January 28, 2021 Ms. Elise Malek Licensing Manager Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, SC 29061-9121 USA
SUBJECT:
U.S. NUCLEAR REGULATORY COMMISSIONS REVISED SCHEDULE FOR THE LICENSE RENEWAL REVIEW OF THE WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)
Dear Ms. Malek:
The U.S. Nuclear Regulatory Commission (NRC) staff has revised the schedule for its review of Westinghouse Electric Company, LLCs (WECs) license renewal application for its Columbia Fuel Fabrication Facility (SNM-1107) in Hopkins, South Carolina. By letter dated August 10, 2020 (Agencywide Documents Access and Management System [ADAMS] Accession No. ML20217L372), the NRC staff established a schedule for the environmental impact statement (EIS) and anticipated publication of the final EIS in November 2021 and completion of the license renewal review in December 2021. The EIS schedule was based on the EIS process, as required by Title 10 of the Code of Federal Regulations (10 CFR) Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, the status of the environmental review, and timely and high-quality responses to NRCs RAIs issued on November 3, 2020 (ADAMS Accession No. ML20275A251).
Additionally, the schedule considered Westinghouses tentative due dates for key milestones (ADAMS Accession No. ML20202A678) in the Phase II Remedial Investigation Work Plan activities under the Consent Agreement with the South Carolina Department of Health and Environmental Control (DHEC).
WEC submitted its responses to the NRC staffs RAIs on December 18, 2020 (ADAMS Accession No. ML20353A275) and, while the responses are complete, there are several RAI responses that refer to the Phase II Remedial Investigation Work Plan, which WEC is currently executing.
The enclosure to this letter provides the revised license renewal review schedule, including major milestones. The anticipated schedule can change depending on the findings of the ongoing technical review or other factors. Additionally, based on WECs responses to the RAIs, information requested will be included in the Phase II Interim Report anticipated to be submitted to South Carolina DHEC in September 2021. Therefore, the Phase II Interim Report represents a risk to the final EIS schedule. The NRC staff anticipates reviewing the report and will determine impacts, if any, to the development of the EIS and next steps. Accordingly, the NRC
E. Malek 2
staff continues to encourage Westinghouse to keep the NRC staff informed of any changes to the Phase II Interim Remedial Investigation activities and schedule.
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this communication will be available electronically for public inspection in the NRC Public Document Room, or from the NRCs ADAMS. ADAMS is accessible from the NRC Web site at: http://www.nrc.gov/readingrm/adams.html.
If you have any questions regarding the license renewal review, please contact me at 301-415-8740 or via email at David.Tiktinsky@nrc.gov.
Sincerely, David H. Tiktinsky, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 70-1151 License No.: SNM-1107
Enclosure:
Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule cc: K. Taylor, South Carolina DHEC westinghouse_ff@listmgr.nrc.gov David H. Tiktinsky Digitally signed by David H.
Tiktinsky Date: 2021.01.28 08:14:29 -05'00'
E. Malek 3
SUBJECT:
U.S. NUCLEAR REGULATORY COMMISSIONS REVISED SCHEDULE FOR THE LICENSE RENEWAL REVIEW OF THE WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)
DATED: January 28, 2021 DISTRIBUTION:
Public DFM r/f EMichel, RII LClark, OGC TVukovinsky, RII AKock, NMSS JMcManus, OGC JTrefethen, NMSS CRegan, NMSS JSaxton, NMSS KCoyne, NMSS JGwo, NMSS JTappert, NMSS DMcIntyre, OPA JWeil, OCA RHannah, RII LWilkins, OCA ADAMS Accession Number: ML21026A062
- via email OFFICE NMSS/REFS/
ERMB/PM*
NMSS/DFM/
FFLB/LA*
NMSS/REFS/
ERMB/BC*
NMSS/DFM/
FFLB/PM*
NMSS/DFM/
FFLB/BC (A)*
NAME DDiaz-Toro ELee JQuintero DTiktinsky KRamsey DATE 01/19/2021 01/27/2021 01/27/2021 01/ 27 /2021 01/ 27 /2021 OFFICIAL RECORD COPY
Enclosure U.S. Nuclear Regulatory Commission Revised License Renewal Schedule for the Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Docket 70-1151 SNM -1107 Milestone Previous Date Revised Date Notice of Intent to prepare an environmental impact statement (EIS) and begin the scoping process published in the Federal Register (85 FR 46193)
July 31, 2020(A)
July 31, 2020(A)
End of 30-day scoping comment period August 31, 2020(A)
August 31, 2020(A)
Issuance of NRCs Requests for Additional Information (RAIs)
September 2020(T)
November 3, 2020 (A)
WECs Responses to NRCs RAIs December 3, 2020 (T)
December 18, 2020(A)
Publication of Draft EIS1 for a 45-day comment period April 2021(T)
June 2021(T)
Publication of the Final EIS November 2021(T)
January 2022(T)
Licensing Decision and Record of Decision2 December 2021(T)
February 2022(T)
(T) - Target (A) - Actual 1 The draft EIS anticipated publication date assumed a 30-day RAI response time.
2 The NRC, per 10 CFR 51.100(a)(ii), must wait 30 days after publication of the U.S. Environmental Protection Agencys Federal Register Notice announcing that the issuance of the final EIS.