April 17, 2012 EY -

POINT BEACH NRC 2012-0025 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Calculation Proiect lm~lementationCommitment Change

References:

(1) NextEra Energy Point Beach, LLC letter to NRC, dated September 21, 2011, Calculation Project Schedule Update (MLI 12650313)

Via Reference (I), NextEra Energy Point Beach, LLC (NextEra) committed to implementing 163 safety-related calculations completed during the course of the calculation review and reconstitution project by September 30, 2012. lmplementation of 141 of the 163 safety-related calculations will be completed by the committed date of September 30, 2012. NextEra has determined that additional time is required to implement the remaining 22 safety-related calculations. lmplementation of the remaining calculations into Emergency Operating Procedures (EOPs) will coincide with NextEra's implementation of the Westinghouse Owners Group Emergency Response Guidelines (ERG), Revision 2A guidance.

Annual Operating Exams and Biennial Written Exams will take place at Point Beach Nuclear Plant (PBNP) during the Summer and Fall of 2012 on the current EOPs. To provide sufficient time to update procedures and provide training, implementation of the revised EOPs, including the remaining 22 safety-related calculations and the ERG, Revision 2A guidance, will begin following these 2012 examination periods. Licensed operator training classes for the revised EOPs are scheduled for Spring and Summer of 2013. Therefore, full implementation of the remaining 22 safety-related calculations and the ERG, Revision 2A guidance will occur by September 30, 2013.

Summarv of Reaulatorv Commitments:

The Regulatory Commitment contained in Reference (1) states:

lmplementation of the 163 safety-related calculations completed during the course of the calculation review and reconstitution project will be completed by September 30, 2012.

NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

Document Control Desk Page 2 NextEra is modifying this Regulatory Commitment to state:

lmplementation of 141 safety-related calculations completed during the course of the calculation review and reconstitution project and not related to the EOPs will be completed by September 30, 2012.

NextEra is also adding a Regulatory Commitment to state:

lmplementation of the 22 safety-related calculations completed during the course of the calculation review and reconstitution project related to the EOPs will be completed by September 30, 2013.

Very truly yours, NextEra Energy Point Beach, LLC W s i t e Vice President cc: Administrator, Region Ill, USNRC NRC Project Manager, Point Beach Nuclear Plant, USNRC NRC Resident Inspector, Point Beach Nuclear Plant, USNRC