Westinghouse Submittal of Environmental Sampling and Monitoring Program for NRC Review and Approval
ML23114A359
Person / Time
Site: Westinghouse
Issue date: 04/24/2023
From: Donnelly P
Westinghouse
To:
Office of Nuclear Material Safety and Safeguards, Document Control Desk
Shared Package
ML23114A358 List:
References
LTR-RAC-23-31
Download: ML23114A359 (1)


Text

WESTINGHOUSE NON-PROPRIETARY CLASS 3 Westinghouse Electric Company LLC Columbia Fuel Site 5801 Bluff Road Hopkins, South Carolina 29061-9121 USA Director, Office of Nuclear Material Safety and Direct tel: 803-647-1957 Safeguards U. S. Nuclear Regulatory Commission e-mail: donnelpb@westinghouse.com Document Control Desk 11555 Rockville Pike Your ref:

Rockville, Maryland 20852-2738 Our ref: LTR-RAC-23-31 April 24, 2023

REFERENCE:

1) License SNM-1107, Docket 70-1151
2) Westinghouse letter to NRC dated October 21, 2022, Request to Amend License SNM-1107 and Submittal of SNM-1107 License Application Page Changes (ML22294A179, ML22294A181)

SUBJECT:

Westinghouse Submittal of Environmental Sampling and Monitoring Program for NRC Review and Approval On March 23, 2023, the South Carolina Department of Health and Environmental Control (SC-DHEC) approved the Final Remedial Investigation Report (RI) for the Columbia Fuel Fabrication Facility (CFFF).

Westinghouse Electric Company LLC (Westinghouse) is providing a copy of the Final Remedial Investigation (RI) Report for the CFFF Site as Enclosure 1. The SC-DHEC approval letter is included as . Accordingly, the CFFF environmental sampling and monitoring program (Section 10.1.4 and associated tables and figures of the SNM-1107 License Application) in Enclosure 3 is being submitted for NRC review and approval as required by SNM-1107, License Condition S-17 and Section 10.1.10.1 of the SNM-1107 License Application. No changes are proposed to the program. Revision 1 of the SNM-1107 License Application was previously submitted as an administrative update with page changes for Chapters 1, 2, 10 and 11 in accordance with SNM-1107 License Condition S-4 in Reference 2.

SC-DHEC and Westinghouse entered into a Consent Agreement (CA) in February 2019 to comprehensively assess and address the impact of current and historical operations at the CFFF. The agreement follows the state-equivalent Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) process. The first step of the CA was to complete an RI. The Final RI Report provides a comprehensive evaluation of existing onsite impacts to environmental media. The source, nature and extent of these impacts from past operations are well within the facility property boundary, and there is no evidence that these impacts have or will affect properties off-site in the future.

The second step of the CA is to complete a Feasibility Study (FS) to evaluate remedial alternatives for these limited impacts. The FS Work Plan will be submitted to SC-DHEC for approval no later than July 15, 2023.

Please note that due to file size limitations, Appendices Q, R, S and U in Enclosure 1 are not included in this submittal. Relevant data from these appendices is summarized in the report.

© 2023 Westinghouse Electric Company LLC All Rights Reserved

WESTINGHOUSE NON-PROPRIETARY CLASS 3 LTR-RAC-23-31 If you have any questions regarding the Final RI Report or the environmental sampling and monitoring program, please contact Nancy Parr, Manager, Environmental Protection at (803) 647-3338.

Patrick Donnelly Patrick Donnelly (Apr 24, 2023 11:00 EDT)

Patrick Donnelly Regulatory Affairs Manager Westinghouse Columbia Fuel Fabrication Facility Docket 07001151 License SNM-1107 : Final Remedial Investigation Report, dated February 28, 2023. : SCDHEC Approval Letter of Westinghouse RI Report, dated March 23, 2023 : Environmental Sampling and Monitoring Program Section of SNM-1107 License Application cc (w/o enclosures):

NRC, Ms. Jennifer Tobin NRC, Mr. Thomas Vukovinsky

WESTINGHOUSE NON-PROPRIETARY CLASS 3 LTR-RAC-23-31 Enclosure 1 Enclosure 1 Final Remedial Investigation Report for the CFFF Site (Non-Proprietary)

WESTINGHOUSE NON-PROPRIETARY CLASS 3 LTR-RAC-23-31 Enclosure 2 Enclosure 2 SCDHEC Approval Letter of Westinghouse RI Report, dated March 23, 2023 (Non-Proprietary)

WESTINGHOUSE NON-PROPRIETARY CLASS 3 LTR-RAC-23-31 Enclosure 3 Enclosure 3 Environmental Sampling and Monitoring Program Section of SNM-1107 License Application (Non-Proprietary)