Annette Pope Site Director, Columbia Fuel Fabrication Facility Westinghouse Electric Company 5801 Bluff Road Hopkins, SC 29061
SUBJECT:
WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY -
INSPECTION SCHEDULE FOR CALENDAR YEAR 2025
Dear Annette Pope:
Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the Columbia Fuel Fabrication Facility in calendar year 2025. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.
Please note that any regional initiative or reactive inspections are not included in the schedule. If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Thomas Vukovinsky at (404) 997-4622 with any questions or concerns you may have regarding this letter or the inspection schedule.
This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html, and at the NRC Public Document Room, in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 07001151 License No. SNM-1107
Enclosure:
As stated cc w/ encl: Distribution via LISTSERV June 24, 2024 Signed by Michel, Eric on 06/24/24
SUNSI Review X
Non-Sensitive
Sensitive X
Publicly Available
Non-Publicly Available OFFICE RII/DFFI RII/DFFI RII/DFFI NAME T. Vukovinsky N. Peterka E. Michel DATE 6/21/2024 6/24/2024 6/24/2024
Enclosure 2025 U.S. NUCLEAR REGULATORY COMMISSION INSPECTION/ACTIVITY PLAN FOR COLUMBIA FUEL FABRICATION FACILITY Dates Number of Inspectors Description/Inspection Procedures (IPs)
March 10 - 14 3
Nuclear Criticality Safety 1 (IP 88015)
Fire Protection (IP 88055)
To Be Determined 1
Material Control and Accountability (MC&A)
Observation (Various IPs)
June 23 - 27 3
Operational Safety 1 (IP 88020)
Emergency Preparedness (IP 88050)
September 15 - 19 2
MC&A (Various IPs)
September 22 - 26 3
Nuclear Criticality Safety 2 (IP 88015)
Plant Modifications - Annual (IP 88070)
November 17 - 21 3
Operational Safety 2 (IP 88020)
Environmental Safety (IP 88045)