| | issue date = 12/22/2005 | | | issue date = 12/22/2005 |
| | title = RAI, Fire Protection Exemption from Automatic Fire Suppression and Detection Requirements | | | title = RAI, Fire Protection Exemption from Automatic Fire Suppression and Detection Requirements |
| | author name = Moroney B T | | | author name = Moroney B |
| | author affiliation = NRC/NRR/ADRO/DORL/LPLD | | | author affiliation = NRC/NRR/ADRO/DORL/LPLD |
| | addressee name = Stall J A | | | addressee name = Stall J |
| | addressee affiliation = Florida Power & Light Co | | | addressee affiliation = Florida Power & Light Co |
| | docket = 05000250, 05000251 | | | docket = 05000250, 05000251 |
| | license number = DPR-031, DPR-041 | | | license number = DPR-031, DPR-041 |
| | contact person = Moroney B T, NRR/DLPM, 415-3974 | | | contact person = Moroney B, NRR/DLPM, 415-3974 |
| | case reference number = TAC MC5542, TAC MC5543 | | | case reference number = TAC MC5542, TAC MC5543 |
| | document type = Letter, Request for Additional Information (RAI) | | | document type = Letter, Request for Additional Information (RAI) |
Letter Sequence RAI |
---|
|
|
MONTHYEARML0506801972005-04-0707 April 2005 Results of Acceptance Regarding Request from 10 CFR Part 50 Appendix R, Section III.G.3. (MC5542 and MC5543) (L-2004-176) Project stage: Other ML0534800302005-12-22022 December 2005 RAI, Fire Protection Exemption from Automatic Fire Suppression and Detection Requirements Project stage: RAI ML0621604222006-09-20020 September 2006 Environmental Assessment, Exempt Licensee from Requirements of 10 CFR Part 50, Appendix R, Subsection III.g.3 for Fixed Suppression in Mechanical Equipment Room & for Detection & Fixed Suppression in Subsection of Control Building Project stage: Other ML0621603872006-09-27027 September 2006 Exemption from the Requirements of 10 CFR 50, Appendix R Project stage: Approval 2005-04-07
[Table View] |
|
---|
Category:Letter
MONTHYEARL-2024-184, Radiological Emergency Plan Revision 772024-11-0505 November 2024 Radiological Emergency Plan Revision 77 L-2024-173, Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-31031 October 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-175, Cycle 34 Core Operating Report2024-10-24024 October 2024 Cycle 34 Core Operating Report ML24291A2882024-10-24024 October 2024 Westinghouse Topical Report - Request for Withholding Information from Public Disclosure L-2024-177, Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis2024-10-22022 October 2024 Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24276A2302024-10-16016 October 2024 Westinghouse Topical Report – Request for Withholding Information from Public Disclosure L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes ML24289A2372024-10-15015 October 2024 Transmittal of Revision 1 Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles IR 05000250/20243012024-10-0303 October 2024 NRC Operator License Examination Report 05000250/2024301 and 05000251/2024301 L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24269A1292024-09-24024 September 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24260A2262024-09-18018 September 2024 NRC Examination Results Summary - Examination Reports: 05000250/2024301 and 05000251/2024301 ML24262A2272024-09-18018 September 2024 Transmittal of Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles ML24158A0052024-09-17017 September 2024 Completion of Subsequent License Renewal Site Specific Environmental Review and Modification to Subsequent Renewed Facility Operating Licenses L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24207A0342024-09-13013 September 2024 – Exemption from Certain Requirements of 10 CFR 50.46 for Use of Axiom Fuel Rod Cladding – Letter ML24256A1132024-09-13013 September 2024 Regulatory Audit Summary Related to the Review of Regarding the Updated Spent Fuel Pool Criticality Safety Analysis License Amendment Request IR 05000250/20240052024-08-23023 August 2024 Updated Inspection Plan for Turkey Point Units 3 & 4 - Report 05000250/2024005 and 05000251/2024005 ML24234A0062024-08-22022 August 2024 Project Manager Assignment L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000250/LER-2024-002-01, Condition Prohibited by Technical Specifications2024-07-10010 July 