|
|
(One intermediate revision by the same user not shown) |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:}} | | {{#Wiki_filter:PSL SLRA: Breakout Questions SLRA Section 2.4 - Structural Scoping and Screening |
| | |
| | Note: Breakout Questions are provided to the applicant and will be incorporated into the publicly-available audit report. |
| | |
| | Technical Reviewer Bryce Lehman 12/17 /21 Technical Branch Chief Joseph Colaccino 12/20/21 Breakout Session Date/Time To be filled in by PM |
| | |
| | Applicant Staff NRC staff To be filled out by PM during breakout |
| | |
| | Question SLRA SLRA Background / Issue Discussion Question / Request Outcome of Discussion Number Section Page (As applicable/needed) 1 2.4. 9 2.4 -20 SLRA Section 2.4.9 notes that water Explain if the intake screens enters the intake structure and passes are within in the scope of SLR. |
| | through stationary and traveling screens. If they are not within scope provide a technical SLRA Table 2.4-9 shows the structural justification. If they are in-scoping results for the intake structure but scope, identify the AMR that does not list intake screens as a addresses these components. |
| | component receiving an AMR. It also does not list filter as an intended function for any of the components in the table.}} |
Latest revision as of 23:58, 18 November 2024
Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: L-2021-063, Subsequent License Renewal Application Notification, L-2021-192, Subsequent Licensee Renewal Application, Revision 1, Appendix E, Applicant'S Environmental Report, L-2022-108, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Response, L-2023-026, Subsequent License Renewal Application - Aging Management Requests for Additional Information Set 4, ML21215A316, ML21351A238, ML21351A239, ML21351A241, ML21351A248, ML21354A837, ML21356A011, ML22010A094, ML22010A096, ML22010A097, ML22010A100, ML22012A263, ML22012A282, ML22012A391, ML22013A277, ML22013A282, ML22013A284, ML22013A288, ML22013A292, ML22013A293, ML22013A294, ML22013A295, ML22013A296, ML22013A297, ML22013A301, ML22013A302, ML22013A303, ML22013A304, ML22013A305, ML22013A307, ML22013A316, ML22013A317, ML22013A334, ML22188A086, ML23200A123
|
MONTHYEARL-2021-063, Subsequent License Renewal Application Notification2021-03-17017 March 2021 Subsequent License Renewal Application Notification Project stage: Other L-2021-064, Request for Exemption from the Schedular Requirements of 10 CFR 54.17 (C)2021-03-17017 March 2021 Request for Exemption from the Schedular Requirements of 10 CFR 54.17 (C) Project stage: Request ML21215A3192021-08-0303 August 2021 Appendix E - Applicant'S Environmental Report for St. Lucie Project stage: Request ML21215A3172021-08-0303 August 2021 Enclosure 2: Affidavits Supporting Withholding Proprietary Information from Public Disclosure Project stage: Request ML21215A3162021-08-0303 August 2021 Enclosure 1: Subsequent License Renewal Application Enclosures Summary Project stage: Other ML21215A3152021-08-0303 August 2021 Application for Subsequent Renewed Facility Operating Licenses Project stage: Request L-2021-192, Subsequent Licensee Renewal Application, Revision 1, Appendix E, Applicant'S Environmental Report2021-10-12012 October 2021 Subsequent Licensee Renewal Application, Revision 1, Appendix E, Applicant'S Environmental Report Project stage: Other ML22013A2772021-11-21021 November 2021 2.4 Structural Scoping and Screening Breakout Questions Project stage: Other ML21356A0112021-12-17017 December 2021 Trp 148.3 and 148.4 St Lucie SLRA Breakout Questions Project stage: Other ML21351A2382021-12-17017 December 2021 Trp 148.1 St. Lucie SLRA - Breakout Questions for TLAA Section 4.7.1 Rev. 1 Project stage: Other ML21351A2392021-12-17017 December 2021 Trp 14 St. Lucie SLRA - Buried Pipe Breakout Questions - Allik.Docx Project stage: Other ML21351A2412021-12-17017 December 2021 Trp 15 St. Lucie SLRA - Internal Coatings Breakout Questions - Allik Project stage: Other ML21351A2482021-12-17017 December 2021 Trp 26 St. Lucie SLRA - Fire Protection Breakout Questions Project stage: Other ML21354A8372021-12-20020 December 2021 Trp 11 St. Lucie SLRA Breakout Questions Project stage: Other ML22013A2962021-12-21021 December 2021 Trp 74 St. Lucie SLRA - Breakout Questions Project stage: Other ML22013A3012021-12-21021 December 2021 TRP60 St. Lucie SLRA - Breakout Questions Fatigue Monitoring Project stage: Other ML22013A3022021-12-21021 December 2021 Trp 143.1 St Lucie SLRA - Breakout Questions Class 1 Fatigue Project stage: Other ML22013A3032021-12-21021 December 2021 Trp 143.2 St Lucie SLRA - Breakout Questions Non-Class 1 Fatigue Project stage: Other ML22013A3042021-12-21021 December 2021 Trp 143.3 St Lucie SLRA - Breakout Questions EAF Project stage: Other ML22013A3052021-12-21021 December 2021 Trp 143.4 St Lucie SLRA - Breakout Questions HELB Project stage: Other ML22013A2972021-12-21021 December 2021 Trp 77 St. Lucie SLRA - Breakout Questions Corrosion Structural Project stage: Other ML22013A2822021-12-21021 December 2021 SLRA - Breakoutt Questions Corrosion OE Project stage: Other ML22013A2842021-12-21021 December 2021 Trp 18 St. Lucie SLRA - Breakout Questions Bolting Integrity Project stage: Other ML22013A2882021-12-21021 December 2021 Trp 23 & 147.8 St. Lucie SLRA - Breakout Questions Cranes AMP-TLAA Project stage: Other ML22013A2922021-12-21021 December 2021 Trp 41 St. Lucie SLRA - Breakout Questions Project stage: Other ML22013A2932021-12-21021 December 2021 Trp 45 St. Lucie SLRA - Breakout Questions Masonry Walls Project stage: Other ML22013A2942021-12-21021 December 2021 Trp 46 St. Lucie SLRA - Breakout Questions Structures Monitoring Project stage: Other ML22013A2952021-12-21021 December 2021 Trp 47 St. Lucie SLRA - Breakout Questions Project stage: Other ML21356A5772021-12-22022 December 2021 Slar Breakout Questions - Fire Protection Scoping and Screening Project stage: Approval ML22010A0942022-01-0404 January 2022 Trp 29 St. Lucie SLRA - Tank Breakout Project stage: Other ML22010A0962022-01-0505 January 2022 Trp 010 St Lucie SLRA - Boricacidcorrbreakoutq - Makar Project stage: Other ML22010A1002022-01-0707 January 2022 Trp 033 Psl Selective Leaching Breakout Questions - Allik Project stage: Other ML22010A0972022-01-0707 January 2022 Trp 038 Psl Internal Surfaces Breakout Questions - Allik Project stage: Other ML22012A2632022-01-10010 January 2022 Trp 3 - St. Lucie Psl SLRA Breakout Question Reactor Head Closure Stud Bolting Project stage: Other ML22012A2822022-01-10010 January 2022 TRP142- St. Lucie SLRA Section 4.2 - Breakout Questions Project stage: Other ML22013A3072022-01-11011 January 2022 Trp 084 St Lucie SLRA - Ssnial Scclombreakoutq Project stage: Other ML22013A3342022-01-11011 January 2022 TRP16 - St. Lucie SLRA Breakout Questions_Pwr Internals Project stage: Other ML22130A6542022-01-11011 January 2022, 21 January 2022 SLRA - Audit Report - Audit Questions Transmitted to Florida Power & Light (FPL) Project stage: Request ML22012A3912022-01-11011 January 2022 Scoping and Screening 2.3.3.2 & 2.3.3.4 St. Lucie SLRA - Breakout Questions Project stage: Other ML22013A3162022-01-12012 January 2022 Trp 020 - St. Lucie SLRA Breakout Questions_Occw Project stage: Other ML22013A3172022-01-12012 January 2022 Trp 030 - St. Lucie SLRA Breakout Questions_Fuel Oil Project stage: Other L-2022-043, Subsequent License Renewal Application Revision 1 - Supplement 12022-04-0707 April 2022 Subsequent License Renewal Application Revision 1 - Supplement 1 Project stage: Supplement L-2022-044, Subsequent License Renewal Application Revision 1, Supplement 22022-04-13013 April 2022 Subsequent License Renewal Application Revision 1, Supplement 2 Project stage: Supplement L-2022-071, Subsequent License Renewal Application Revision 1 - Supplement 32022-05-19019 May 2022 Subsequent License