| {{#Wiki_filter:~July 11, 2024 Docket ID NRC-2024-0076 1 of 2 | | {{#Wiki_filter:~July 11, 2024 Docket ID NRC-2024-0076 1 of 2 |
|
| |
|
| Due to the imposed time constraints for comments today, I have submitted the full text of my statement to the NRC Docket and members of the press. I regret that the public will not have the opportunity to hear my complete comment today. | | Due to the imposed time constraints for comments today, I have submitted the full text of my statement to the NRC Docket and members of the press. I regret that the public will not have the opportunity to hear my complete comment today. |
| * My name is Alan Blind, and I am a resident of Baroda, Michigan. I am speaking on behalf of the residents of Palisades Park in Covert, Michigan. | | * My name is Alan Blind, and I am a resident of Baroda, Michigan. I am speaking on behalf of the residents of Palisades Park in Covert, Michigan. |
| Governor Whitmer supported continuing operations at Palisades, yet Entergy shut down the plant, surrendered its operating license, and sold it as "junk," suitable only for decommissioning. These actions should not be easily reversible. | | Governor Whitmer supported continuing operations at Palisades, yet Entergy shut down the plant, surrendered its operating license, and sold it as "junk," suitable only for decommissioning. These actions should not be easily reversible. |
| Holtec has proposed exploiting a loophole from a NRC denial letter concerning a 2019 Petition for Rulemaking for a fast and easy way to allow it to reload fuel and operate Palisades. | | Holtec has proposed exploiting a loophole from a NRC denial letter concerning a 2019 Petition for Rulemaking for a fast and easy way to allow it to reload fuel and operate Palisades. |
| If allowed, this will permit Holtec and the NRC to evaluate today's proceedings with very little public involvement under a "fast and simple" process. This process has already been used to allow NRC to agree with Holtec's "Motion for Secretary Order, denying public hearings" The petitioner appealed the Holtec proposed order to not allow public hearings; and captured our concern today: | | If allowed, this will permit Holtec and the NRC to evaluate today's proceedings with very little public involvement under a "fast and simple" process. This process has already been used to allow NRC to agree with Holtec's "Motion for Secretary Order, denying public hearings" The petitioner appealed the Holtec proposed order to not allow public hearings; and captured our concern today: |
| 411,2024 Docket ID NRC-2024-0076 2of2 | | 411,2024 Docket ID NRC-2024-0076 2of2 |
|
| |
|
| The device of exemption here is being invoked to camouflage the actual nature of the request, which is a license amendment. The exemption being sought would relieve Holtec from adhering to the core regulations the Atomic Entergy Act imposes to ensure safe regulation of commercial nuclear power plants in the interest of public health and safety, as well as environmental protection. | | The device of exemption here is being invoked to camouflage the actual nature of the request, which is a license amendment. The exemption being sought would relieve Holtec from adhering to the core regulations the Atomic Entergy Act imposes to ensure safe regulation of commercial nuclear power plants in the interest of public health and safety, as well as environmental protection. |
| Exemptions are for short-duration bypasses of NRC regulations, not for reversing a major licensing event. This request for permission to restart is a major change that requires full-blown ... licensing proceedings." | | Exemptions are for short-duration bypasses of NRC regulations, not for reversing a major licensing event. This request for permission to restart is a major change that requires full-blown... licensing proceedings." |
| Back to my comment today, The residents of Palisades Park and 1 request that the NRC General Counsel approve the current NRC staff interpretation of the Holtec/NRC's use of selected words, in part and in whole, taken out of context from the denial of "PRM-50-117", dated February 19, 2019. | | Back to my comment today, The residents of Palisades Park and 1 request that the NRC General Counsel approve the current NRC staff interpretation of the Holtec/NRC's use of selected words, in part and in whole, taken out of context from the denial of "PRM-50-117", dated February 19, 2019. |
| As a better approach, we request that the NRC agree with our Petition for Rulemaking to include an NRC Commission-approved process for returning a decommissioned plant to operational status. | | As a better approach, we request that the NRC agree with our Petition for Rulemaking to include an NRC Commission-approved process for returning a decommissioned plant to operational status. |
| Thank you. | | Thank you. |
| Who Am I? | | Who Am I? |
| * A.Alan Blind | | * A.Alan Blind |
| * 1975-1997: Site Vice President: American Electric Power Cook Nuclear | | * 1975-1997: Site Vice President: American Electric Power Cook Nuclear |
| * 1997 - 2002: Consolidated Edison of NY. Indian Point. Vice President Nuclear | | * 1997 - 2002: Consolidated Edison of NY. Indian Point. Vice President Nuclear |
| * 2002-2003: Ontario Power Generation: Pickering. Pickering One Restart | | * 2002-2003: Ontario Power Generation: Pickering. Pickering One Restart |
| * 2006 - 2013: Entergy Nuclear Operations. Palisades. Engineering Director. | | * 2006 - 2013: Entergy Nuclear Operations. Palisades. Engineering Director. |
|
| |
|
| Definition of "Is it Safe?". | | Definition of "Is it Safe?". |
|
| |
|
| My standard of safety is met when any nuclear plant, including Palisades, meets all NRG Design Criteria. | | My standard of safety is met when any nuclear plant, including Palisades, meets all NRG Design Criteria. |
|
| |
|
| 1 0CFR50 includes all of the NRG requirements, including Design Criteria. Current Design Standards includes all of the collective experience over the last 50 years of commercial power design. | | 1 0CFR50 includes all of the NRG requirements, including Design Criteria. Current Design Standards includes all of the collective experience over the last 50 years of commercial power design. |
| building and operations. | | building and operations. |
|
| |
|
| What are my concerns about a Palisades Restart? | | What are my concerns about a Palisades Restart? |
|
| |
|
| Broadly speaking, I have two concerns; 1) NRC Full Commission Must be Involved, and 2) project justification, cost and schedule. This is a mater of public interest given the use of Sta~e and Federal subsidies. ** | | Broadly speaking, I have two concerns; 1) NRC Full Commission Must be Involved, and 2) project justification, cost and schedule. This is a mater of public interest given the use of Sta~e and Federal subsidies. ** |
|
| |
|
| I petition the full NRG Commissioners to codify the process used to define the required, minimum design basis for Palisades. NRC staff recognizes there are no codified regulations for restarting, such as Palisades. Holtec is asking to use a modern process, meant for new plants, at the same time requesting a design basis that predated NRC design requirements, be used. This is unreasonable and the full commission needs to step in and define the startup process for Palisades. | | I petition the full NRG Commissioners to codify the process used to define the required, minimum design basis for Palisades. NRC staff recognizes there are no codified regulations for restarting, such as Palisades. Holtec is asking to use a modern process, meant for new plants, at the same time requesting a design basis that predated NRC design requirements, be used. This is unreasonable and the full commission needs to step in and define the startup process for Palisades. |
|
| |
|
| Basic project management requirements include firm scope definition. Given the large number of unknowns stemming from the lack of information of equipment condition, especially the steam generators, and unknown number of safety upgrades, and lack of an agreed upon design standard and NRC_ inspection program, it is impossible for any company to plan out, schedule and cost estimate a large project such a Holtec is proposing. Given even the current cost and schedule estimates, the project cannot possibly be in the state, federal, and rate payers interest.}} | | Basic project management requirements include firm scope definition. Given the large number of unknowns stemming from the lack of information of equipment condition, especially the steam generators, and unknown number of safety upgrades, and lack of an agreed upon design standard and NRC_ inspection program, it is impossible for any company to plan out, schedule and cost estimate a large project such a Holtec is proposing. Given even the current cost and schedule estimates, the project cannot possibly be in the state, federal, and rate payers interest.}} |
Letter Sequence Request |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
Results
Other: ML24152A134, ML24152A195, ML24152A199, ML24155A003, ML24155A010, ML24155A026, ML24163A055, ML24163A082, ML24163A083, ML24163A109, ML24163A147, ML24163A192, ML24163A239, ML24183A127, ML24183A128, ML24183A129, ML24183A130, ML24183A131, ML24183A132, ML24183A133, ML24183A134, ML24183A135, ML24183A136, ML24183A137, ML24183A138, ML24183A139, ML24183A140, ML24183A141, ML24183A142, ML24183A143, ML24183A144, ML24183A145, ML24183A146, ML24183A147, ML24183A148, ML24183A149, ML24183A150, ML24183A151, ML24183A153, ML24183A154, ML24183A155, ML24183A156, ML24183A157, ML24183A158, ML24183A159, ML24183A160, ML24183A161, ML24219A420
|
MONTHYEARPNP 2022-010, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2022-06-13013 June 2022 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel Project stage: Request ML23032A3992023-02-0101 February 2023 Regulatory Path to Reauthorize Power Operations Project stage: Request PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations Project stage: Request ML23107A1252023-03-16016 March 2023, 20 March 2023, 20 April 2023 Summary of March 20, 2023, Meeting with Holtec Decommissioning International, Llc Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant Project stage: Request ML23107A0652023-03-31031 March 2023 Revision 36 to Updated Final Safety Analysis Report Project stage: Request PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report Project stage: Request PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports Project stage: Request ML23171B1242023-05-19019 May 2023, 24 May 2023, 22 June 2023 Summary of May 24, 2023, Meeting with Holtec Decommissioning International, LLC Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant Project stage: Request PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 Project stage: Request PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments Project stage: Request PNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations Project stage: Request PNP 2024-001, License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-02-0909 February 2024 License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations Project stage: Request PNP 2024-005, License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-05-0101 May 2024 License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations Project stage: Request ML24178A0002024-05-21021 May 2024 U.S. Fish and Wildlife List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project Michigan Ecological Services Field Office Palisades Restart Review Project stage: Request ML24149A0022024-06-24024 June 2024 Federal Register Notice - Noi to Conduct Scoping and Develop an Environmental Assessment for the Palisades Nuclear Plant Reauthorization to Power Operation Project stage: Request ML24155A0262024-06-27027 June 2024 Jean A. Fleming, VP Licensing, Holtec-Palisades-NOI to Conduct Scoping Process and Prep an EA-EPID No. L-2024-LNE-0003; Docket 50-0255 Project stage: Other ML24163A1472024-06-28028 June 2024 Scott Hicks, FWS-Palisades-NOI to Conduct Scoping Process and Prepare an EA-EPID No. L-2024-LNE-0003-Docket No.50-0255 Project stage: Other ML24163A1092024-07-0101 July 2024 Tribal Letter-Grand Traverse Band Project stage: Other ML24152A1952024-07-0101 July 2024 Carin Speidel, Acting Division Director, Environmental Health - Palisades - Noi to Conduct Scoping Process and Prepare an EA EPID No. L-2024-LNE-0003, Docket No. 50-0255 Project stage: Other ML24152A1342024-07-0101 July 2024 Nancy Ann Whaley, Geneva Township-Palisades-NOI to Conduct Scoping Process and Prep an EA-EPID No. L-2024-LNE-0003-Docket No. 50-0255 Project stage: Other ML24152A1992024-07-0101 July 2024 Richie Garcia, Water Filtration Supervisor-Palisades-NOI to Conduct Scoping Process and Prepare an EA EPID No. L-2024-LNE-0003 Docket No. 50-0255 Project stage: Other ML24155A0032024-07-0101 July 2024 Kathy Kowal, Us EPA Region 5-Palisades-NOI to Cibdyct Scoping Process and Prepare an EA EPID L-2024-LNE-0003 Project stage: Other ML24155A0102024-07-0101 July 2024 Quentin L. Messer Jr., Michigan Econ-Palisades-NOI to Conduct Scoping Process and Prep an EA-EPID No. L-2024-LNE-0003 Docket No.50-0255P Project stage: Other ML24156A0222024-07-0101 July 2024 Initiation of Scoping Process to Prepare an Environmental Assessment