|
|
(2 intermediate revisions by the same user not shown) |
Line 16: |
Line 16: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:DTE October 11, 2021 10 CFR 50.59 10 CFR 52 Appendix E 10 CFR 52.3 NRC3-21-0002 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 | | {{#Wiki_filter:October 11, 2021 DTE 10 CFR 50.59 10 CFR 52 Appendix E 10 CFR 52.3 |
| | |
| | NRC3-21-0002 |
| | |
| | U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 |
|
| |
|
| ==Reference:== | | ==Reference:== |
Line 22: |
Line 26: |
|
| |
|
| ==Subject:== | | ==Subject:== |
| DTE Electric Company Submittal of Fermi 3 Periodic Reports This submittal provides periodic Fermi 3 reports as required by NRC regulations and license conditions for a Part 52 combined license holder. This submittal provides the following report updates: | | DTE Electric Company Submittal of Fermi 3 Periodic Reports |
| | |
| | This submittal provides periodic Fermi 3 reports as required by NRC regulations and license conditions for a Part 52 combined license holder. This submittal provides the following report updates: |
| * Semi-Annual Departures Report | | * Semi-Annual Departures Report |
| * Semi-Annual Changes, Tests and Experiments Report | | * Semi-Annual Changes, Tests and Experiments Report |
| * Semi-Annual Schedule for Implementation of Operational Programs and other License Conditions Report | | * Semi-Annual Schedule for Implementation of Operational Programs and other License Conditions Report |
| * Annual Final Safety Analysis Report (FSAR) Update Semi-Annual Departures Report: During the period from April 12, 2021 to October 11, 2021, there were no plant-specific departures from the ESBWR DCD for Fermi 3. | | * Annual Final Safety Analysis Report (FSAR) Update |
| Semi-Annual Changes, Tests, and Experiments Report: During the period from April 12, 2021 to October 11, 2021, there were no changes, tests or experiments made pursuant to 10 CFR 50.59(c). | | |
| | Semi-Annual Departures Report: During the period from April 12, 2021 to October 11, 2021, there were no plant-specific departures from the ESBWR DCD for Fermi 3. |
| | |
| | Semi-Annual Changes, Tests, and Experiments Report: During the period from April 12, 2021 to October 11, 2021, there were no changes, tests or experiments made pursuant to 1 O CFR 50.59(c). |
| * Semi-Annual Schedule Update for Implementation of Operational Programs and Other License Conditions: During the period from April 12, 2021 to October 11, 2021, there were no schedule updates. The scheduled implementation dates for the operational programs remain as "To Be Determined" (TBD). | | * Semi-Annual Schedule Update for Implementation of Operational Programs and Other License Conditions: During the period from April 12, 2021 to October 11, 2021, there were no schedule updates. The scheduled implementation dates for the operational programs remain as "To Be Determined" (TBD). |
| | |
| Annual FSAR Update: No FSAR information has been revised, deleted, or added since the last submittal. Therefore, the previously submitted FSAR continues to be current. | | Annual FSAR Update: No FSAR information has been revised, deleted, or added since the last submittal. Therefore, the previously submitted FSAR continues to be current. |
| | USNRC NRC3-21-0002 Page2 |
| | |
| | If you have any questions, or need additional information, please contact me at (313) 235-0443. |
|
| |
|
| USNRC NRC3-21-0002 Page2 If you have any questions, or need additional information, please contact me at (313) 235-0443.
