ML24187A026: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:From:                   Michael Mahoney Sent:                   Wednesday, July 3, 2024 3:48 PM To:                     Dennis Earp (dennis.Earp@duke-energy.com)
{{#Wiki_filter:From: Michael Mahoney Sent: Wednesday, July 3, 2024 3:48 PM To: Dennis Earp (dennis.Earp@duke-energy.com)


==Subject:==
==Subject:==
Line 29: Line 29:
On April 17, 2024 (ML24094A328), the NRC staff notified you that your request had been accepted for review, and the NRC staff estimated it would complete the review by June 7, 2024, and require 105 hours.
On April 17, 2024 (ML24094A328), the NRC staff notified you that your request had been accepted for review, and the NRC staff estimated it would complete the review by June 7, 2024, and require 105 hours.


In the {{letter dated|date=April 17, 2024|text=April 17, 2024, letter}}, it was stated that additional clarity was needed in the areas of adverse impacts and defense-in-depth. A virtual audit was performed for the staff to gain an understanding of these areas. An audit plan was sent on April 22, 2024 (ML24113A252) and on May 22, 2024, an audit call was held. At the conclusion of the audit, the licensee informed the NRC that a supplement was to be sent to the NRC addressing the audit plan dated April 22, 2024. A supplement dated June 7, 2024 (ML24159A746) addressed the audit plan t     opics. The purpose of this email is to officially inform you that the NRC staff now expects to complete its review by July 28, 2024.
In the {{letter dated|date=April 17, 2024|text=April 17, 2024, letter}}, it was stated that additional clarity was needed in the areas of adverse impacts and defense-in-depth. A virtual audit was performed for the staff to gain an understanding of these areas. An audit plan was sent on April 22, 2024 (ML24113A252) and on May 22, 2024, an audit call was held. At the conclusion of the audit, the licensee informed the NRC that a supplement was to be sent to the NRC addressing the audit plan dated April 22, 2024. A supplement dated June 7, 2024 (ML24159A746) addressed the audit plan t opics. The purpose of this email is to officially inform you that the NRC staff now expects to complete its review by July 28, 2024.
If there are emergent complexities or challenges in our review that would result in a change to the estimated completion date or significant changes in the estimated hours, the reasons for the change, and a revised estimate will be communicated during routine interactions with the assigned project manager. The change in the estimated completion date was discussed with and approved by the Deputy Director for the Division of Operating Reactor Licensing.
If there are emergent complexities or challenges in our review that would result in a change to the estimated completion date or significant changes in the estimated hours, the reasons for the change, and a revised estimate will be communicated during routine interactions with the assigned project manager. The change in the estimated completion date was discussed with and approved by the Deputy Director for the Division of Operating Reactor Licensing.
If you have any questions, please contact me.
If you have any questions, please contact me.
Thanks Mike Mahoney Project Manager, LPL2-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Desk: (301)-415-3867 Mobile: (301)-250-0450 Email: Michael.Mahoney@nrc.gov
Thanks Mike Mahoney Project Manager, LPL2-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Desk: (301)-415-3867 Mobile: (301)-250-0450 Email: Michael.Mahoney@nrc.gov


Hearing Identifier: NRR_DRMA Email Number:       2545
Hearing Identifier: NRR_DRMA Email Number: 2545


Mail Envelope Properties   (SA1PR09MB948660CC527D1ECBB86148A8E5DD2)
Mail Envelope Properties (SA1PR09MB948660CC527D1ECBB86148A8E5DD2)


==Subject:==
==Subject:==
Change in Review Schedule - Harris RIPE Exemption (L-2024-LLE-0004)
Change in Review Schedule - Harris RIPE Exemption (L-2024-LLE-0004)
Sent Date:         7/3/2024 3:48:29 PM Received Date:     7/3/2024 3:48:33 PM From:               Michael Mahoney
Sent Date: 7/3/2024 3:48:29 PM Received Date: 7/3/2024 3:48:33 PM From: Michael Mahoney