for the Environmental Review of Holtec Decommissioning International, Llc’S Licensing and Regulatory Requests for Reauthorization of Power Operations at Palisades EPID L-2 Project stage: Approval ML24163A0552024-07-0101 July 2024 Rebecca Held Knoche NOAA-Palisades-NOI to Conduct Scoping Process and Prepare an EA - EPID No. L-2024-LNE-0003-Docket No. 50-0255 Project stage: Other ML24163A0822024-07-0101 July 2024 Ltr to J Loichinger Achp Re Initiation of Scoping Process, Section 106 Consult for Env Rev of HDI, LLC Request for Reauth of Power Operations at Palisades Nuclear Plant Project stage: Other ML24163A1922024-07-0101 July 2024 Jeremy Rubio, Dept of Env, Great Lakes and Energy, Kalamazoo District-Palisades-NOI to Conduct Scoping Process and Prepare an EA EPID No. L-2024-LNE-0003 Docket No.50-0255 Project stage: Other ML24163A0832024-07-0101 July 2024 Ltr to R Schumaker SHPO Re Initiation of Scoping Process, Section 106 Consult for Env Rev of HDI, LLC Request for Reauth of Power Operations at Palisades Nuclear Plant Project stage: Other ML24183A1372024-07-0101 July 2024 Tribal Letter-Lac Courte Oreilles Band of Lake Superior Chippewa Project stage: Other ML24163A2392024-07-0101 July 2024 Sara Thompson, Michigan DNR-Palisades-NOI to Conduct Scoping Process and Prepare an EPID No. L-2024-LNE-0003-Docket No. 50-0255 Project stage: Other ML24183A1572024-07-0101 July 2024 Tribal Letter - Saint Croix Chippewa Indians of Wisconsin Project stage: Other ML24183A1392024-07-0101 July 2024 Tribal Letter-Lac Vieux Desert Band of Lake Superior Chippewa Indians Project stage: Other ML24183A1582024-07-0101 July 2024 Tribal Letter Sault Ste. Marie Tribe of Chippewa Indians Project stage: Other ML24183A1502024-07-0101 July 2024 Tribal Letter - Prarie Band Potawatomi Nation Project stage: Other ML24183A1542024-07-0101 July 2024 Tribal Letter Red Cliff Band of Lake Superior Chippewa Indians Project stage: Other ML24183A1442024-07-0101 July 2024 Tribal Letter - Menominee Indian Tribe of Wisconsin Project stage: Other ML24183A1282024-07-0101 July 2024 Tribal letter-Bay Mills Indian Community Project stage: Other ML24183A1352024-07-0101 July 2024 Tribal Letter-Hannahville Indian Community Project stage: Other ML24183A1302024-07-0101 July 2024 Tribal Letter-Chippewa Cree Indians of the Rocky Boys Reservation Project stage: Other ML24183A1492024-07-0101 July 2024 Tribal Letter - Pokagon Band of Potawatomi Indians Project stage: Other ML24183A1312024-07-0101 July 2024 Tribal Letter-Citizen Potawatomi Nation Project stage: Other ML24183A1432024-07-0101 July 2024 Tribal Letter- Match-e-be-Nash-She-Wish Band of Pottawatomi Indians Project stage: Other ML24183A1402024-07-0101 July 2024 Tribal Letter-Leech Lake Band of Ojibwe Project stage: Other ML24183A1552024-07-0101 July 2024 Tribal Letter - Red Lake Band of Chippewa Indians Project stage: Other ML24183A1452024-07-0101 July 2024 Tribal Letter - Miami Tribe of Oklahoma Project stage: Other ML24183A1272024-07-0101 July 2024 Tribal Letter-Bad River Band of the Lake Superior Tribe of Chippewa Project stage: Other ML24183A1292024-07-0101 July 2024 Tribal Letter-Bois Forte Band Project stage: Other ML24183A1562024-07-0101 July 2024 Tribal Letter - Saginaw Chippewa Indian Tribe of Michigan Project stage: Other ML24183A1462024-07-0101 July 2024 Tribal letter-Mille Lacs Band of Ojibwe Project stage: Other ML24183A1482024-07-0101 July 2024 Tribal Letter - Ottawa Tribe of Oklahoma Project stage: Other 2023-04-19
[Table View] |
|
---|
Category:- No Document Type Applies
MONTHYEARML24219A3892024-07-11011 July 2024 Hardcopy Comments from Blind - Concerns About Palisades Restart ML24219A3932024-07-11011 July 2024 Restart Scoping Hybrid Public Meeting - In-person Sign-in Sheet ML24113A1612024-04-18018 April 2024 Results_File_Palisades CEDM, 0.5 Weld Width_1 (Redacted) ML24113A1502024-04-18018 April 2024 Released Set_Part 1_NRC-2020-000324 ML24113A1472024-04-18018 April 2024 Released Set_Part 2_NRC-2020-000324 ML24113A1512024-04-18018 April 2024 Released Set_Part 3_NRC-2020-000324 ML24113A1572024-04-18018 April 2024 Results_File_Palisades CEDM_5 (Redacted) ML24113A1552024-04-18018 April 2024 Rresults_File_Near Weld_3 (Redacted) ML24113A1542024-04-18018 April 2024 Results_File_Expanded Region_4 (Redacted) ML24113A1632024-04-18018 April 2024 Results_File_Palisades CEDM_1 (Redacted) ML24113A1602024-04-18018 April 2024 Results_File_Palisades CEDM_2 (Redacted) ML24113A1532024-04-18018 