Category:Inspection Report
MONTHYEARIR 05000250/20243012024-10-0303 October 2024 NRC Operator License Examination Report 05000250/2024301 and 05000251/2024301 IR 05000250/20240052024-08-23023 August 2024 Updated Inspection Plan for Turkey Point Units 3 & 4 - Report 05000250/2024005 and 05000251/2024005 IR 05000250/20240022024-08-0101 August 2024 Integrated Inspection Report 05000250/2024002 and 05000251/2024002 IR 05000250/20244012024-06-0505 June 2024 – Security Baseline Inspection Report 05000250-2024401, 05000251-2024401 and 07200062-2024401 IR 05000250/20240012024-05-10010 May 2024 Integrated Inspection Report 05000250/2024001 and 05000251/2024001 ML24072A2382024-03-20020 March 2024 Review of the Fall 2023 Steam Generator Tube Inspections During Refueling Outage No. 33 IR 05000250/20244202024-03-11011 March 2024 – Security Baseline Inspection Report 05000250/2024420 and 05000251/2024420 - Final IR 05000250/20230062024-02-28028 February 2024 Annual Assessment Letter for Turkey Point Units 3 & 4 - Report 05000250/2023006 and 05000251/2023006 IR 05000250/20240112024-02-15015 February 2024 Notification of Turkey Point Nuclear Generating Station - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 05000250/2024011 and 05000251/2024011 IR 05000250/20230042024-02-13013 February 2024 Integrated Inspection Report 05000250/2023004 and 05000251/2023004 IR 05000250/20240102024-01-0505 January 2024 Focused Engineering Inspection 05000250/2024010 and 05000251/2024010 IR 05000250/20230032023-11-0909 November 2023 – Integrated Inspection Report 05000250/2023003 and 05000251/2023003 IR 05000250/20230102023-09-29029 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000250/2023010 and 05000251/2023010 IR 05000250/20230052023-08-21021 August 2023 Updated Inspection Plan for Turkey Point, Units 3 & 4 (Report 05000250/2023005 and 05000251/2023005) IR 05000250/20230022023-08-14014 August 2023 Integrated Inspection Report 05000250/2023002 and 05000251/2023002 IR 05000250/20234022023-06-12012 June 2023 – Security Baseline Inspection Report 05000250/2023402 and 05000251/2023402 IR 05000250/20233012023-05-17017 May 2023 – NRC Operator License Examination Report 05000250/2023301 and 05000251/2023301 IR 05000250/20230012023-05-12012 May 2023 – Integrated Inspection Report 05000250/2023001 and 05000251/2023001 IR 05000250/20220062023-03-0101 March 2023 Annual Assessment Letter for Turkey Point, Units 3 & 4 (Report 05000250/2022006 and 05000251/2022006) IR 05000250/20220042023-01-27027 January 2023 – Integrated Inspection Report 05000250/2022004 and 05000251/2022004 IR 05000250/20220112022-12-20020 December 2022 – Design Basis Assurance Inspection (Programs) Inspection Report 05000250/2022011 and 05000251/2022011 IR 05000250/20220102022-11-29029 November 2022 Triennial Fire Protection Inspection Report 05000250/2022010 and 05000251/2022010 IR 05000250/20224022022-11-0707 November 2022 Security Baseline Inspection Report 05000250 2022402 and 05000251 2022402 IR 05000250/20220032022-10-31031 October 2022 Integrated Inspection Report 05000250/2022003 and 05000251/2022003 ML22286A1262022-10-28028 October 2022 Review of the Fall 2021 Steam Generator Tube Inspections During Refueling Outage No. 32 IR 05000250/20234012022-10-19019 October 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000250/2023401 and 05000251/2023401 IR 05000250/20220052022-08-26026 August 2022 Updated Inspection Plan for Turkey Point Units 3 & 4 Report 05000250 2022005 and 05000251 2022005-Final ML22229A5332022-08-18018 August 2022 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000250 2022402 and 05000251 2022402) IR 05000250/20220022022-08-12012 August 2022 Integrated Inspection Report 05000250/2022002 and 05000251/2022002 IR 05000250/20220012022-05-11011 May 2022 Integrated Inspection Report 05000250/2022001 and 05000251/2022001 L-2022-072, Steam Generator Tube Inspection Report2022-05-0606 May 2022 Steam Generator Tube Inspection Report IR 05000250/20224012022-03-0808 March 2022 Security Baseline Inspection Report 05000250/2022401 and 05000251/2022401(U) IR 05000250/20210062022-03-0202 March 2022 Annual Assessment Letter