2024 Condition Prohibited by Technical Specifications L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal ML24173A1902024-06-28028 June 2024 Withdrawal of an Amendment Request ML24159A2652024-06-26026 June 2024 Correction of Safety Evaluation for Issuance of Amendment Nos. 298 & 291 Regarding Revising the Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter IR 05000250/20244012024-06-0505 June 2024 – Security Baseline Inspection Report 05000250-2024401, 05000251-2024401 and 07200062-2024401 L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000250/20240012024-05-10010 May 2024 Integrated Inspection Report 05000250/2024001 and 05000251/2024001 ML24135A0942024-05-0909 May 2024 Periodic Update to the Updated Final Safety Analysis Report ML24127A1862024-05-0909 May 2024 Request for Withholding Information from Public Disclosure L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-073, Cycle 34 Core Operating Limits Report2024-05-0101 May 2024 Cycle 34 Core Operating Limits Report L-2024-072, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report L-2024-048, Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision2024-04-30030 April 2024 Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision L-2024-069, Radiological Emergency Plan Revision 762024-04-22022 April 2024 Radiological Emergency Plan Revision 76 L-2024-066, Sixth 10-Year Inservice Testing Interval Relief Request No. PR-022024-04-17017 April 2024 Sixth 10-Year Inservice Testing Interval Relief Request No. PR-02 2024-09-25
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24282A6722024-10-0808 October 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24261B8062024-09-17017 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24250A0242024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24250A0852024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24234A0842024-08-21021 August 2024 Notification of Inspection and Request for Information ML24234A0142024-08-20020 August 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Spent Fuel Storage License Amendment Request (LAR) (L-2023-LLA-0142) ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan IR 05000250/20240102024-01-0505 January 2024 Focused Engineering Inspection 05000250/2024010 and 05000251/2024010 ML23226A0752023-08-14014 August 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23129A8322023-05-0505 May 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23038A1892023-02-0303 February 2023 RP RFI April 2023 ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22311A4752022-11-0707 November 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - ITS IR 05000250/20234012022-10-19019 October 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000250/2023401 and 05000251/2023401 ML22255A0502022-09-15015 September 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Replace Instrumentation with Digital Systems ML22229A5332022-08-18018 August 2022 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000250 2022402 and 05000251 2022402) ML22181A0562022-06-30030 June 2022 NRR E-mail Capture - Request for Additional Information - Turkey Point U3 Sgtir (L-2022-LRO-0070) ML22081A0292022-03-21021 March 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit No. 3 - Request for Additional Information - Icw Alternative ML22068A2352022-03-17017 March 2022 Licensed Operator Positive Fitness-For-Duty Test ML22074A0932022-03-14014 March 2022 RP RFI March 2022 ML21342A2932021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Requested License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 5 ML21298A0572021-10-25025 October 2021 NRR E-mail Capture - Final: Tpn Request for Additional Information - Round 2 Concerning Relief Request 10 - Extension EPID: L-2021-LLR-0077 ML21291A1272021-10-14014 October 2021 NRR E-mail Capture - Request for Additional Information - Fifth Ten-Year Inservice Inspection Interval Relief Request No.10 - Extension (L-2021-LLR-0077) ML21270A1652021-09-27027 September 2021 NRR E-mail Capture - Turkey Point Request for Additional Information Concerning Full Spectrum LOCA Methodology - EPID L-2021-LLA-0070 ML21252A2142021-09-0101 September 2021 NRR E-mail Capture - Final: Turkey Point Units 3 and 4 - Request for Additional Information Concerning