April 2024 Results_File_Expanded Region_2 (Redacted) ML24113A1592024-04-18018 April 2024 Results_File_Near Weld_2 (Redacted) ML24113A1622024-04-18018 April 2024 Results_File_Near Weld_1 (Redacted) ML24113A1562024-04-18018 April 2024 Results_File_Palisades CEDM_4 (Redacted) ML24113A1582024-04-18018 April 2024 Results_File_Palisades CEDM_3 (Redacted) ML24113A1652024-04-18018 April 2024 Results_File_Expanded Region_1 (Redacted) ML24113A1642024-04-18018 April 2024 Results_File_Expanded Region_3 (Redacted) ML21354A7602021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 15 of 18 ML21354A7462021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 1 of 18 ML21354A7492021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 4 of 18 ML21354A7562021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 11 of 18 ML21354A7572021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 12 of 18 ML21354A7592021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 14 of 18 ML21354A7612021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 16 of 18 ML21354A7632021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 18 of 18 ML21291A2372021-12-0303 December 2021 Proposed Issuance of an Order Approving a License Transfer Application for Which a Hearing Has Been Requested ML18354A4262018-12-20020 December 2018 Superseded Pages Amendment #16 ML18354A4282018-12-20020 December 2018 Superseded by Amendment #14 ML18354A4292018-12-20020 December 2018 Superseded by Amendment #12 Re Component Testing ML17166A4972017-05-0404 May 2017 Teleconference, Meeting Material for Steam Generator Tube Inspection Tube Inspection Discussion During Palisades 2017(1R25) Outage (Preliminary Information) CNRO-2016-00024, Entergy - Form 10-K for Fiscal Year Ended December 31, 20152016-12-20020 December 2016 Entergy - Form 10-K for Fiscal Year Ended December 31, 2015 ML16132A1752016-05-10010 May 2016 E-Mail: Palisades Nuclear Plant - Request for Information for Onsite Review 2016 002 (Msh) ML17080A4782016-05-0505 May 2016 EA-15-039;Confirmatory Order Consent and Hearing Waiver Form - Palisades ML16061A3722016-02-29029 February 2016 NFPA 805 Transition FAQ 14-0073 Revision 1 ML15028A5272015-01-28028 January 2015 Attachment 1 - Response to Request for Additional Information Regarding the License Amendment Request for Approval of Palisades Nuclear Plant 10 CFR Appendix G Equivalent Margins Analysis ML15014A1532015-01-14014 January 2015 Attachment 1- NEI Comments on NRC Working Group Recommendations to Revise the Substantive Cross-Cutting Issue Process ML15014A1602015-01-14014 January 2015 Attachment 2 - NRC Working Group Recommendations to Revise the Substantive Cross-Cutting Issue Process ML14316A1982014-11-12012 November 2014 Attachment 2 - Responses to Request for Additional Information Questions ML14316A1932014-11-12012 November 2014 Attachment 1 - Description and Assessment of Requested Change ML14311A5052014-11-0505 November 2014 NFPA 805 Transition FAQ 14-0073 Revision 0 ML14308A2472014-11-0404 November 2014 Attachment 1: Palisades Nuclear Plant, Response to Request for Additional Information License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactors ML14077A3672014-03-18018 March 2014 LTR-14-0141-1-Ticket - Michael Mulligan Ltr. Overhaul the Nuclear Regulatory Commission'S 2.206 Petition Process to Gain Transparency in Upcoming Palisades 2.206 Petition ML14071A0042014-03-12012 March 2014 OEDO-14-00145-Ticket - Mike Mulligan Ltr. 2.206 - Palisades ML13228A1982013-08-16016 August 2013 Meeting Audio Recording for July 16, 2013, Internet Event Briefing ML13169A2322013-06-18018 June 2013 G20130462/LTR-13-0528-Ticket - Senator Debbie Stabenow Ltr. Constituent Concerns Regarding Repairs at Palisades ML13077A3032013-03-18018 March 2013 for the Record-03-18-2013: Pressurized Thermal Shock and Palisades ML12177A3652012-06-20020 June 2012 Cyber Security, Attachment 5 to Pnp 2012-046, List of Regulatory Commitments ML12177A3632012-06-20020 June 2012 Cyber Security, Attachment 2 to Pnp 2012-046, Proposed Pnp Operating Change (Mark-up) ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status 2024-07-11
[Table view] |
Text
~July 11, 2024 Docket ID NRC-2024-0076 1 of 2
Due to the imposed time constraints for comments today, I have submitted the full text of my statement to the NRC Docket and members of the press. I regret that the public will not have the opportunity to hear my complete comment today.