for Turkey Point, Units 3 and 4 (Report No. 05000250/2021006 and 05000251/2021006) IR 05000250/20210042022-02-0202 February 2022 Integrated Inspection Report 05000250/2021004 and 05000251/2021004 IR 05000250/20210072021-11-0303 November 2021 Follow-Up Assessment Letter Report 05000250/2021007 IR 05000250/20210032021-11-0303 November 2021 Integrated Inspection Report 05000250/2021003 and 05000251/2021003 IR 05000250/20210402021-09-30030 September 2021 95001 Supplemental Inspection Report 05000250/2021040 and 05000251/2021040 IR 05000250/20210052021-08-25025 August 2021 Updated Inspection Plan for Turkey Point, Units 3 & 4 (Report 05000250/2021005 and 05000251/2021005) IR 05000250/20210022021-08-0404 August 2021 Integrated Inspection Report 05000250/2021002 and 05000251/2021002 IR 07200062/20210012021-07-21021 July 2021 Operation of an Independent Spent Fuel Storage Installation Report 07200062/2021001 IR 05000250/20214012021-06-11011 June 2021 Security Baseline Inspection Report 05000250/2021401, 05000251/2021401, and 07200062/2021401 IR 05000250/20210012021-05-0707 May 2021 Integrated Inspection Report 05000250/2021001 and 05000251/2021001 and Assessment Follow-Up Letter IR 05000250/20210122021-05-0505 May 2021 Biennial Problem Identification and Resolution Inspection Report 05000250/2021012 and 05000251/2021012 IR 05000250/20214202021-04-29029 April 2021 Security Baseline Inspection Report 05000250/2021420 and 05000251/2021420 Cover Letter IR 05000250/20213012021-04-10010 April 2021 NRC Operator License Examination Report 05000250/2021301 and 05000251/2021301 IR 05000250/20210902021-04-0606 April 2021 Notice of Violation and Proposed Imposition of Civil Penalty $150,000, NRC Inspection Report Nos.05000250/2021090 and 05000251/2021090; Investigation Report Nos. 2-2019-011 and 2-2019-025 Exercise of Enforcement Discretion IR 05000250/20200062021-03-0303 March 2021 Annual Assessment Letter for Turkey Point Nuclear Plant, Unit 3 and Unit 4 Report 05000250/2020006 and 05000251/2020006 IR 05000250/20210102021-02-26026 February 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000250/2021010 and 05000251/2021010 IR 05000250/20204022021-02-12012 February 2021 Material Control and Accounting Program Inspection Report 05000250/2020402 and 05000251/2020402 Public Version (Cover Letter Only) IR 05000250/20200042021-02-11011 February 2021 Integrated Inspection Report 05000250/2020004 and 05000251/2020004 and Independent Spent Fuel Storage Installation Inspection (ISFSI) 07200062/2020002 2024-08-23
[Table view] Category:Letter
MONTHYEARL-2024-184, Radiological Emergency Plan Revision 772024-11-0505 November 2024 Radiological Emergency Plan Revision 77 L-2024-173, Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-31031 October 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-175, Cycle 34 Core Operating Report2024-10-24024 October 2024 Cycle 34 Core Operating Report ML24291A2882024-10-24024 October 2024 Westinghouse Topical Report - Request for Withholding Information from Public Disclosure L-2024-177, Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis2024-10-22022 October 2024 Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24276A2302024-10-16016 October 2024 Westinghouse Topical Report – Request for Withholding Information from Public Disclosure L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes ML24289A2372024-10-15015 October 2024 Transmittal of Revision 1 Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles IR 05000250/20243012024-10-0303 October 2024 NRC Operator License Examination Report 05000250/2024301 and 05000251/2024301 L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24269A1292024-09-24024 September 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24260A2262024-09-18018 September 2024 NRC Examination Results Summary - Examination Reports: 05000250/2024301 and 05000251/2024301 ML24262A2272024-09-18018 September 2024 Transmittal of Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles ML24158A0052024-09-17017 September 2024 Completion of Subsequent License Renewal Site Specific Environmental Review and Modification to Subsequent Renewed Facility