparedness Information Requested by NRC Letter, Request for Information Pursuant to 10 CFR 50.54(f) Re Recommendation 2.1, 2.3 and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident. | | | title = Emergency Preparedness Information Requested by NRC Letter, Request for Information Pursuant to 10 CFR 50.54(f) Re Recommendation 2.1, 2.3 and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident. |
| | author name = Reasoner C O | | | author name = Reasoner C |
| | author affiliation = Ameren Missouri, Union Electric Co | | | author affiliation = Ameren Missouri, Union Electric Co |
| | addressee name = | | | addressee name = |
|
---|
Category:Letter type:ULNRC
MONTHYEARULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds ULNRC-06844, Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification2023-12-0707 December 2023 Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification ULNRC-06827, Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2023-11-20020 November 2023 Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) ULNRC-06824, Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A2023-08-17017 August 2023 Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A ULNRC-06830, Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak2023-08-15015 August 2023 Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak ULNRC-06223, Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004)2023-07-25025 July 2023 Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004) ULNRC-06799, Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications2023-07-13013 July 2023 Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications ULNRC-06821, Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301)2023-06-21021 June 2023 Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301) ULNRC-06822, Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a2023-06-14014 June 2023 Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a ULNRC-06815, Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a2023-06-0505 June 2023 Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a ULNRC-06818, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate .2023-06-0505 June 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate . ULNRC-06816, Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015)2023-05-0909 May 2023 Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015) ULNRC-06812, Submittal of 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 Submittal of 2022 Annual Radiological Environmental Operating Report ULNRC-06806, Submittal of Radiological Emergency Response Plan, Revision 552023-04-12012 April 2023 Submittal of Radiological Emergency Response Plan, Revision 55 ULNRC-06807, Submittal of Single Positive Test Forms2023-04-0303 April 2023 Submittal of Single Positive Test Forms ULNRC-06798, Submittal of Status of Plant Decommissioning Funding and ISFSI Decommissioning Funding Plan2023-03-30030 March 2023 Submittal of Status of Plant Decommissioning Funding and ISFSI Decommissioning Funding Plan ULNRC-06801, CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions2023-03-30030 March 2023 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06804, Submittal of Nuclear Property Insurance Reporting2023-03-29029 March 2023 Submittal of Nuclear Property Insurance Reporting ULNRC-06751, Application to Revise Technical Specifications to Adopt TSTF-501-A, Rev. 1, Relocate Stored Oil & Lube Oil Volume Values to Licensee Control2023-03-29029 March 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Rev. 1, Relocate Stored Oil & Lube Oil Volume Values to Licensee Control ULNRC-06803, Submittal of Response to Request for Additional Information Regarding Results of Steam Generator Tube In-Service Inspection2023-03-29029 March 2023 Submittal of Response to Request for Additional Information Regarding Results of Steam Generator Tube In-Service Inspection ULNRC-06805, Transmittal of Special Report 2023-02 Non-Functionality of Containment Hydrogen Analyzer Channel for Greater than 30 Days2023-03-21021 March 2023 Transmittal of Special Report 2023-02 Non-Functionality of Containment Hydrogen Analyzer Channel for Greater than 30 Days ULNRC-06802, Special Report 2023-01 (PAM Report); Non-Functionality of a Post-Accident Monitoring Instrument2023-03-0909 March 2023 Special Report 2023-01 (PAM Report); Non-Functionality of a