ML21154A066: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
(One intermediate revision by the same user not shown) | |||
Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:June 2, 2021 | ||
Mr. Daniel G. Stoddard | |||
Senior Vice President and | |||
Chief Nuclear Officer | |||
Innsbrook Technical Center | |||
5000 Dominion Boulevard | |||
Glen Allen, VA 23060-6711 | |||
SUBJECT: NOTIFICATION OF NORTH ANNA POWER STATION, UNITS 1 & 2 DESIGN | |||
BASES ASSURANCE INSPECTION (TEAM) - U.S. NUCLEAR REGULATORY | |||
COMMISSION INSPECTION REPORT 05000338/2021010 AND | |||
05000339/2021010 | |||
Dear Mr. Stoddard: | |||
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) | |||
Region II staff will conduct a Design Bases Assurance Inspection (DBAI) at your North Anna | |||
Power Station, Units 1 & 2 during the weeks of September 20th and October 4th , 2021. | |||
Mr. Theodore Fanelli, a Senior Reactor Inspector from the NRCs Region II office, will lead the | |||
inspection team. The inspection will be conducted in accordance with Inspection Procedure | |||
71111.21M, Design Bases Assurance Inspection (Team), dated December 8, 2016 (ADAMS | |||
ML16340B000). | |||
The inspection will evaluate the capability of components that have been modified and risk- | |||
significant/low-margin components to function as designed and to support proper system | |||
operation. The inspection will also include a review of selected operator actions, operating | |||
experience, and modifications. | |||
During a telephone conversation on May 27, 2021, with Mr. Danny McGinnis, we confirmed | |||
arrangements for an information-gathering site visit and the two-week onsite inspection. The | |||
schedule is as follows: | |||
* Information-gathering visit: Week of August 30 to September 3, 2021 | |||
* Onsite weeks: Weeks of September 20 and October 4, 2021 | |||
The purpose of the information-gathering visit is to meet with members of your staff to identify | |||
components that have been modified, risk-significant components and operator actions. | |||
Information and documentation needed to support the inspection will also be identified. | |||
Mr. Andy Rosebrook, a Region II Senior Risk Analyst, will support Mr. Fanelli during the | |||
information-gathering visit to review probabilistic risk assessment data and identify components | |||
to be examined during the inspection. Additionally, during the onsite weeks, time will be needed | |||
on the plant-referenced simulator in order to facilitate the development of operator action-based | |||
scenarios. | |||
D. Stoddard 2 | |||
The enclosure lists documents that will be needed prior to the information-gathering visit. | |||
Please provide the referenced information to the Region II Office by August 24, 2021 Additional | |||
documents will be requested following the information-gathering visit. The inspectors will try to | |||
minimize your administrative burden by specifically identifying only those documents required | |||
for inspection preparation. The additional information will be needed in the Region II office by | |||
September 9, 2021, to support the inspection teams preparation week. During the information- | |||
gathering trip, Mr. Fanelli will also discuss the following inspection support administrative | |||
details: (1) availability of knowledgeable plant engineering and licensing personnel to serve as | |||
points of contact during the inspection; (2) method of tracking inspector requests during the | |||
inspection; (3) licensee computer access; (4) working space; (5) arrangements for site access; | |||
and (6) other applicable information. | |||
This letter, its enclosure, and your response (if any) will be made available for public inspection | |||
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document | |||
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for | |||
Withholding. | |||
Thank you for your cooperation in this matter. If you have any questions, regarding the | |||
information requested or the inspection, please contact Mr. Fanelli at 404-997-4433 or contact | |||
me at 404-997-4506. | |||
Sincerely, | |||
/RA/ | |||
James Baptist, Chief | |||
Engineering Branch 1 | |||
Division of Reactor Safety | |||
Docket Nos.: 50-338, 50-339 | |||
License Nos.: NPF-4, NPF-7 | |||
Enclosure: | |||
Notification of North Anna Power Station, units 1 & 2, | |||
Design Bases Assurance Inspection (Team) | |||
cc: Distribution via Listserv | |||
D. Stoddard 2 | |||