- My name is Alan Blind, and I am a resident of Baroda, Michigan. I am speaking on behalf of the residents of Palisades Park in Covert, Michigan.
Governor Whitmer supported continuing operations at Palisades, yet Entergy shut down the plant, surrendered its operating license, and sold it as "junk," suitable only for decommissioning. These actions should not be easily reversible.
Holtec has proposed exploiting a loophole from a NRC denial letter concerning a 2019 Petition for Rulemaking for a fast and easy way to allow it to reload fuel and operate Palisades.
If allowed, this will permit Holtec and the NRC to evaluate today's proceedings with very little public involvement under a "fast and simple" process. This process has already been used to allow NRC to agree with Holtec's "Motion for Secretary Order, denying public hearings" The petitioner appealed the Holtec proposed order to not allow public hearings; and captured our concern today:
411,2024 Docket ID NRC-2024-0076 2of2
The device of exemption here is being invoked to camouflage the actual nature of the request, which is a license amendment. The exemption being sought would relieve Holtec from adhering to the core regulations the Atomic Entergy Act imposes to ensure safe regulation of commercial nuclear power plants in the interest of public health and safety, as well as environmental protection.
Exemptions are for short-duration bypasses of NRC regulations, not for reversing a major licensing event. This request for permission to restart is a major change that requires full-blown... licensing proceedings."
Back to my comment today, The residents of Palisades Park and 1 request that the NRC General Counsel approve the current NRC staff interpretation of the Holtec/NRC's use of selected words, in part and in whole, taken out of context from the denial of "PRM-50-117", dated February 19, 2019.
As a better approach, we request that the NRC agree with our Petition for Rulemaking to include an NRC Commission-approved process for returning a decommissioned plant to operational status.
Thank you.
Who Am I?
- 1975-1997: Site Vice President: American Electric Power Cook Nuclear
- 1997 - 2002: Consolidated Edison of NY. Indian Point. Vice President Nuclear
- 2002-2003: Ontario Power Generation: Pickering. Pickering One Restart
- 2006 - 2013: Entergy Nuclear Operations. Palisades. Engineering Director.
Definition of "Is it Safe?".
My standard of safety is met when any nuclear plant, including Palisades, meets all NRG Design Criteria.
1 0CFR50 includes all of the NRG requirements, including Design Criteria. Current Design Standards includes all of the collective experience over the last 50 years of commercial power design.
building and operations.
What are my concerns about a Palisades Restart?
Broadly speaking, I have two concerns; 1) NRC Full Commission Must be Involved, and 2) project justification, cost and schedule. This is a mater of public interest given the use of Sta~e and Federal subsidies. **
I petition the full NRG Commissioners to codify the process used to define the required, minimum design basis for Palisades. NRC staff recognizes there are no codified regulations for restarting, such as Palisades. Holtec is asking to use a modern process, meant for new plants, at the same time requesting a design basis that predated NRC design requirements, be used. This is unreasonable and the full commission needs to step in and define the startup process for Palisades.
Basic project management requirements include firm scope definition. Given the large number of unknowns stemming from the lack of information of equipment condition, especially the steam generators, and unknown number of safety upgrades, and lack of an agreed upon design standard and NRC_ inspection program, it is impossible for any company to plan out, schedule and cost estimate a large project such a Holtec is proposing. Given even the current cost and schedule estimates, the project cannot possibly be in the state, federal, and rate payers interest.