Renewal Application Revision 1 - Supplement 3 Project stage: Supplement L-2022-075, Subsequent License Renewal Application-Aging Management Requests for Additional Information (RAI) Set 1A Response and Request for Confirmation of Information (RCI) Set 1 Response2022-06-13013 June 2022 Subsequent License Renewal Application-Aging Management Requests for Additional Information (RAI) Set 1A Response and Request for Confirmation of Information (RCI) Set 1 Response Project stage: Request ML22188A0862022-07-0707 July 2022 SLRA - Audit Report Project stage: Other L-2022-108, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Response2022-07-11011 July 2022 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Response Project stage: Other L-2022-154, Subsequent License Renewal Application Revision 1, Supplement 42022-09-22022 September 2022 Subsequent License Renewal Application Revision 1, Supplement 4 Project stage: Supplement L-2022-165, Subsequent License Renewal Application - Aging Management Request for Additional Information (RAI) 4.3.1-1a(second Round) - Class 1 Fatigue Response2022-10-26026 October 2022 Subsequent License Renewal Application - Aging Management Request for Additional Information (RAI) 4.3.1-1a(second Round) - Class 1 Fatigue Response Project stage: Request ML22325A0672022-11-18018 November 2022 RAI Set 4 Project stage: Request 2022-01-04
[Table View] |
|
---|
Category:- No Document Type Applies
MONTHYEARML23067A0522023-03-0808 March 2023 SLRA - Scoping and Screening, Sections 2.3.3.2 and 2.3.3.4 ML22013A2932021-12-21021 December 2021 Trp 45 St. Lucie SLRA - Breakout Questions Masonry Walls ML21356A0112021-12-17017 December 2021 Trp 148.3 and 148.4 St Lucie SLRA Breakout Questions ML21351A2482021-12-17017 December 2021 Trp 26 St. Lucie SLRA - Fire Protection Breakout Questions ML22013A2772021-11-21021 November 2021 2.4 Structural Scoping and Screening Breakout Questions ML19203A0182019-07-22022 July 2019 Public Notice of Exigent License Amendment Request ML18127A9112018-05-0707 May 2018 Figure 10.4.9B-4, Fault Tree of Loop - Manual ML18127A9102018-05-0707 May 2018 Figure 10.4.9B-3, Fault Tree of Lfow - Manual ML17073A1252017-03-14014 March 2017 NRC 659 Public Meeting Feedback for Saint Lucie Unit 1 Regulatory Conference 03/21/2017 ML20294A1332017-02-17017 February 2017 Video of January 9, 2014 Flooding at St. Lucie ML20294A0722016-12-29029 December 2016 Video of January 9, 2014 Flooding at St. Lucie ML20294A1512016-12-22022 December 2016 Video of January 9, 2014 Flooding at St. Lucie ML14081A0132014-03-22022 March 2014 LTR-14-0153-1-Ticket - Ace Hoffman, the Animated Software Co. Email St. Lucie Plant - Steam Generator Tube Leak ML14063A1482014-02-27027 February 2014 LTR-14-0118-Ticket - Representative Kathy Castor Ltr. Deterioration of Steam Generator Tubes at St. Lucie Nuclear Power Plant - Troubling Press Report ML13364A2832013-12-30030 December 2013 Announcement of 2014 Generic Fundamentals Examination Administration Dates-Letter Dated Dec 30, 2013 ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12004A1092012-01-0202 January 2012 December 2011 Marine Turtle Captures ML11258A2652011-09-0404 September 2011 August 2011 Marine Turtle Captures L-2010-259, St. Lucie, Unit 1 - License Amendment Request for Extended Power Uprate, Attachment 5; Appendix B, Additional Codes and Methods2010-12-15015 December 2010 St. Lucie, Unit 1 - License Amendment Request for Extended Power Uprate, Attachment 5; Appendix B, Additional Codes and Methods ML1035604312010-12-15015 December 2010 St. Lucie, Unit 1 - License Amendment Request for Extended Power Uprate, Attachment 5; Appendix B, Additional Codes and Methods ML1019301952010-06-0909 June 2010 Onsite Ground/Surface Water Monitoring Questionnaire for St. Lucie L-2010-123, Substantial NPDES Permit Revision St. Lucie Plant Response to FDEP RFI 12010-06-0808 June 2010 Substantial NPDES Permit Revision St. Lucie Plant Response to FDEP RFI #1 ML1013201982010-05-11011 May 2010 Public Meeting - Attendees ML1019304602010-03-25025 March 2010 List of Historical Leaks and Spills at Us Commercial Nuclear Power Plants ML0933507512010-01-14014 January 2010 Temporary Instruction 2515/180, Managing Fatigue ML0806704192008-03-0707 March 2008 CDBI Findings ML0732400242007-10-25025 October 2007 Examples of Max Thermal Power License Conditions ML0709600032007-05-0303 May 2007 License Pages - Change to Renewed FOLs in Conjunction W/Order EA-06-037 and Revisions to Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan ML0634705992006-12-14014 December 2006 Plant Service List ML0620602852006-08-0303 August 2006 Letter Summary of SG Inspection Conference Call ML0622205302006-07-28028 July 2006 Cover Sheet - Warning - Investigative Material - St. Lucie Accurate Response ML0622205152006-07-28028 July 2006 Cover Sheet - Warning - Investigative Material - St. Lucie Termination & Violation ML0622205702006-07-28028 July 2006 Selected Pages from St. Lucie Unit 1 Updated Final Safety Analysis Report (Ufsar): Page 6.3-5 & Figure 6.2-28 Re Refueling Water Tank ML0622205192005-04-28028 April 2005 Index of Concerns - RII-2005-A-0056 ML0622206112005-04-19019 April 2005 Allegation Review Board Briefing Sheet and Allegation Report L-2005-012, Enclosure 2, St. Lucie Unit 2, Responses to NRC Requests for Additional Information on WCAP-16208-P, Revision 0, NDE Inspection Length for CE Steam Generator Tubesheet Region Explosive Expansions.2005-02-10010 February 2005 Enclosure 2, St. Lucie Unit 2, Responses to NRC Requests for Additional Information on WCAP-16208-P, Revision 0, NDE Inspection Length for CE Steam Generator Tubesheet Region Explosive Expansions. ML0503203862005-01-31031 January 2005 OI Report 2-2004-030, Synopsis - St. Lucie ML0510302632005-01-14014 January 2005 Enclosure C&D, FPL Conference Call Summary on SL2-15 Refueling Outage (Tac No. MC5538) ML0404104922004-02-20020 February 2004 Order EA-03-009 Service List ML0505404642004-02-0909 February 2004 Dynamic Web Page Printout Dated 02/09/2004 Regarding Applied Violations for Nuclear Power Plants ML0328009092003-10-0202 October 2003 NPF-16 Appendix C ML0328009612003-10-0202 October 2003 NPF-16 Appendix D ML0403506912003-08-27027 August 2003 DRS Open Items Status ML0403502122003-08-13013 August 2003 DRS Open Items Status ML0403506872003-08-0505 August 2003 DRS Open Item Status ML0317404292003-06-30030 June 2003 FPL Handout ML0306603132003-03-0606 March 2003 Attachment 1, NFPA Formal Interpretation Request Form ML0306603152003-03-0606 March 2003 Attachment 2, NFPA Formal Interpretation Request Form ML0306603192003-03-0606 March 2003 Attachment 3, NFPA Formal Interpretation Request Form ML0306603432003-03-0606 March 2003 Attachment 5, NFPA 2023-03-08
[Table view] |
Text
PSL SLRA: Breakout Questions SLRA Section 2.4 - Structural Scoping and Screening
Note: Breakout Questions are provided to the applicant and will be incorporated into the publicly-available audit report.
Technical Reviewer Bryce Lehman 12/17 /21 Technical Branch Chief Joseph Colaccino 12/20/21 Breakout Session Date/Time To be filled in by PM
Applicant Staff NRC staff To be filled out by PM during breakout
Question SLRA SLRA Background / Issue Discussion Question / Request Outcome of Discussion Number Section Page (As applicable/needed) 1 2.4. 9 2.4 -20 SLRA Section 2.4.9 notes that water Explain if the intake screens enters the intake structure and passes are within in the scope of SLR.
through stationary and traveling screens. If they are not within scope provide a technical SLRA Table 2.4-9 shows the structural justification. If they are in-scoping results for the intake structure but scope, identify the AMR that does not list intake screens as a addresses these components.
component receiving an AMR. It also does not list filter as an intended function for any of the components in the table.