Operating Licenses L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24207A0342024-09-13013 September 2024 – Exemption from Certain Requirements of 10 CFR 50.46 for Use of Axiom Fuel Rod Cladding – Letter ML24256A1132024-09-13013 September 2024 Regulatory Audit Summary Related to the Review of Regarding the Updated Spent Fuel Pool Criticality Safety Analysis License Amendment Request IR 05000250/20240052024-08-23023 August 2024 Updated Inspection Plan for Turkey Point Units 3 & 4 - Report 05000250/2024005 and 05000251/2024005 ML24234A0062024-08-22022 August 2024 Project Manager Assignment L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000250/LER-2024-002-01, Condition Prohibited by Technical Specifications2024-07-10010 July 2024 Condition Prohibited by Technical Specifications L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal ML24173A1902024-06-28028 June 2024 Withdrawal of an Amendment Request ML24159A2652024-06-26026 June 2024 Correction of Safety Evaluation for Issuance of Amendment Nos. 298 & 291 Regarding Revising the Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter IR 05000250/20244012024-06-0505 June 2024 – Security Baseline Inspection Report 05000250-2024401, 05000251-2024401 and 07200062-2024401 L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000250/20240012024-05-10010 May 2024 Integrated Inspection Report 05000250/2024001 and 05000251/2024001 ML24135A0942024-05-0909 May 2024 Periodic Update to the Updated Final Safety Analysis Report ML24127A1862024-05-0909 May 2024 Request for Withholding Information from Public Disclosure L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-073, Cycle 34 Core Operating Limits Report2024-05-0101 May 2024 Cycle 34 Core Operating Limits Report L-2024-072, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report L-2024-048, Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision2024-04-30030 April 2024 Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision L-2024-069, Radiological Emergency Plan Revision 762024-04-22022 April 2024 Radiological Emergency Plan Revision 76 L-2024-066, Sixth 10-Year Inservice Testing Interval Relief Request No. PR-022024-04-17017 April 2024 Sixth 10-Year Inservice Testing Interval Relief Request No. PR-02 2024-09-25
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24282A6722024-10-0808 October 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24261B8062024-09-17017 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24250A0242024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24250A0852024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24234A0842024-08-21021 August 2024 Notification of Inspection and Request for Information ML24234A0142024-08-20020 August 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Spent Fuel Storage License Amendment Request (LAR) (L-2023-LLA-0142) ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan IR 05000250/20240102024-01-0505 January 2024 Focused Engineering Inspection 05000250/2024010 and 05000251/2024010 ML23226A0752023-08-14014 August 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23129A8322023-05-0505 May 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23038A1892023-02-0303 February 2023 RP RFI April 2023 ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22311A4752022-11-0707 November 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - ITS IR 05000250/20234012022-10-19019 October 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000250/2023401 and 05000251/2023401 ML22255A0502022-09-15015 September 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Replace Instrumentation with Digital Systems ML22229A5332022-08-18018 August 2022 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000250 2022402 and 05000251 2022402) ML22181A0562022-06-30030 June 2022 NRR E-mail Capture - Request for Additional Information - Turkey Point U3 Sgtir (L-2022-LRO-0070) ML22081A0292022-03-21021 March 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit No. 3 - Request for Additional Information - Icw Alternative ML22068A2352022-03-17017 March 2022 Licensed Operator Positive Fitness-For-Duty Test