Relief Requests 8 and 9 ML21238A3282021-08-26026 August 2021 RP RFI October 2020 ML20315A0182020-11-10010 November 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML20149K6262020-05-27027 May 2020 NRR E-mail Capture - Turkey Point Unit 4 - Request for Additional Information Concerning 2019 Steam Generator Tube Inspections ML20122A1172020-05-0101 May 2020 NRR E-mail Capture - Final: Turkey Point Units 3 and 4 Request for Additional Information Concerning Emergency Action Level Scheme Change (EPID L-2019-LLA-0271) (FPL: L-2019-203) ML20104B2232020-04-0909 April 2020 NRR E-mail Capture - Action: Turkey Point Unit 3 - Request for Additional Information Concerning Deferral of Steam Generator Inservice Inspections ML20084G5622020-03-20020 March 2020 NRR E-mail Capture - Turkey Point Containment Radiation Monitors Request for Additional Information ML20028C7372019-12-0202 December 2019 Notification of Inspection and Request for Information ML19184A1002019-07-0303 July 2019 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4, Request for Additional Information Regarding License Amendment Request 266 ML19101A3312019-04-11011 April 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 11 (EPID No. L-2018-RNW-0002) - Enclosure ML19087A2112019-03-28028 March 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 10 (EPID No. L-2018-RNW-0002) - Enclosure ML19073A0042019-03-14014 March 2019 Safety RAIs - Set 10 - Draft ML19053A6122019-02-22022 February 2019 Response Date Extension for RAIs Set 8, Revision 1, for the Safety Review of the Turkey Point Subsequent License Renewal Application ML19037A3982019-02-0606 February 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 9 (EPID No. L-2018-RNW-0002) - Enclosure ML19032A3972019-02-0101 February 2019 SLRA Request for Additional Information RAIs 3.5.2.2.2.6 Revision 1 Set 8 Final ML19016A2332019-01-16016 January 2019 NRR E-mail Capture - Request for Additional Information - Turkey Point LAR 265 PRA - NFPA RCP Seals - EPID L-2018-LLA-0280 ML18341A0052019-01-15015 January 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 8 (EPID No. L-2018-RNW-0002) - Enclosure ML18341A0042019-01-15015 January 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 8 (EPID No. L-2018-RNW-0002) - E-Mail ML18348A5852018-12-13013 December 2018 Emergency Preparedness Inspection and Request for Information ML18318A4332018-11-19019 November 2018 Supplemental Information Needed for Acceptance of License Amendment Request to Revise NFPA 805 License Condition for Reactor Coolant Pump Seals ML18292A7462018-10-31031 October 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application; Set 7 (EPID No. L-2018-RNW-0002) - Enclosure ML18269A2282018-10-0404 October 2018 Request for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 6 (EPID No. L-2018-RNW-0002) - Enclosure ML18269A2102018-10-0101 October 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 4 (EPID L-2018-RNW-0002) - Enclosure ML18243A0072018-09-17017 September 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 3 (EPID No. L-2018-RNW-0002) - Email ML18259A0002018-09-17017 September 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application; Set 3 (EPID No. L-2018-RNW-0002) - Enclosure 2 2024-09-06
[Table view] |
Text
December 22, 2005Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420
SUBJECT:
TURKEY POINT PLANT, UNITS 3 AND 4 - REQUEST FOR ADDITIONALINFORMATION REGARDING PROPOSED EXEMPTION FROM AUTOMATIC FIRE SUPPRESSION AND DETECTION REQUIREMENTS (TAC NOS. MC5542 AND MC5543)
Dear Mr. Stall:
By letter dated December 27, 2004, as supplemented May 23, 2005, Florida Power & LightCompany submitted a proposed exemption from certain requirements of Title 10 to the Code ofFederal Regulations, Part 50, Appendix R. Specifically, the request involves an exemption fromthe requirements of subsection III.G.3 of Appendix R for automatic suppression and detectionfor specific fire zones located in the Mechanical Equipment Room and Control Room roof at Turkey Point Units 3 and 4. The U.S. Nuclear Regulatory Commission staff has reviewed your submittal and finds that aresponse to the enclosed Request for Additional Information is needed before we can complete the review.This request was discussed with Ms. Olga Hanek of your staff on December 8, 2005, and it wasagreed that a response would be provided by January 13, 2006. If you have any questions, please contact me at (301) 415-3974.Sincerely, /RA/Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-250 and 50-251
Enclosure:
As stated cc w/encl: See next page December 22, 2005Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420
SUBJECT:
TURKEY POINT PLANT, UNITS 3 AND 4 - REQUEST FOR ADDITIONALINFORMATION REGARDING PROPOSED EXEMPTION FROM AUTOMATIC FIRE SUPPRESSION AND DETECTION REQUIREMENTS (TAC NOS. MC5542 AND MC5543)
Dear Mr. Stall:
By letter dated December 27, 2004, as supplemented May 23, 2005, Florida Power & LightCompany submitted a proposed exemption from certain requirements of Title 10 to the Code ofFederal Regulations, Part 50, Appendix R. Specifically, the request involves an exemption fromthe requirements of subsection III.G.3 of Appendix R for automatic suppression and detectionfor specific fire zones located in the Mechanical Equipment Room and Control Room roof at Turkey Point Units 3 and 4. The U.S. Nuclear Regulatory Commission staff has reviewed your submittal and finds that aresponse to the enclosed Request for Additional Information is needed before we can complete the review.This request was discussed with Ms. Olga Hanek of your staff on December 8, 2005, and it wasagreed that a response would be provided by January 13, 2006. If you have any questions, please contact me at (301) 415-3974.Sincerely, /RA/Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-250 and 50-251
Enclosure:
As stated cc w/encl: See next page Distribution:PUBLICLPL II-2 R/FRidsPMBMoroneyRidsNrrDorlLpldBClayton (paper copy)RidsOgcRpRidsRgn2MailCenter (SBinoy)RidsAcrsAcnwMailCenterSWeerakkodyALavretta RidsNrrDlpmDprADAMS ACCESSION No.: ML053480030 NRR-088OFFICELPL2-2/PMLPL2-2/LAAFPB/CLPL2-2/BCNAMEBMoroneyBClaytonSWeerokkodyby memo datedMMarshallDATE12/16 /0512/16/0511/15/200512/22/05OFFICIAL RECORD COPY EnclosureREQUEST FOR ADDITIONAL INFORMATION FIRE PROTECTION EXEMPTIONFLORIDA POWER AND LIGHT COMPANYTURKEY POINT UNITS 3 AND 4DOCKET NOS. 50-250 AND 50-2511.Identify the fire barrier material used in each of the fire zones for which the exemption isrequested. 2.A 100-foot fire hose located outside the Cable Spreading Room is used as thesecondary means of fire protection for the Mechanical Equipment Room (Fire Zone 097). In order to assess the accessibility of the hose to all points in theMechanical Equipment Room, provide distances from the hose station, along the paththat would be taken to reach the Mechanical Equipment Room in the event of a fire, to all points in the Mechanical Equipment Room. 3.Provide the following information regarding the detection system proposed for theMechanical Equipment Room (FZ 097). a.What type of detection system will be used?
b.Is the air flow within the room turbulent such that smoke detection could becompromised by inadequate placement of the detector(s)? c.What version of National Fire Protection Association standard NFPA 72 isreferenced for the design and installation standard for the detector(s)?
Mr. J. A. StallTURKEY POINT PLANT Florida Power and Light Company cc:M. S. Ross, Managing Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420
Marjan Mashhadi, Senior Attorney Florida Power & Light Company 801 Pennsylvania Avenue, NW.
Suite 220 Washington, DC 20004T. O. Jones, Site Vice PresidentTurkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 County Manager Miami-Dade County 111 Northwest 1 Street, 29th Floor Miami, Florida 33128 Senior Resident InspectorTurkey Point Nuclear Plant U.S. Nuclear Regulatory Commission 9762 SW. 344 th StreetFlorida City, Florida 33035Mr. William A. Passetti, ChiefDepartment of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741Mr. Craig Fugate, DirectorDivision of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304Michael O. PearcePlant General Manager Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035Walter ParkerLicensing Manager Turkey Point Nuclear Plant 9760 SW 344th Street Florida City, FL 33035Mark Warner, Vice PresidentNuclear Operations Support Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420Mr. Rajiv S. KundalkarVice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420