Post-Accident Monitoring Instrument ULNRC-06795, Submittal of Fitness for Duty Reports for 2022, Including Single Positive Test Forms2023-01-24024 January 2023 Submittal of Fitness for Duty Reports for 2022, Including Single Positive Test Forms ULNRC-06794, Submittal of Fitness for Duty Program Data for 20222023-01-24024 January 2023 Submittal of Fitness for Duty Program Data for 2022 ULNRC-06787, Response to Request for Additional Information Regarding License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications (LDCN 21-0015)2022-12-0808 December 2022 Response to Request for Additional Information Regarding License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications (LDCN 21-0015) ULNRC-06781, License Amendment Request to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2022-12-0101 December 2022 License Amendment Request to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) ULNRC-06780, Additional Supplement to License Amendment Request to Adopt TSTF-439 and TSTF-505, LDCN 20-0072022-11-30030 November 2022 Additional Supplement to License Amendment Request to Adopt TSTF-439 and TSTF-505, LDCN 20-007 ULNRC-06772, 10 CFR 50.59 and 10 CFR 72.48 Summary Report2022-11-23023 November 2022 10 CFR 50.59 and 10 CFR 72.48 Summary Report ULNRC-06777, Operating Quality Assurance Manual (Oqam) Revision 362022-11-16016 November 2022 Operating Quality Assurance Manual (Oqam) Revision 36 ULNRC-06779, ULNRC-06779: Contesting of Green NCV 05000483/2022010-03, Failure to Perform Required Inservice Testing of Residual Heat Removal Heat Exchanger Pneumatically (Air) Operated Outlet and Bypass Valves2022-11-14014 November 2022 ULNRC-06779: Contesting of Green NCV 05000483/2022010-03, Failure to Perform Required Inservice Testing of Residual Heat Removal Heat Exchanger Pneumatically (Air) Operated Outlet and Bypass Valves ULNRC-06765, License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Testing Frequencies (LDCN 2020-0004)2022-11-0303 November 2022 License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Testing Frequencies (LDCN 2020-0004) ULNRC-06773, Results of Steam Generator Tube In-Service Inspection2022-11-0101 November 2022 Results of Steam Generator Tube In-Service Inspection ULNRC-06775, Submittal of Non-Functionality of Loose-Part Detection System Channel for Greater than 30 Days2022-10-27027 October 2022 Submittal of Non-Functionality of Loose-Part Detection System Channel for Greater than 30 Days ULNRC-06771, Correction to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections (LDCN 21-0013)2022-10-25025 October 2022 Correction to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections (LDCN 21-0013) ULNRC-06770, Cycle 25 Commitment Change Summary Report2022-10-19019 October 2022 Cycle 25 Commitment Change Summary Report ULNRC-06766, Correction of Text Contained in Enclosures Provided with Supplements to Request for License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address GSI-191 and Respond to GL 2004-02 (LDCN 19-0014)2022-09-0808 September 2022 Correction of Text Contained in Enclosures Provided with Supplements to Request for License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address GSI-191 and Respond to GL 2004-02 (LDCN 19-0014) ULNRC-06767, Presentation Information for Pre-Application Meeting Regarding New License Amendment Request for Use of Framatome Fuel Assemblies2022-09-0606 September 2022 Presentation Information for Pre-Application Meeting Regarding New License Amendment Request for Use of Framatome Fuel Assemblies ULNRC-06764, Revised Response to Request for Additional Information Regarding License Amendment Request for Adoption Off Alternate Source Term and Revision of Technical Specifications (LDCN 21-0015)2022-09-0101 September 2022 Revised Response to Request for Additional Information Regarding License Amendment Request for Adoption Off Alternate Source Term and Revision of Technical Specifications (LDCN 21-0015) ULNRC-06763, Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspection (LDCN 21-0013)2022-09-0101 September 2022 Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspection (LDCN 21-0013) ULNRC-06762, Submittal of Owner'S Activity Reports (OAR-1 Forms) for Cycle/Refuel 252022-08-25025 August 2022 Submittal of Owner'S Activity Reports (OAR-1 Forms) for Cycle/Refuel 25 ULNRC-06758, Union Electric Co. - Renewed Facility Operating