SUBJECT: NOTIFICATION OF NORTH ANNA POWER STATION, UNITS 1 & 2 DESIGN | |||
BASES ASSURANCE INSPECTION (TEAM) - U.S. NUCLEAR REGULATORY | |||
COMMISSION INSPECTION REPORT 05000338/2021010 AND | |||
05000339/2021010 dated June 2, 2021 | |||
Distribution: | |||
T. Fanelli, RII | |||
J. Baptist, RII | |||
ADAMS _ML21154A066____________________________________ | |||
OFFICE RII:DRS RII:DRS | |||
NAME FANELLI BAPTIST | |||
DATE 5/27/2021 6/ 2 /2021 | |||
OFFICIAL RECORD COPY | |||
INFORMATION REQUEST FOR NORTH ANNA POWER STATION, UNITS 1 & 2 | |||
DESIGN BASES ASSURANCE INSPECTION (TEAM) | |||
Please provide the information electronically in .pdf files, Excel, or other searchable format on | |||
file sharing website, if utilized (ex. FTP site, SharePoint, etc.) or CDROM. The website (or | |||
CDROM) should be indexed and hyperlinked to facilitate ease of use. The requested items | |||
below, identified with an asterisk (*), should have a date range from January 1, 2018, until | |||
present. | |||
1. *List and brief description of permanent and field work completed plant modifications | |||
including permanent plant changes, design changes, set point changes, procedure | |||
changes, equivalency evaluations, suitability analyses, calculations, and commercial grade | |||
dedications. Include an index of systems (system numbers/designators and corresponding | |||
names), the safety classification for each modification, and type of modification. | |||
2. From your most recent probabilistic safety analysis (PSA) excluding external events and | |||
fires: | |||
a. Two risk rankings of components from your site-specific PSA: one sorted by Risk | |||
Achievement Worth (RAW), and the other sorted by Birnbaum Importance | |||
b. A list of the top 500 cut-sets | |||
c. A list of the top 500 LERF contributors | |||
3. From your most recent PSA including external events and fires: | |||
a. Two risk rankings of components from your site-specific PSA: one sorted by RAW, | |||
and the other sorted by Birnbaum Importance | |||
b. A list of the top 500 cut-sets | |||
4. Risk ranking of operator actions from your site-specific PSA sorted by RAW and human | |||
reliability worksheets for these items | |||
5. List of time-critical operator actions with a brief description of each action | |||
6. *List of components with low-design margins (i.e., pumps closest to the design limit for flow | |||
or pressure, diesel generator close to design-required output, heat exchangers close to | |||
rated design heat removal, and motor-operated valve risk-margin rankings, etc.) and | |||
associated evaluations or calculations | |||
7. *List and brief description of Root Cause Evaluations performed | |||
8. *List and brief description of common-cause component failures that have occurred | |||
9. List and brief description of equipment currently in degraded or nonconforming status as | |||
described in NRC Inspection Manual Chapter 0326, issued November 20, 2017 | |||
Enclosure | |||
2 | |||
10. *List and brief description of Operability Determinations and Functionality Assessments | |||
11. *List and reason for equipment that has been classified in maintenance rule (a)(1) status | |||
12. *List of equipment on the sites Station Equipment Reliability Issues List, including a | |||
description of the reason(s) why each component is on that list, and summaries (if | |||
available) of your plans to address the issue(s) along with dates added or removed from | |||
the issues list | |||
13. List of current operator work arounds/burdens | |||
14. Copy of Updated Final Safety Analysis Report | |||
15. Copy of Technical Specification(s) | |||
16. Copy of Technical Specifications Bases | |||
17. Copy of Technical Requirements Manual(s) | |||
18. Copy of the Quality Assurance Program Manual | |||
19. Copy of Corrective Action Program Procedure(s) | |||
20. Copy of Operability Determination Procedure(s) | |||
21. Copy of procedures addressing the following: Modifications, design changes, set point | |||
changes, equivalency evaluations or suitability analyses, commercial grade dedications, | |||
post-modifications testing, 10 CFR 50.59 screenings and evaluations, and UFSAR updates. | |||
22. List of motor operated valves and air operated valves in the valve program, and their | |||
associated design margin and risk ranking | |||
23. Primary AC and DC calculations for safety-related buses | |||
24. One-line diagram of electrical plant (Electronic only) | |||
25. Index and legend for electrical plant one-line diagrams | |||
26. Piping and instrumentation diagrams (P&IDs) for safety-related systems (Electronic) | |||
27. Index and legend for P&IDs | |||
28. Index (procedure number, title, and current revision) of station Emergency Operating | |||
Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures | |||
29. Copies of corrective action documents generated from previous CDBI | |||
30. Copy of any self-assessments performed, and corrective action documents generated, in | |||
preparation for current DBAI | |||
3 | |||
31. Contact information for a person to discuss PSA information prior to and during the | |||
information-gathering trip (Name, title, phone number, and e-mail address) | |||
}} | }} |
Latest revision as of 15:00, 20 January 2022
ML21154A066 | |
Person / Time | |
---|---|
Site: | North Anna |
Issue date: | 06/02/2021 |
From: | James Baptist Division of Reactor Safety II |
To: | Stoddard D Virginia Electric & Power Co (VEPCO) |
References | |
IR 2021010 | |
Download: ML21154A066 (6) | |
See also: IR 05000338/2021010
Text
June 2, 2021
Mr. Daniel G. Stoddard
Senior Vice President and
Chief Nuclear Officer
Innsbrook Technical Center
5000 Dominion Boulevard
Glen Allen, VA 23060-6711
SUBJECT: NOTIFICATION OF NORTH ANNA POWER STATION, UNITS 1 & 2 DESIGN
BASES ASSURANCE INSPECTION (TEAM) - U.S. NUCLEAR REGULATORY
COMMISSION INSPECTION REPORT 05000338/2021010 AND
Dear Mr. Stoddard:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a Design Bases Assurance Inspection (DBAI) at your North Anna
Power Station, Units 1 & 2 during the weeks of September 20th and October 4th , 2021.
Mr. Theodore Fanelli, a Senior Reactor Inspector from the NRCs Region II office, will lead the
inspection team. The inspection will be conducted in accordance with Inspection Procedure 71111.21M, Design Bases Assurance Inspection (Team), dated December 8, 2016 (ADAMS
The inspection will evaluate the capability of components that have been modified and risk-
significant/low-margin components to function as designed and to support proper system
operation. The inspection will also include a review of selected operator actions, operating
experience, and modifications.
During a telephone conversation on May 27, 2021, with Mr. Danny McGinnis, we confirmed
arrangements for an information-gathering site visit and the two-week onsite inspection. The
schedule is as follows:
- Information-gathering visit: Week of August 30 to September 3, 2021
- Onsite weeks: Weeks of September 20 and October 4, 2021
The purpose of the information-gathering visit is to meet with members of your staff to identify
components that have been modified, risk-significant components and operator actions.
Information and documentation needed to support the inspection will also be identified.
Mr. Andy Rosebrook, a Region II Senior Risk Analyst, will support Mr. Fanelli during the
information-gathering visit to review probabilistic risk assessment data and identify components
to be examined during the inspection. Additionally, during the onsite weeks, time will be needed
on the plant-referenced simulator in order to facilitate the development of operator action-based
scenarios.
D. Stoddard 2
The enclosure lists documents that will be needed prior to the information-gathering visit.
Please provide the referenced information to the Region II Office by August 24, 2021 Additional
documents will be requested following the information-gathering visit. The inspectors will try to
minimize your administrative burden by specifically identifying only those documents required
for inspection preparation. The additional information will be needed in the Region II office by
September 9, 2021, to support the inspection teams preparation week. During the information-
gathering trip, Mr. Fanelli will also discuss the following inspection support administrative
details: (1) availability of knowledgeable plant engineering and licensing personnel to serve as
points of contact during the inspection; (2) method of tracking inspector requests during the
inspection; (3) licensee computer access; (4) working space; (5) arrangements for site access;
and (6) other applicable information.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Thank you for your cooperation in this matter. If you have any questions, regarding the
information requested or the inspection, please contact Mr. Fanelli at 404-997-4433 or contact
me at 404-997-4506.