ML22074A0932022-03-14014 March 2022 RP RFI March 2022 ML21342A2932021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Requested License Amendment Request Concerning Technical Specification Conversion to NUREG-1431, Revision 5 ML21298A0572021-10-25025 October 2021 NRR E-mail Capture - Final: Tpn Request for Additional Information - Round 2 Concerning Relief Request 10 - Extension EPID: L-2021-LLR-0077 ML21291A1272021-10-14014 October 2021 NRR E-mail Capture - Request for Additional Information - Fifth Ten-Year Inservice Inspection Interval Relief Request No.10 - Extension (L-2021-LLR-0077) ML21270A1652021-09-27027 September 2021 NRR E-mail Capture - Turkey Point Request for Additional Information Concerning Full Spectrum LOCA Methodology - EPID L-2021-LLA-0070 ML21252A2142021-09-0101 September 2021 NRR E-mail Capture - Final: Turkey Point Units 3 and 4 - Request for Additional Information Concerning Relief Requests 8 and 9 ML21238A3282021-08-26026 August 2021 RP RFI October 2020 ML20315A0182020-11-10010 November 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML20149K6262020-05-27027 May 2020 NRR E-mail Capture - Turkey Point Unit 4 - Request for Additional Information Concerning 2019 Steam Generator Tube Inspections ML20122A1172020-05-0101 May 2020 NRR E-mail Capture - Final: Turkey Point Units 3 and 4 Request for Additional Information Concerning Emergency Action Level Scheme Change (EPID L-2019-LLA-0271) (FPL: L-2019-203) ML20104B2232020-04-0909 April 2020 NRR E-mail Capture - Action: Turkey Point Unit 3 - Request for Additional Information Concerning Deferral of Steam Generator Inservice Inspections ML20084G5622020-03-20020 March 2020 NRR E-mail Capture - Turkey Point Containment Radiation Monitors Request for Additional Information ML20028C7372019-12-0202 December 2019 Notification of Inspection and Request for Information ML19184A1002019-07-0303 July 2019 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4, Request for Additional Information Regarding License Amendment Request 266 ML19101A3312019-04-11011 April 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 11 (EPID No. L-2018-RNW-0002) - Enclosure ML19087A2112019-03-28028 March 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 10 (EPID No. L-2018-RNW-0002) - Enclosure ML19073A0042019-03-14014 March 2019 Safety RAIs - Set 10 - Draft ML19053A6122019-02-22022 February 2019 Response Date Extension for RAIs Set 8, Revision 1, for the Safety Review of the Turkey Point Subsequent License Renewal Application ML19037A3982019-02-0606 February 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 9 (EPID No. L-2018-RNW-0002) - Enclosure ML19032A3972019-02-0101 February 2019 SLRA Request for Additional Information RAIs 3.5.2.2.2.6 Revision 1 Set 8 Final ML19016A2332019-01-16016 January 2019 NRR E-mail Capture - Request for Additional Information - Turkey Point LAR 265 PRA - NFPA RCP Seals - EPID L-2018-LLA-0280 ML18341A0052019-01-15015 January 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 8 (EPID No. L-2018-RNW-0002) - Enclosure ML18341A0042019-01-15015 January 2019 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 8 (EPID No. L-2018-RNW-0002) - E-Mail ML18348A5852018-12-13013 December 2018 Emergency Preparedness Inspection and Request for Information ML18318A4332018-11-19019 November 2018 Supplemental Information Needed for Acceptance of License Amendment Request to Revise NFPA 805 License Condition for Reactor Coolant Pump Seals ML18292A7462018-10-31031 October 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application; Set 7 (EPID No. L-2018-RNW-0002) - Enclosure ML18269A2282018-10-0404 October 2018 Request for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 6 (EPID No. L-2018-RNW-0002) - Enclosure ML18269A2102018-10-0101 October 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 4 (EPID L-2018-RNW-0002) - Enclosure ML18243A0072018-09-17017 September 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 3 (EPID No. L-2018-RNW-0002) - Email ML18259A0002018-09-17017 September 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application; Set 3 (EPID No. L-2018-RNW-0002) - Enclosure 2 2024-09-06