Created By:         Michael.Mahoney@nrc.gov
Created By: Michael.Mahoney@nrc.gov


Recipients:
Recipients:
Line 48: Line 48:
Tracking Status: None
Tracking Status: None


Post Office:       SA1PR09MB9486.namprd09.prod.outlook.com
Post Office: SA1PR09MB9486.namprd09.prod.outlook.com


Files                     Size                   Date & Time MESSAGE                   2228                   7/3/2024 3:48:33 PM
Files Size Date & Time MESSAGE 2228 7/3/2024 3:48:33 PM


Options Priority:                 Normal Return Notification:       No Reply Requested:           No Sensitivity:               Normal Expiration Date:}}
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:}}

Latest revision as of 11:36, 4 October 2024

NRR E-mail Capture - Change in Review Schedule - Harris Risk-Informed Process for Evaluations Exemption (L-2024-LLE-0004)
ML24187A026
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 07/03/2024
From: Michael Mahoney
NRC/NRR/DORL/LPL2-2
To: Earp D
Duke Energy Progress
References
L-2024-LLE-0004
Download: ML24187A026 (2)


Text

From: Michael Mahoney Sent: Wednesday, July 3, 2024 3:48 PM To: Dennis Earp (dennis.Earp@duke-energy.com)

Subject:

Change in Review Schedule - Harris RIPE Exemption (L-2024-LLE-0004)

Hi Dennis,

By application dated February 6, 2024 (ML24037A284), as supplemented by letters dated April 3, 2024 (ML24058A246), and June 7, 2024 (ML24159A746), Duke Energy Progress, LLC (Duke or the licensee), pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.12, Specific exemptions, requested an exemption from certain requirements of 10 CFR 50.55a(h)(2), Protection systems, requiring protection systems meet the requirements of IEEE 279-1971, Criteria for Protection Systems for Nuclear Power Generating Stations, for Shearon Harris Nuclear Power Plant (Harris).

On April 17, 2024 (ML24094A328), the NRC staff notified you that your request had been accepted for review, and the NRC staff estimated it would complete the review by June 7, 2024, and require 105 hours0.00122 days <br />0.0292 hours <br />1.736111e-4 weeks <br />3.99525e-5 months <br />.

In the April 17, 2024, letter, it was stated that additional clarity was needed in the areas of adverse impacts and defense-in-depth. A virtual audit was performed for the staff to gain an understanding of these areas. An audit plan was sent on April 22, 2024 (ML24113A252) and on May 22, 2024, an audit call was held. At the conclusion of the audit, the licensee informed the NRC that a supplement was to be sent to the NRC addressing the audit plan dated April 22, 2024. A supplement dated June 7, 2024 (ML24159A746) addressed the audit plan t opics. The purpose of this email is to officially inform you that the NRC staff now expects to complete its review by July 28, 2024.

If there are emergent complexities or challenges in our review that would result in a change to the estimated completion date or significant changes in the estimated hours, the reasons for the change, and a revised estimate will be communicated during routine interactions with the assigned project manager. The change in the estimated completion date was discussed with and approved by the Deputy Director for the Division of Operating Reactor Licensing.

If you have any questions, please contact me.

Thanks Mike Mahoney Project Manager, LPL2-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Desk: (301)-415-3867 Mobile: (301)-250-0450 Email: Michael.Mahoney@nrc.gov

Hearing Identifier: NRR_DRMA Email Number: 2545

Mail Envelope Properties (SA1PR09MB948660CC527D1ECBB86148A8E5DD2)

Subject:

Change in Review Schedule - Harris RIPE Exemption (L-2024-LLE-0004)

Sent Date: 7/3/2024 3:48:29 PM Received Date: 7/3/2024 3:48:33 PM From: Michael Mahoney

Created By: Michael.Mahoney@nrc.gov

Recipients:

"Dennis Earp (dennis.Earp@duke-energy.com)" <dennis.Earp@duke-energy.com>

Tracking Status: None

Post Office: SA1PR09MB9486.namprd09.prod.outlook.com

Files Size Date & Time MESSAGE 2228 7/3/2024 3:48:33 PM

Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: