NRC 2013-0102, Completion of the Calculation Project Implementation Commitment: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 19: Line 19:


==Reference:==
==Reference:==
( 1) NextEra Energy Point Beach, LLC letter to NRC, dated April 17, 2012, Clarification to the Calculation Project Implementation Commitment Change (ML 12109A078)
( 1) NextEra Energy Point Beach, LLC letter to NRC, dated April 17, 2012, Clarification to the Calculation Project Implementation Commitment Change (ML12109A078)
Via Reference (1 ), NextEra Energy Point Beach, LLC (NextEra) committed to implementing 22 safety-related calculations that were completed during the course of the calculation review and reconstitution project related to the EOPs. NextEra committed to an implementation date of September 30, 2013. Associated documents (e.g., procedures, design and licensing basis documents) were identified for each calculation in accordance with site procedures.
Via Reference (1 ), NextEra Energy Point Beach, LLC (NextEra) committed to implementing 22 safety-related calculations that were completed during the course of the calculation review and reconstitution project related to the EOPs. NextEra committed to an implementation date of September 30, 2013. Associated documents (e.g., procedures, design and licensing basis documents) were identified for each calculation in accordance with site procedures.
Document revisions that were considered a condition adverse to quality were completed by September 30, 2013. Implementation of the final 22 safety-related calculations committed to in reference (1) is complete.
Document revisions that were considered a condition adverse to quality were completed by September 30, 2013. Implementation of the final 22 safety-related calculations committed to in reference (1) is complete.
Very truly yours, NextEra Energy Point Beach, LLC Larry ey_ Site
Very truly yours, NextEra Energy Point Beach, LLC Larry ey_ Site
* President cc: Administrator, Region Ill, USNRC NRC Project Manager, Point Beach Nuclear Plant , USNRC NRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241}}
* President cc: Administrator, Region Ill, USNRC NRC Project Manager, Point Beach Nuclear Plant , USNRC NRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241}}

Revision as of 21:07, 21 June 2019

Completion of the Calculation Project Implementation Commitment
ML13304A728
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 10/30/2013
From: Meyer L
Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2013-0102
Download: ML13304A728 (1)


Text

NEXT era October 30, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Completion of the Calculation Project Implementation Commitment POINT BEACH NRC 2013-0102

Reference:

( 1) NextEra Energy Point Beach, LLC letter to NRC, dated April 17, 2012, Clarification to the Calculation Project Implementation Commitment Change (ML12109A078)

Via Reference (1 ), NextEra Energy Point Beach, LLC (NextEra) committed to implementing 22 safety-related calculations that were completed during the course of the calculation review and reconstitution project related to the EOPs. NextEra committed to an implementation date of September 30, 2013. Associated documents (e.g., procedures, design and licensing basis documents) were identified for each calculation in accordance with site procedures.

Document revisions that were considered a condition adverse to quality were completed by September 30, 2013. Implementation of the final 22 safety-related calculations committed to in reference (1) is complete.

Very truly yours, NextEra Energy Point Beach, LLC Larry ey_ Site

  • President cc: Administrator, Region Ill, USNRC NRC Project Manager, Point Beach Nuclear Plant , USNRC NRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241