| number = ML17266A083
| number = ML17266A083
| issue date = 07/03/1979
| issue date = 07/03/1979
| title = LER 79-019/03L-0 on 790605:Control Element Assembly Dropped Four Times within 2-h Period.Caused by Failure of Coil Power Programmer Timing Module.Module Replaced
| title = LER 79-019/03L-0 on 790605:control Element Assembly Dropped Four Times within 2-h Period.Caused by Failure of Coil Power Programmer Timing Module.Module Replaced
| author name = SCHOPPMAN M A
| author name = Schoppman M
| author affiliation = FLORIDA POWER & LIGHT CO.
| author affiliation = FLORIDA POWER & LIGHT CO.
| addressee name =  
| addressee name =  
Line 14: Line 14:
| document type = LICENSEE EVENT REPORT (SEE ALSO AO,RO), TEXT-SAFETY REPORT
| document type = LICENSEE EVENT REPORT (SEE ALSO AO,RO), TEXT-SAFETY REPORT
| page count = 3
| page count = 3
| revision = 0
}}
}}
=Text=
{{#Wiki_filter:.4. 5 NRC FOAM Sdi                                                                                                                                U.*NUCLEAR RSGULATQRY COMMISSION Il 771                                                                          LICENSE:" EVENT REPORT CQNTROL SLCCXI IQI                      (PLSASS PRINT OR TYPe ALL RKQUIRSO INPORMATIQNI I~4 I
I
                    ~FLI            5    LI5111,Q,                    0    01.            I      '          I        I-              IJ      4        I Q ~
5'.0J~
1            9          UCSV$ 45 CQCS                I~                              UC$ 454 vuMBSR                            1$      5      L4CSVSC      YPS    14      55  Ms $ 3 C  N'T
                          ";; IL IS tl 54              41 5    tll0        0 COCK ST NUAISSJI 31      3 ii                  iVSNT OATS              IS Qa 1$
1    r RiPCAT OATS.
t      i
                                                                                                                                                                                                          $4 Q9 aslaNT OESCRIPTIQN ANO PROSASLS CQ04SRQUasVCcS Qlo 0 I 2          llhile in the start u mode followin                                                          a    refuelin ou a e CEA 419 dro ed four times within a two hour period.                                                            After each of the first three drops CEA'II'19 was                  restored to                  its          normal        position within the time limit speci-fied by Technical Specification 3.1.3.1.e, action statement l. After the fourth drop the coil power programmer timing module was'replaced and CEA il19 was returned to its normal position within the time l.imit speci-
      ~0 fied        by Technical                      Specification 3.1.3.1.e                                  and has performed                          normally.
1        3  9                                                                                                                                COMP, 5Y5TSAI              CAUSS          CAUSS                                                                              VALVS C  Oi                CQC4        SUSCOOS                    CCMPONSNT C004                        SUSCQOa          SuaCQQS
        ~09 1        5                        9 IJ~SS ISIS  IO            II LSJS I1
                                                                                                      ~tl IS s          I IS S MJS    19 WzS 14 54QUSNTIAL                              OCCURRSiVCS              RSPORT                        R SVISIQN 1111                                                                                19          14
                                                                                                                      ''Js 14                14  "        11            $
ATT5AO<MSNT          VPROA          PRIMS CCMR
                                                                                                                                                                                                                  ' 4 ACTION FUTURS                    SPFSC    ~        SssVTOCWN
                                                                                                                                                                          's 5'JPPUCR LJs ~~'
A TICJI      . CN PLANT              SIST>00            -      IIQURS Q22          SVSMITT 0        PQR.'ASVB                                  JJIANUFAC,URSA COMPONSNT'AJISN M~sMis JJs  $4                                        14 JJJ1 41 13                ~<>                            41 CAUSC OSSCRIPTION ANO COAASLC0 IV8 ACTIONS                                Q2>
CEA 819            dro ped due to                        a    failure of the coil ower ro                                              rammer          timin module.              No        cause          or failure mode has been determined.                                                        The timer module was      replaced and                        CEA 819          performed normally.                              No      other corrective action is required.
1 5
PACIU Y.
3 ATU5
                            ~
C Qs        ~00 45 PC%SR 0      Qs            NA OTIISR STATUS
                                                                                                  ~
IQ,uSTNOO OP OISCQVSRY
                                                                                                            ~JJ    rQl Operator:"QisSerVP>on"                                0 3    5              IO                I'1      IS                                44    4$
CCNTL IT ACTIVITY RCLS+$ 40 QP      RSL~S                        AMOUNTQP ACTIVITYQ35 O'A
                                                                                                                'k NA I QCATICN OP RSLSASS        Q 4      ~Z      Q22    ~ZQ2$
I4            I1                                                              <$
1      3    9 PSR50NNSL 4'APOSVISSS
                      ~o7 II'"0 IQ33            "z'rQs '"'"""NT
        ~~      5    3                II      11            11 PSRSCNNSL INIURISS 3  9
                      ~00          0 Qs II      I1 NA 1
LCSS QP CR OANAC1 0 PACIUTV Q2
                      ~Z'QA2                                              NA 1      3                IO                                                                                                                                                                                  34 PU8UC:1 OSSCPIPT:CN GS 7'                                                                            NRC 444 QPILV HEI    3 ISSV30 l
5 0    !4 HA                                                                                              I  '      l        l I            I I  I I'!
PIAAIF OP PR-PARSR                      M. A. Scho pman                                                    , N..(305) 552-2802
REPORTABLE OCCURRENCE  335-79-19 LICENSEE EVENT REPORT PAGE 2 ADDITIONAL EYENT DESCRIPTION The  coil power programmer timer module was replaced after CEA >19 dropped for the fourth time within a two hour period. CEA 819 was returned to its normal position and has performed normally for 3 weeks.
Since the reactor was at zero power (Mode 2) at the time of      this occur-rence, Technical Specification 3.2      was not applicable, and no power distribution limits  were exceeded.
This was the second occurrence for CEA n19. Ho cause was determined for the first occurrence reported by LER 335-78-18. No other dropped CEA's have been  specifically attributed to    a timer module failure, however, two other occurrences were corrected    by  replacing components including the timer module.
    'L
~ s}}

