{{#Wiki_filter:November 29, 2021 Ms. Elise Malek Licensing Manager Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, SC 29061-9121 USA
{{#Wiki_filter:November 29, 2021
 
Ms. Elise Malek Licensing Manager Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, SC 29061-9121 USA


==SUBJECT:==
==SUBJECT:==
WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM-1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)
WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM -1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)


==Dear Ms. Malek:==
==Dear Ms. Malek :==
The U.S. Nuclear Regulatory Commission (NRC) staff has revised the schedule for its review of Westinghouse Electric Company, LLCs (WECs) license renewal application for its Columbia Fuel Fabrication Facility (CFFF) in Hopkins, South Carolina. The attached revised schedule reflects the NRCs decision to re-open and extend the public comment period for the draft environmental impact statement (EIS) for the license renewal of the CFFF. The draft EIS comment period was originally scheduled to close on September 20, 2021 Federal Register (86 FR 43276). After careful consideration of requests from external stakeholders to extend the draft EIS comment period, the NRC decided to re-open and extend the comment period for an additional 60 days. The draft EIS comment period closed on November 19, 2021 (86 FR 53694).


The U.S. Nuclear Regulatory Commission (NRC) staff has revised the schedule for its review of Westinghouse Electric Company, LLCs (WECs) license renewal application for its Columbia Fuel Fabrication Facility (CFFF) in Hopkins, South Carolina. The attached revised schedule reflects the NRCs decision to re-open and extend the public comment period for the draft environmental impact statement (EIS) for the license renewal of the CFFF. The draft EIS comment period was originally scheduled to close on September 20, 2021 Federal Register (86 FR 43276). After careful consideration of requests from external stakeholders to extend the draft EIS comment period, the NRC decided to re-open and extend the comment period for an additional 60 days. The draft EIS comment period closed on November 19, 2021 (86 FR 53694).
The NRC staff now plans to publish the final EIS in April 2022, the safety evaluation report, and the licensing decision after the Record of Decision is published by early June 2022. The EIS schedule is based on the EIS process, as required by Title 10 of the Code of Federal Regulations (10 CFR) Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, and the status of the ongoing environmental review and Westinghouses Phase II Remedial Investigation (RI) Work Plan under the Consent Agreement with the South Carolina Department of Health and Environmental Control. As stated in previous schedule letters, the execution of the RI Work Plan represents a risk to the EIS schedule. The NRC staff continues to encourage Westinghouse to keep the NRC staff informed of any changes to the RI activities and schedule.
The NRC staff now plans to publish the final EIS in April 2022, the safety evaluation report, and the licensing decision after the Record of Decision is published by early June 2022. The EIS schedule is based on the EIS process, as required by Title 10 of the Code of Federal Regulations (10 CFR) Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, and the status of the ongoing environmental review and Westinghouses Phase II Remedial Investigation (RI) Work Plan under the Consent Agreement with the South Carolina Department of Health and Environmental Control. As stated in previous schedule letters, the execution of the RI Work Plan represents a risk to the EIS schedule. The NRC staff continues to encourage Westinghouse to keep the NRC staff informed of any changes to the RI activities and schedule.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this communication will be available electronically for public inspection in the NRC Public Document Room, or from the NRCs ADAMS. ADAMS is accessible from the NRC Web site at: http://www.nrc.gov/readingrm/adams.html.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this communication will be available electronically for public inspection in the NRC Public Document Room, or from the NRCs ADAMS. ADAMS is accessible from the NRC Web site at: http://www.nrc.gov/readingrm/adams.html.


E. Malek                                   2 If you have any questions regarding the license renewal review, please contact me at 301-415-8740 or via email at David.Tiktinsky@nrc.gov.
E. Malek 2
Sincerely, David H.                Digitally signed by David H.
 
Tiktinsky Tiktinsky              Date: 2021.11.29 14:46:51
If you have any questions regarding the license renewal review, please contact me at 301-415-8740 or via email at David.Tiktinsky@nrc.gov.
                                                                      -05'00' David H. Tiktinsky, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 70-1151 License No.: SNM-1107
 
Sincerely,
 
David H. Tiktinsky, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards
 
Docket No.: 70- 1151 License No.: SNM-1107


==Enclosure:==
==Enclosure:==
Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule


Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule cc: K. Taylor, South Carolina DHEC westinghouse_ff@listmgr.nrc.gov
cc: K. Taylor, South Carolina DHEC westinghouse_ff@listmgr.nrc.gov