Sincerely,
/RA/
James Baptist, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos.: 50-338, 50-339
Enclosure:
Notification of North Anna Power Station, units 1 & 2,
Design Bases Assurance Inspection (Team)
cc: Distribution via Listserv
D. Stoddard 2
SUBJECT: NOTIFICATION OF NORTH ANNA POWER STATION, UNITS 1 & 2 DESIGN
BASES ASSURANCE INSPECTION (TEAM) - U.S. NUCLEAR REGULATORY
COMMISSION INSPECTION REPORT 05000338/2021010 AND
05000339/2021010 dated June 2, 2021
Distribution:
T. Fanelli, RII
J. Baptist, RII
ADAMS _ML21154A066____________________________________
OFFICE RII:DRS RII:DRS
NAME FANELLI BAPTIST
DATE 5/27/2021 6/ 2 /2021
OFFICIAL RECORD COPY
INFORMATION REQUEST FOR NORTH ANNA POWER STATION, UNITS 1 & 2
DESIGN BASES ASSURANCE INSPECTION (TEAM)
Please provide the information electronically in .pdf files, Excel, or other searchable format on
file sharing website, if utilized (ex. FTP site, SharePoint, etc.) or CDROM. The website (or
CDROM) should be indexed and hyperlinked to facilitate ease of use. The requested items
below, identified with an asterisk (*), should have a date range from January 1, 2018, until
present.
1. *List and brief description of permanent and field work completed plant modifications
including permanent plant changes, design changes, set point changes, procedure
changes, equivalency evaluations, suitability analyses, calculations, and commercial grade
dedications. Include an index of systems (system numbers/designators and corresponding
names), the safety classification for each modification, and type of modification.
2. From your most recent probabilistic safety analysis (PSA) excluding external events and
fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by Risk
Achievement Worth (RAW), and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
c. A list of the top 500 LERF contributors
3. From your most recent PSA including external events and fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by RAW,
and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
4. Risk ranking of operator actions from your site-specific PSA sorted by RAW and human
reliability worksheets for these items
5. List of time-critical operator actions with a brief description of each action
6. *List of components with low-design margins (i.e., pumps closest to the design limit for flow
or pressure, diesel generator close to design-required output, heat exchangers close to
rated design heat removal, and motor-operated valve risk-margin rankings, etc.) and
associated evaluations or calculations
7. *List and brief description of Root Cause Evaluations performed
8. *List and brief description of common-cause component failures that have occurred
9. List and brief description of equipment currently in degraded or nonconforming status as
described in NRC Inspection Manual Chapter 0326, issued November 20, 2017
Enclosure
2
10. *List and brief description of Operability Determinations and Functionality Assessments
11. *List and reason for equipment that has been classified in maintenance rule (a)(1) status
12. *List of equipment on the sites Station Equipment Reliability Issues List, including a
description of the reason(s) why each component is on that list, and summaries (if
available) of your plans to address the issue(s) along with dates added or removed from
the issues list
13. List of current operator work arounds/burdens
14. Copy of Updated Final Safety Analysis Report
15. Copy of Technical Specification(s)
16. Copy of Technical Specifications Bases
17. Copy of Technical Requirements Manual(s)
18. Copy of the Quality Assurance Program Manual
19. Copy of Corrective Action Program Procedure(s)
20. Copy of Operability Determination Procedure(s)
21. Copy of procedures addressing the following: Modifications, design changes, set point
changes, equivalency evaluations or suitability analyses, commercial grade dedications,
post-modifications testing, 10 CFR 50.59 screenings and evaluations, and UFSAR updates.
22. List of motor operated valves and air operated valves in the valve program, and their
associated design margin and risk ranking
23. Primary AC and DC calculations for safety-related buses
24. One-line diagram of electrical plant (Electronic only)
25. Index and legend for electrical plant one-line diagrams
26. Piping and instrumentation diagrams (P&IDs) for safety-related systems (Electronic)
27. Index and legend for P&IDs
28. Index (procedure number, title, and current revision) of station Emergency Operating
Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures
29. Copies of corrective action documents generated from previous CDBI
30. Copy of any self-assessments performed, and corrective action documents generated, in
preparation for current DBAI
3
31. Contact information for a person to discuss PSA information prior to and during the
information-gathering trip (Name, title, phone number, and e-mail address)