[Table view] |
See also: IR 05000250/2022402
Text
Mr. Bob Coffey
Executive Vice President,
Nuclear and Chief Nuclear Officer
Florida Power & Light Company
700 Universe Blvd.
Mail Stop: EX/JB
Juno Beach, FL 33408
SUBJECT: TURKEY POINT, UNITS 3, AND 4 - NOTIFICATION OF TARGET SET
INSPECTION AND REQUEST FOR INFORMATION (NRC INSPECTION
REPORT NO. 05000250/2022402 AND 05000251/2022402)
Dear Mr. Coffey:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II (RII) staff will conduct an inspection of the Target Sets specified by the conditions of
your operating license at the Turkey Point Nuclear Station Units 3 and 4 on October 3 - 5, 2022.
The inspection will be led by Mr. Philipp Braaten, Sr. Reactor Inspector, of the NRC RII office.
The inspection will be conducted in accordance with Inspection Procedure 71130.14, Review of
Power Reactor Target Sets, and effective as of January 1, 2018.
On August 17, 2022, during phone communications between Mr. Antonio Lopez of your staff,
and Mr. Philipp Braaten, NRC RII, our respective staff, confirmed arrangements for a three-day
onsite inspection. The schedule is as follows:
Onsite preparation / SGI review: October 3, 2022
Onsite inspection: October 4 - 5, 2022
In order to complete the inspection in the time allotted, Mr. Braaten needs to review your non-
SGI target sets program references and other pertinent documents prior to the inspection.
Please provide the non-SGI documents listed below via email or CERTREC upload by
September 26, 2022.
Please indicate how you would like our staff to dispose of any SGI documents after we have
completed our review. Mr. Braaten plans to only review SGI material onsite in your secure
spaces and return materials to your staff at the end of each day.August 18, 2022
The types of documents the team will be reviewing during the conduct of the inspection are
listed below. Please contact Mr. Braaten at (404) 997-4651 prior to preparing copies and
sending/uploading the files, if there are any questions. The inspection team will try to minimize
your administrative burden by specifically identifying those documents required for inspection
preparation.
Provide the following documents:
- All non-SGI procedures that relate to the Target Set identification, maintenance and
development
- Site Target Sets (ready for review once onsite)
- List of the Target Set Expert Panel members (names, qualifications, and positions)
- Response to security event operations procedure
- Any procedure listed as a credited operator action (OMA) in the target sets
- Results of the last two target set expert panel reviews (meeting minutes)
- Corrective action program (CAP) procedures and LIST of CRs associated with
Target Sets and the program since the last triennial target set inspection
(last 3 years)
- A list of any issue/condition reports since the last target set inspection (3 years)
directly related to target sets and/or Safety/Security interface
- A LIST of design change packages or modification packages that affected target sets
- A summary or list of any changes that have occurred to the target sets since the last
inspection
- A copy of the sites Safety / Security Interface procedure
Items needed during the Inspection Week:
- Access to all NON-SGI and SGI procedures related to Target Sets
- A point of contact knowledgeable in Target Sets and the protective defensive strategy
- We will require a meeting with Target Set knowledgeable personnel (including
operations) to discuss target set content
We will keep the requested information only as long as it is necessary to complete the
inspection activity. Additionally, if you feel that any requested documents would contain
proprietary or company sensitive information, please make sure they are appropriately marked
and attached to an appropriate affidavit for withholding in accordance with 10 CFR 2.390.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, under control number
3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,
a request for information or an information collection requirement unless the requesting
document displays a currently valid Office of Management and Budget control number.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget under control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Your cooperation and support during this inspection will be appreciated. If you have
questions concerning this inspection or the inspection teams information or logistical needs,
please contact Philipp Braaten, the team lead inspector, in the Region II office at (404) 997-
4651 or philipp.braaten@nrc.gov or me at (404) 997-4551.
Sincerely,
Gerald McCoy, Branch Chief
Engineering Branch 2
Division of Reactor Safety
Docket Nos.: 50-250; 50-251
License Nos.: DPR-31, DPR-41
Signed by McCoy, Gerald
on 08/18/22