Line 14: Line 14:
| page count = 2
| page count = 2
| project = TAC:ME3959
| project = TAC:ME3959
| stage = Other
| stage = Response to RAI
}}
}}



Revision as of 05:18, 3 April 2018

Seabrook Station - Response to Request for Additional Information for the Review of the Seabrook Station License Renewal Application Severe Accident Mitigation Alternatives Review
ML14034A019
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 01/22/2014
From: Walsh K T
NextEra Energy Seabrook
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
SBK-L-14006, TAC ME3959
Download: ML14034A019 (2)


Text

NExTeraEN ERGY-SEABROKJanuary 22, 2014SBK-L-14006Docket No. 50-443U.S. Nuclear Regulatory CommissionAttention: Document Control DeskOne White Flint North11555 Rockville PikeRockville, MD 20852Seabrook StationResponse to Request for Additional Information for the Review of the Seabrook StationLicense Renewal Application Severe Accident Mitigation Alternatives ReviewReferences:1. NextEra Energy Seabrook, LLC letter SBK-L-10077, "Seabrook Station Application forRenewed Operating License," May 25, 2010. (Accession Number ML101590099)2. NRC Letter, Request for Additional Information for the Review of the SeabrookStation License Renewal Application-Severe Accident Mitigation AlternativesReview (Tag No. ME3959), December 27, 2013, (Accession Number ML13353A536)In Reference 1, NextEra Energy Seabrook, LLC (NextEra) submitted an application for arenewed facility operating license for Seabrook Station Unit 1 in accordance with the Code ofFederal Regulations, Title 10, Parts 50, 51, and 54.In Reference 2 the staff requested additional information to support the review of the SevereAccident Mitigation Alternatives. Enclosure 1 provides the NextEra responses to the requestedadditional information.If there are any questions or additional information is needed, please contact Mr. Edward JCarley, N. Engineering Supervisor -License Renewal, at (603) 773-7957. If you have anyquestions regarding this correspondence, please contact Mr. Michael Ossing, Licensing Manager,at (603) 773-7512.NextEra Energy Seabrook, LLC,.P.O. Box 300, Lafayette Road, Seabrook, NH 03874 SBK-L-14006U.S. Nuclear Regulatory Commission/Page 2I declare under penalty of perjury that the foregoing is true and correct.Executed on January J, 2014Kevin T. WalshSite Vice PresidentNextEra Energy Seabrook, LLCEnclosurecc: W.M. DeanJ. G. LambP. C. CataldoR. A. PlasseL. M. JamesNRC Region I AdministratorNRC Project ManagerNRC Senior Resident InspectorNRC Project Manager, License RenewalNRC Project Manager, License RenewalMr. Perry PlummerDirector Homeland Security and Emergency ManagementNew Hampshire Department of SafetyDivision of Homeland Security and Emergency ManagementBureau of Emergency Management33 Hazen DriveConcord, NH 03305Mr. John Giarrusso, Jr., Nuclear Preparedness ManagerThe Commonwealth of MassachusettsEmergency Management Agency400 Worcester RoadFramingham, MA 01702-5399