Latest revision as of 10:06, 4 February 2020

LER 79-019/03L-0 on 790605:control Element Assembly Dropped Four Times within 2-h Period.Caused by Failure of Coil Power Programmer Timing Module.Module Replaced
ML17266A083
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 07/03/1979
From: Schoppman M
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML17206A897 List:
References
LER-79-019-03L-01, LER-79-19-3L-1, NUDOCS 7907120641
Download: ML17266A083 (3)


Text

.4. 5 NRC FOAM Sdi U.*NUCLEAR RSGULATQRY COMMISSION Il 771 LICENSE:" EVENT REPORT CQNTROL SLCCXI IQI (PLSASS PRINT OR TYPe ALL RKQUIRSO INPORMATIQNI I~4 I

I

~FLI 5 LI5111,Q, 0 01. I ' I I- IJ 4 I Q ~

5'.0J~

1 9 UCSV$ 45 CQCS I~ UC$ 454 vuMBSR 1$ 5 L4CSVSC YPS 14 55 Ms $ 3 C N'T

";; IL IS tl 54 41 5 tll0 0 COCK ST NUAISSJI 31 3 ii iVSNT OATS IS Qa 1$

1 r RiPCAT OATS.

t i

$4 Q9 aslaNT OESCRIPTIQN ANO PROSASLS CQ04SRQUasVCcS Qlo 0 I 2 llhile in the start u mode followin a refuelin ou a e CEA 419 dro ed four times within a two hour period. After each of the first three drops CEA'II'19 was restored to its normal position within the time limit speci-fied by Technical Specification 3.1.3.1.e, action statement l. After the fourth drop the coil power programmer timing module was'replaced and CEA il19 was returned to its normal position within the time l.imit speci-

~0 fied by Technical Specification 3.1.3.1.e and has performed normally.

1 3 9 COMP, 5Y5TSAI CAUSS CAUSS VALVS C Oi CQC4 SUSCOOS CCMPONSNT C004 SUSCQOa SuaCQQS

~09 1 5 9 IJ~SS ISIS IO II LSJS I1

~tl IS s I IS S MJS 19 WzS 14 54QUSNTIAL OCCURRSiVCS RSPORT R SVISIQN 1111 19 14

Js 14 14 " 11 $

ATT5AO<MSNT VPROA PRIMS CCMR

' 4 ACTION FUTURS SPFSC ~ SssVTOCWN

's 5'JPPUCR LJs ~~'

A TICJI . CN PLANT SIST>00 - IIQURS Q22 SVSMITT 0 PQR.'ASVB JJIANUFAC,URSA COMPONSNT'AJISN M~sMis JJs $4 14 JJJ1 41 13 ~<> 41 CAUSC OSSCRIPTION ANO COAASLC0 IV8 ACTIONS Q2>

CEA 819 dro ped due to a failure of the coil ower ro rammer timin module. No cause or failure mode has been determined. The timer module was replaced and CEA 819 performed normally. No other corrective action is required.

1 5

PACIU Y.

3 ATU5

~

C Qs ~00 45 PC%SR 0 Qs NA OTIISR STATUS

~

IQ,uSTNOO OP OISCQVSRY

~JJ rQl Operator:"QisSerVP>on" 0 3 5 IO I'1 IS 44 4$

CCNTL IT ACTIVITY RCLS+$ 40 QP RSL~S AMOUNTQP ACTIVITYQ35 O'A

'k NA I QCATICN OP RSLSASS Q 4 ~Z Q22 ~ZQ2$

I4 I1 <$

1 3 9 PSR50NNSL 4'APOSVISSS

~o7 II'"0 IQ33 "z'rQs '"'"""NT

~~ 5 3 II 11 11 PSRSCNNSL INIURISS 3 9

~00 0 Qs II I1 NA 1

LCSS QP CR OANAC1 0 PACIUTV Q2

~Z'QA2 NA 1 3 IO 34 PU8UC:1 OSSCPIPT:CN GS 7' NRC 444 QPILV HEI 3 ISSV30 l

5 0 !4 HA I ' l l I I I I I'!

PIAAIF OP PR-PARSR M. A. Scho pman , N..(305) 552-2802

REPORTABLE OCCURRENCE 335-79-19 LICENSEE EVENT REPORT PAGE 2 ADDITIONAL EYENT DESCRIPTION The coil power programmer timer module was replaced after CEA >19 dropped for the fourth time within a two hour period. CEA 819 was returned to its normal position and has performed normally for 3 weeks.

Since the reactor was at zero power (Mode 2) at the time of this occur-rence, Technical Specification 3.2 was not applicable, and no power distribution limits were exceeded.

This was the second occurrence for CEA n19. Ho cause was determined for the first occurrence reported by LER 335-78-18. No other dropped CEA's have been specifically attributed to a timer module failure, however, two other occurrences were corrected by replacing components including the timer module.