License NPF-30, Withdrawal of License Amendment Request and Exemption Request Regarding Transition to Framatome Fuel (LDCN 22-0002)2022-08-0404 August 2022 Union Electric Co. - Renewed Facility Operating License NPF-30, Withdrawal of License Amendment Request and Exemption Request Regarding Transition to Framatome Fuel (LDCN 22-0002) ULNRC-06755, Response to Requests for Additional Information for Proposed Revision to Radiological Emergency Response Plan Regarding Response and Notification Goals2022-07-13013 July 2022 Response to Requests for Additional Information for Proposed Revision to Radiological Emergency Response Plan Regarding Response and Notification Goals ULNRC-06754, Response to Request for Additional Information Regarding Licensee Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications2022-07-0505 July 2022 Response to Request for Additional Information Regarding Licensee Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications ULNRC-06739, Post-Audit Supplement to License Amendment Request to Adopt TSTF-439 and TSTF-505 (LDCN 20-0007)2022-06-30030 June 2022 Post-Audit Supplement to License Amendment Request to Adopt TSTF-439 and TSTF-505 (LDCN 20-0007) ULNRC-06752, Evacuation Time Estimates Report2022-06-27027 June 2022 Evacuation Time Estimates Report ULNRC-06753, Presentation Information for Pre-Submittal Meeting Regarding Updated Spent Fuel Criticality Safety Analysis2022-06-23023 June 2022 Presentation Information for Pre-Submittal Meeting Regarding Updated Spent Fuel Criticality Safety Analysis ULNRC-06750, Submittal of Cycle 26 Core Operating Limits Report (COLR)2022-06-13013 June 2022 Submittal of Cycle 26 Core Operating Limits Report (COLR) ULNRC-06735, Response to Request for Additional Information Regarding Request for License Amendment and Regulatory Exemptions for Risk-Informed Approach to Address GSI-191 and Respond to Generic Letter 2004-02 (LDCN 19-0014).2022-05-27027 May 2022 Response to Request for Additional Information Regarding Request for License Amendment and Regulatory Exemptions for Risk-Informed Approach to Address GSI-191 and Respond to Generic Letter 2004-02 (LDCN 19-0014). 2024-01-29
[Table view] |
Text
WAmeren MISSOURI June 5, 2012 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Ladies and Gentlemen:
ULNRC-05868 10 CFR 50.54(+/-) DOCKET NUMBER 50-483 CALLA WAY PLANT UNIT 1 UNION ELECTRIC CO. Callaway Plant FACILITY OPERATING LICENSE NPF-30 EMERGENCY PREPAREDNESS INFORMATION REQUESTED BY NRC LETTER, "REQUEST FOR INFORMATION PURSUANT TO 10 CFR 50.54(f) REGARDING RECOMMENDATIONS 2.1, 2.3 AND 9.3, OF THE NEAR-TERM TASK FORCE REVIEW OF INSIGHTS FROM THE FUKUSHIMA DAI-ICID ACCIDENT"
References:
- 1. NRC letter, "Request for Information Pursuant to Title 10 of the Code ofFederal Regulations 50.54(+/-) Regarding Recommendations 2.1, 2.3, and 9.3, ofthe Near-Term Task Force Review oflnsights from the Fukushima Dai-Ichi Accident," dated March 12, 2012 2. ULNRC-05862, Arneren Missouri 60-Day Response to NRC Letter, " Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(+/-) Regarding Recommendations 2.1, 2.3, and 9.3, ofthe Near-Term Task Force Review oflnsights from the Fukushima Dai-Ichi Accident," dated May 10, 2012 On March 12, 2012, the NRC staff issued the referenced letter (Reference 1). Enclosure 5 ofthat letter contains specific Requested Actions and Requested Information associated with Recommendation
- 9. 3 for Emergency Preparedness (EP) programs.
In accordance with 10 CFR 50.54, "Conditions of licenses," paragraph (f), addressees were requested to submit a written response to the information requests.
The NRC letter also provided requested due dates for written responses.
PO Box 620 Fulton, MD 65251 AmerenMissouri.com ULNRC-05868 June 5, 2012 Page 2 of4 In accordance with the NRC letter, on May 10, 2012, Ameren Missouri submitted an alternative course of action (Reference
- 2) for providing the requested information.
The alternative course of action included revised information, due dates, and the basis for those dates. As described in the alternative course of action, Attachment 1 to this letter transmits the responses to the following information requests from the March 12, 2012 NRC letter: Enclosure 5, Communications Request 2 and Staffing Requests 3, 4 and 5. Attachment 2 contains the regulatory commitments associated with this response.
If you have any questions concerning the content of this letter, please contact Scott Maglio, Regulatory Affairs Manager, at 573-676-8719.
I declare under penalty of perjury that the foregoing is true and correct. Executed on: SJM/nls ----------------
Cleveland
- 0. Reasoner Vice President, Engineering Attachment 1: Ameren Missouri's 90-Day Response to Request for Information Pursuant to 10 CFR 50.54(t) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Attachment 2: List of Commitments ULNRC-05868 June 5, 2012 Page 3 of4 cc: Mr. Elmo E. Collins Regional Administrator U. S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Andrew Hon Senior Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-8G 14 Washington, DC 20555-2738 Mr. Eric J. Leeds Director, Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-13H16M Washington, DC 20555-0001 ULNRC-05868 June 5, 2012 Page 4 of4 Index and send hardcopy to QA File A160.0761 Hardcopy:
Certrec Corporation 4150 International Plaza Suite 820 Fort Worth, TX 76109 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)
Electronic distribution for the following can be made via Responses and Reports ULNRC Distribution:
A. C. Heflin F. M. Diya C. 0. Reasoner III D. W. Neterer L. H. Graessle J. T. Patterson S.M. Maglio T. B. Elwood S. J. Meyer J. L. Fortman P. J. McKenna R. Holmes-Bobo NSRB Secretary Mr. Paul Parmenter, Director (SEMA) Mr. Thomas Mohr, Senior REP Planner (SEMA) Mr. Tom Masso, REP Planner (SEMA) Mr. Bill Muilenburg (WCNOC) Mr. Tim Hope (Luminant Power) Mr. Ron Barnes (APS) Mr. Tom Baldwin (PG&E) Mr. Mike Murray (STPNOC) Ms. Linda Conklin (SCE) Mr. John O'Neill (Pillsbury Winthrop Shaw Pittman LLP) Mr. Dru Buntin (DNR)
Attachment 1 to ULNRC-05868 Page 1 of3 ATTACHMENT 1 Ameren Missouri's 90-Day Response to Request for Information Pursuant to 10 CFR 50.54(t) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Communications Request #2-Describe any interim actions that have been taken or are planned to be taken to enhance existing communications systems power supplies until the communications assessment and the resulting actions are complete.
Actions Taken or Planned Estimated Completion Date 1. Callaway has obtained three portable diesel generators for use at the Complete Control Room, Technical Support Center (TSC) and Emergency Offsite Facility (EOF). These generators can be used to provide power to satellite phone and radio battery chargers.
- 2. Callaway has issued a purchase order for a portable radio cart with 9/1/2012 -Radio antenna tower and on-board diesel generator.
The cart will be cart on-site. equipped with chargers for radio batteries.
The plant passive antenna system in the power block will be modified for direct 10/4/2014-connection to the cart to enhance in-plant communication capability.
Passive antenna system modified for radio cart connection.
- 3. Callaway has obtained 15 new satellite phones. Four ofthese 7/31/2012-phones will be placed in the four counties within the Callaway Satellite phones Emergency Planning Zone (EPZ). The remaining phones will be distributed to 4 available for use by Field Monitoring Teams (FMT), the Control counties and Room, TSC, and EOF. External antennas will be installed at the remammg Control Room, TSC, and EOF to support satellite phone phones available communications.
These phones utilize a battery power source that for FMTs, TSC, increases the overall diversity of communication power supplies.
andEOF. 10/4/2014-External antennas installed.
Attachment 1 to ULNRC-05868 Page 2 of3 Staffing Request #3-Identify how the augmented staff would be notified given degraded communications capabilities.
Actions Taken or Planned Estimated Completion Date 1. All ERO members will automatically respond to their assigned 7/31/2012-facilities or a designated staging area when they become aware of Communication a need to augment staffing (e.g. by direct observation, media issued to ERO reports, word-of-mouth, etc.). A communication to ERO members. members will be made to informally implement this change and Emergency Implementing Procedures (EIP) will be revised. 12/31/2012-Procedure revisions complete.