E. Malek                                   3
E. Malek 3


==SUBJECT:==
==SUBJECT:==
WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM-1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)
WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM -1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)
DATE:        November 29, 2021 DISTRIBUTION:
Public                DFM r/f JTappert, NMSS        TVukovinsky, RII    LWilkins, OCA              JTrefethen, NMSS CRegan, NMSS          KCoyne, NMSS        JWeil, OCA                  JGwo, NMSS SHelton, NMSS          EMichel, RII        DGasperson, RII JTappert, NMSS        DMcIntyre, OPA      LClark, OGC ADAMS Accession Number: ML21306A364                                                *via email NMSS/REFS/      NMSS/DFM/      NMSS/REFS/      NMSS/DFM/          NMSS/DFM/
OFFICE ERMB/PM*        FFLB/LA*      ERMB/BC*        FFLB/PM*            FFLB/BC*
NAME      DDiaz-Toro        ELee          JQuintero      DTiktinsky        JZimmerman DATE      10/19/2021      11/03/2021      11/15/2021      11/8/2021          11/17/2021 OFFICIAL RECORD COPY


Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule Docket 70-1151 License SNM -1107 Milestone                             Previous Date                   Revised Date Notice of Intent to prepare an                           July 31, 2020(A)               July 31, 2020(A) environmental impact statement (EIS) and begin the scoping process published in the Federal Register (85 FR 46193)
DATE: November 29, 2021
End of 30-day scoping comment period                   August 31, 2020(A)             August 31, 2020(A)
 
Issuance of NRCs Requests for Additional             November 3, 2020(A)           November 3, 2020 (A)
DISTRIBUTION:
Public DFM r/f JTappert, NMSS TVukovinsky, RII LWilkins, OCA JTrefethen, NMSS CRegan, NMSS KCoyne, NMSS JWeil, OCA JGwo, NMSS SHelton, NMSS EMichel, RII DGasperson, RII JTappert, NMSS DMcIntyre, OPA LClark, OGC
 
ADAMS Accession Number: ML21306A364 *via email OFFICE NMSS/REFS/ NMSS/DFM/ NMSS/REFS/ NMSS/DFM/ NMSS/DFM/
ERMB/PM* FFLB/LA* ERMB/BC* FFLB/PM* FFLB/BC*
NAME DDiaz-Toro ELee JQuintero DTiktinsky JZimmerman DATE 10/19/2021 11/03/2021 11/15/2021 11/8/2021 11/17/2021 OFFICIAL RECORD COPY
 
Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule
 
Docket 70- 1151 License SNM -1107
 
Milestone Previous Date Revised Date Notice of Intent to prepare an July 31, 2020(A) July 31, 2020(A) environmental impact statement (EIS) and begin the scoping process published in the Federal Register (85 FR 46193)
End of 30-day scoping comment period August 31, 2020(A) August 31, 2020(A)
Issuance of NRCs Requests for Additional November 3, 2020(A) November 3, 2020 (A)
Information (RAIs)
Information (RAIs)
WECs Responses to NRCs RAIs                           December 18, 2020           December 18, 2020(A)
WECs Responses to NRCs RAIs December 18, 2020 December 18, 2020(A)
(A)
(A)
Publication of Draft EIS1 for a 45-day                     July 2021(A)                   July 2021(A) comment period Publication of the Final EIS                             February 2022 (T)                 April 2022(T)
Publication of Draft EIS1 for a 45-day July 2021(A) July 2021(A) comment period Publication of the Final EIS February 2022 (T) April 2022(T)
Licensing Decision and Record of                           March 2022(T)                   June 2022(T)
Licensing Decision and Record of March 2022(T) June 2022(T)
Decision 2 (T) - Target (A) - Actual 1 The draft EIS anticipated publication date assumed a 30-day RAI response time.
Decision2 (T) - Target (A) - Actual
 
1 The draft EIS anticipated publication date assumed a 30- day RAI response time.
2 The NRC, per 10 CFR 51.100(a)(ii), must wait 30 days after publication of the U.S. Environmental Protection Agencys Federal Register Notice announcing the issuance of the final EIS.
2 The NRC, per 10 CFR 51.100(a)(ii), must wait 30 days after publication of the U.S. Environmental Protection Agencys Federal Register Notice announcing the issuance of the final EIS.
Enclosure}}
Enclosure}}