| |
| Sincerely, | | Sincerely, |
| .("l, '---- \ l~~ ~ | | . ("l, '---- \\ l~ ~ ~ |
| Michael K. Brandon, Manager Nuclear Development - Licensing DTE Electric Company CC: Michael Dudek, NRG Fermi 3 Project Branch Chief Demetrius Murray, NRG Fermi 3 Project Manager Fermi 2 Resident Inspector Andrea D. Veil, Director, NRG Office of Nuclear Reactor Regulation NRG Region Ill Regional Administrator NRG Region II Regional Administrator Supervisor, Electric Operators, Michigan Public Service Commission Michigan Department of Environmental Quality OWMRP, Radiological Protection Section Craig D. Sly, Dominion Energy, Inc. | | |
| | Michael K. Brandon, Manager Nuclear Development - Licensing DTE Electric Company |
| | |
| | CC: Michael Dudek, NRG Fermi 3 Project Branch Chief Demetrius Murray, NRG Fermi 3 Project Manager Fermi 2 Resident Inspector Andrea D. Veil, Director, NRG Office of Nuclear Reactor Regulation NRG Region Ill Regional Administrator NRG Region II Regional Administrator Supervisor, Electric Operators, Michigan Public Service Commission Michigan Department of Environmental Quality OWMRP, Radiological Protection Section Craig D. Sly, Dominion Energy, Inc. |
| Kent Halac, General Electric Art Zaremba, Duke Energy Steve Franzone, Florida Power and Light}} | | Kent Halac, General Electric Art Zaremba, Duke Energy Steve Franzone, Florida Power and Light}} |
Similar Documents at Fermi |
---|
Category:Letter
MONTHYEARIR 05000341/20240032024-11-0606 November 2024 Integrated Inspection Report 05000341/2024003 IR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000016/20240012024-11-0101 November 2024 Enrico Fermi Atomic Power Plant, Unit 1, NRC Inspection Report 05000016/2024001 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) 2024-09-09
[Table view] Category:Routine Status Report (Recurring Weekly/Monthly)
MONTHYEARML24299A1482024-10-11011 October 2024 DTE Electric Company Submittal of Fermi 3 Periodic Reports ML23124A2032023-04-10010 April 2023 DTE Electric Company Submittal of Fermi 3 Periodic Reports ML21307A0332021-10-11011 October 2021 DTE Electric Company Submittal of Fermi 3 Periodic Reports 2024-10-11
[Table view] |
Text
October 11, 2021 DTE 10 CFR 50.59 10 CFR 52 Appendix E 10 CFR 52.3
NRC3-21-0002
U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001
Reference:
Fermi 3 NRC Docket No.52-033 NRG License No. NPF-95
Subject:
DTE Electric Company Submittal of Fermi 3 Periodic Reports
This submittal provides periodic Fermi 3 reports as required by NRC regulations and license conditions for a Part 52 combined license holder. This submittal provides the following report updates:
- Semi-Annual Departures Report
- Semi-Annual Changes, Tests and Experiments Report
- Semi-Annual Schedule for Implementation of Operational Programs and other License Conditions Report
- Annual Final Safety Analysis Report (FSAR) Update
Semi-Annual Departures Report: During the period from April 12, 2021 to October 11, 2021, there were no plant-specific departures from the ESBWR DCD for Fermi 3.
Semi-Annual Changes, Tests, and Experiments Report: During the period from April 12, 2021 to October 11, 2021, there were no changes, tests or experiments made pursuant to 1 O CFR 50.59(c).
- Semi-Annual Schedule Update for Implementation of Operational Programs and Other License Conditions: During the period from April 12, 2021 to October 11, 2021, there were no schedule updates. The scheduled implementation dates for the operational programs remain as "To Be Determined" (TBD).
Annual FSAR Update: No FSAR information has been revised, deleted, or added since the last submittal. Therefore, the previously submitted FSAR continues to be current.
USNRC NRC3-21-0002 Page2
If you have any questions, or need additional information, please contact me at (313) 235-0443.
Sincerely,
. ("l, '---- \\ l~ ~ ~
Michael K. Brandon, Manager Nuclear Development - Licensing DTE Electric Company
CC: Michael Dudek, NRG Fermi 3 Project Branch Chief Demetrius Murray, NRG Fermi 3 Project Manager Fermi 2 Resident Inspector Andrea D. Veil, Director, NRG Office of Nuclear Reactor Regulation NRG Region Ill Regional Administrator NRG Region II Regional Administrator Supervisor, Electric Operators, Michigan Public Service Commission Michigan Department of Environmental Quality OWMRP, Radiological Protection Section Craig D. Sly, Dominion Energy, Inc.
Kent Halac, General Electric Art Zaremba, Duke Energy Steve Franzone, Florida Power and Light