Request #4-Identify the methods of access (e.g., roadways, navigable bodies of water and dockage, airlift, etc.) to the site that are expected to be available qfter a widespread large scale natural event. Actions Taken or Planned Estimated Completion Date 1. Callaway has multiple roadways providing access to the site. Complete a. State maintained general area access I. From the NE, I-70 to State (St) Road (Rd) D to St. Rd. 0 to St. Rd. CC 11. From the SE, M0-94 to St. Rd. D to St. Rd. 0 to St. Rd.CC ... From the SW, US-54 to M0-94 to St. Rd. CC 111. IV. From the NW, I-70 to US-54 to St. Rd. 0 to St. Rd. CC b. County maintained local access 1. From the north, County (Co) Rd. 448 11. From the east, Co. Rd. 448 111. From the south, Co. Rd. 459 IV. From the west, Co. Rd. 428 2. There are four counties in the Callaway EPZ. County road and Complete bridg_e departments provide representatives to the county Attachment 1 to ULNRC-05868 Page 3 of3 Operations Centers (EOC) in support of their county emergency response plans. Requests for prioritized road clearing would be made through the respective EOC as required.
- 3. Callaway is located approximately five miles north ofthe Missouri River. The plant owns an intake structure and barge unloading facility on the river which are available to offload personnel by boat. In addition, there are river access points located southeast of the plant at Portland, MO and southwest of the plant at Mokane, MO. Under the letter of agreement with the state of Missouri, the state Water Patrol and/or Department of Conservation could be directed to provide waterborne transportation as required.
- 4. The Missouri Air National Guard has a base at the Jefferson City, MO airport, 23 miles southwest ofthe plant. This organization is equipped with helicopters and is routinely utilized in response to natural disasters.
As the governor's agent, the Senior Radiological Emergency Planner (REP) at the State Emergency Management Agency (SEMA) can request support from the Air National Guard. Complete Complete Request #5 -Identify any interim actions that have been taken or are planned prior to the completion of the staffing assessment.
Actions Taken or Planned Estimated Completion Date None NA Attachment 2 to ULNRC-05868 Page 1 of2 ATTACHMENT2 List of Commitments The following table identifies those actions committed to by Ameren Missouri in Attachment 1 of this document.
Any other statements in this document are provided for information purposes and are not considered commitments.
Please direct questions regarding these commitments to Scott Maglio at 573-676-8719.
COMMITMENTS-Communications Request 2 Due Date/Event Commitment (Numbers listed below correspond to Action Number Numbers in Attachment 1 for Communications)
- 2. Callaway will have on-site a portable radio cart 911/2012 50220 with antenna tower and on-board diesel generator.
The cart will be equipped with chargers for radio batteries.
- 2. The plant passive antenna system in the power 10/4/2014 50225 block will be modified for direct connection to the portable radio cart to enhance in-plant communication capability.
- 3. Satellite phones will be placed in the four counties 7/31/2012 50221 within the Callaway Emergency Planning Zone (EPZ) and the remaining phones will be available for use by Field Monitoring Teams (FMT), the Control Room, Technical Support Center (TSC), and Emergency Offsite Facility (EOF). 3. External antennas will be installed in the Control 10/4/2014 50222 Room, TSC, and EOF to support satellite phone communications.
Attachment 2 to ULNRC-05868 Page 2 of2 COMMITMENTS-Staffing Request 3 (Numbers listed below correspond to Action Numbers in Attachment 1 for Staffing)
- 1. A communication will be made to ERO members informing them that they should automatically respond to their assigned facilities or a designated staging area when they become aware of a need to augment (e.g. by direct observation, media reports, word-of-mouth, etc.). 1. Emergency Implementing Procedures will be revised to implement the change that ERO members should automatically respond to their assigned facilities or a designated staging area when they become aware of a need to augment (e.g. by direct observation, media reports, word-of-mouth, etc). Due Date/Event Commitment Number 7/31/2012 50223 12/31/2012 50224