Latest revision as of 12:49, 19 November 2024

Westinghouse License Renewal Schedule Change Letter
ML21306A364
Person / Time
Site: Westinghouse
Issue date: 11/29/2021
From: David Tiktinsky
NRC/NMSS/DFM/FFLB
To: Malek E
Westinghouse Columbia Fuel Fabrication
Jenny Tobin NMSS/DFM/FFLB 301-415-2328
References
Download: ML21306A364 (4)


Text

November 29, 2021

Ms. Elise Malek Licensing Manager Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, SC 29061-9121 USA

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM -1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)

Dear Ms. Malek :

The U.S. Nuclear Regulatory Commission (NRC) staff has revised the schedule for its review of Westinghouse Electric Company, LLCs (WECs) license renewal application for its Columbia Fuel Fabrication Facility (CFFF) in Hopkins, South Carolina. The attached revised schedule reflects the NRCs decision to re-open and extend the public comment period for the draft environmental impact statement (EIS) for the license renewal of the CFFF. The draft EIS comment period was originally scheduled to close on September 20, 2021 Federal Register (86 FR 43276). After careful consideration of requests from external stakeholders to extend the draft EIS comment period, the NRC decided to re-open and extend the comment period for an additional 60 days. The draft EIS comment period closed on November 19, 2021 (86 FR 53694).

The NRC staff now plans to publish the final EIS in April 2022, the safety evaluation report, and the licensing decision after the Record of Decision is published by early June 2022. The EIS schedule is based on the EIS process, as required by Title 10 of the Code of Federal Regulations (10 CFR) Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, and the status of the ongoing environmental review and Westinghouses Phase II Remedial Investigation (RI) Work Plan under the Consent Agreement with the South Carolina Department of Health and Environmental Control. As stated in previous schedule letters, the execution of the RI Work Plan represents a risk to the EIS schedule. The NRC staff continues to encourage Westinghouse to keep the NRC staff informed of any changes to the RI activities and schedule.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this communication will be available electronically for public inspection in the NRC Public Document Room, or from the NRCs ADAMS. ADAMS is accessible from the NRC Web site at: http://www.nrc.gov/readingrm/adams.html.

E. Malek 2

If you have any questions regarding the license renewal review, please contact me at 301-415-8740 or via email at David.Tiktinsky@nrc.gov.

Sincerely,

David H. Tiktinsky, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards

Docket No.: 70- 1151 License No.: SNM-1107

Enclosure:

Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule

cc: K. Taylor, South Carolina DHEC westinghouse_ff@listmgr.nrc.gov

E. Malek 3

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM -1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)

DATE: November 29, 2021

DISTRIBUTION:

Public DFM r/f JTappert, NMSS TVukovinsky, RII LWilkins, OCA JTrefethen, NMSS CRegan, NMSS KCoyne, NMSS JWeil, OCA JGwo, NMSS SHelton, NMSS EMichel, RII DGasperson, RII JTappert, NMSS DMcIntyre, OPA LClark, OGC

ADAMS Accession Number: ML21306A364 *via email OFFICE NMSS/REFS/ NMSS/DFM/ NMSS/REFS/ NMSS/DFM/ NMSS/DFM/

ERMB/PM* FFLB/LA* ERMB/BC* FFLB/PM* FFLB/BC*

NAME DDiaz-Toro ELee JQuintero DTiktinsky JZimmerman DATE 10/19/2021 11/03/2021 11/15/2021 11/8/2021 11/17/2021 OFFICIAL RECORD COPY

Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule

Docket 70- 1151 License SNM -1107

Milestone Previous Date Revised Date Notice of Intent to prepare an July 31, 2020(A) July 31, 2020(A) environmental impact statement (EIS) and begin the scoping process published in the Federal Register (85 FR 46193)

End of 30-day scoping comment period August 31, 2020(A) August 31, 2020(A)

Issuance of NRCs Requests for Additional November 3, 2020(A) November 3, 2020 (A)

Information (RAIs)

WECs Responses to NRCs RAIs December 18, 2020 December 18, 2020(A)

(A)

Publication of Draft EIS1 for a 45-day July 2021(A) July 2021(A) comment period Publication of the Final EIS February 2022 (T) April 2022(T)

Licensing Decision and Record of March 2022(T) June 2022(T)

Decision2 (T) - Target (A) - Actual

1 The draft EIS anticipated publication date assumed a 30- day RAI response time.

2 The NRC, per 10 CFR 51.100(a)(ii), must wait 30 days after publication of the U.S. Environmental Protection Agencys Federal Register Notice announcing the issuance of the final EIS.

Enclosure