| | number = ML12054A062 | | | number = ML12054A062 |
| | issue date = 03/13/2012 | | | issue date = 03/13/2012 |
| | title = 11/03/2010 Summary of Public Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Related to Fire Protection | | | title = Summary of Public Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Related to Fire Protection |
| | author name = Poole J | | | author name = Poole J |
| | author affiliation = NRC/NRR/DORL/LPWB | | | author affiliation = NRC/NRR/DORL/LPWB |
Line 15: |
Line 15: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:... | | {{#Wiki_filter:...~",I\ REGu~ UNITED STATES |
| UNITED STATES NUCLEAR REGULATORY COMMISSION | | ~~v ~o." NUCLEAR REGULATORY COMMISSION |
| ! WASHINGTON, D.C. 20555-0001 | | ! ~0 WASHINGTON, D.C. 20555-0001 |
| <C : 0 :;; "" March 13, 2012 1-" ****i' Tennessee Valley Authority Watts Bar Nuclear Power Plant, Unit 2 | | <C |
| | ~ |
| | ~ |
| | ""1-" ~ March 13, 2012 |
| | ~o |
| | ****i' LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Power Plant, Unit 2 |
| | |
| | ==SUBJECT:== |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| OF NOVEMBER 3,2010, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNIT 2, FINAL SAFETY ANALYSIS REPORT SUBMITTALS On November 3,2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. | | OF NOVEMBER 3,2010, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNIT 2, FINAL SAFETY ANALYSIS REPORT SUBMITTALS On November 3,2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss outstanding issues relating to TVA's Final Safety Analysis Report (FSAR) submittals. |
| The purpose of the meeting was to discuss outstanding issues relating to TVA's Final Safety Analysis Report (FSAR) submittals. | | The NRC staff and TVA discussed information regarding the review of the Fire Protection Report, outstanding issues in FSAR Section 9 Auxiliary Systems, and the Individual Plant Examination for External Events (IPEEE) report review. |
| The NRC staff and TVA discussed information regarding the review of the Fire Protection Report, outstanding issues in FSAR Section 9 Auxiliary Systems, and the Individual Plant Examination for External Events (IPEEE) report review. During the discussion on the Fire Protection Report (FPR), the NRC and TVA staff discussed a new version of the FPR changes table and whether it contained an adequate level of detail. TVA stated that they would submit to the NRC the TVA generated summary of each of the changes for each revision of the FPR, as well as the summary and conclusions of the TVA documents justifying the changes (i.e., Safety Analyses-Safety Evaluations, License Condition Impact Evaluations). | | During the discussion on the Fire Protection Report (FPR), the NRC and TVA staff discussed a new version of the FPR changes table and whether it contained an adequate level of detail. |
| For the discussions on FSAR Section 9, TVA provided additional information on the design of the spent fuel pool cooling, component cooling water, and essential raw cooling water systems for duel unit operation as a followup to the meeting held on October 12, 2010. The NRC staff and TVA went over proposed requests for additional information on IPEEE. | | TVA stated that they would submit to the NRC the TVA generated summary of each of the changes for each revision of the FPR, as well as the summary and conclusions of the TVA documents justifying the changes (i.e., Safety Analyses-Safety Evaluations, License Condition Impact Evaluations). |
| -2 Members of the public did not participate in the meeting. Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov. Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391 cc: Distribution via Listserv | | For the discussions on FSAR Section 9, TVA provided additional information on the design of the spent fuel pool cooling, component cooling water, and essential raw cooling water systems for duel unit operation as a followup to the meeting held on October 12, 2010. |
| -Members of the public did not participate in the Please direct any inquiries to me at 301-415-2048 or Docket No. 50-391 cc: Distribution via Listserv DISTRIBUTION: | | The NRC staff and TVA went over proposed requests for additional information on IPEEE. |
| PUBLIC PMNS Resources RidsNrrPMWattsBar2 Resource RidsNrrDorlLp_WB Resource RidsNrrDorl Resource RHanna, RII ADAMS Accession No'.. MI 12045A062-IRAJ Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsRgn2MailCenter Resource LPWB R/F RidsNrrlLABClayton (Hard copy) RidsOpaMail Resource RidsAcrsAcnw_MailCTR Resource MKotzala, EDO RidsOgcMailCenter Resource RidsNrrOd Resource JLedford, RII CSteger, N R R OFFICE LPWB\PM LPWB\LA LPWB\BC NAME JPoole BClayton SCampbell DATE 03/07/12 03/07/12 03/13/12 OFFICIAL RECORD COpy}}
| | |
| | -2 Members of the public did not participate in the meeting. |
| | Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov. |
| | Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391 cc: Distribution via Listserv |
| | |
| | - 2 Members of the public did not participate in the meeting. |
| | Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov. |
| | IRAJ Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391 cc: Distribution via Listserv DISTRIBUTION: |
| | PUBLIC RidsRgn2MailCenter Resource LPWB R/F PMNS Resources RidsNrrlLABClayton (Hard copy) RidsOpaMail Resource RidsNrrPMWattsBar2 Resource RidsAcrsAcnw_MailCTR Resource MKotzala, EDO RidsNrrDorlLp_WB Resource RidsOgcMailCenter Resource RidsNrrOd Resource RidsNrrDorl Resource JLedford, RII CSteger, N RR RHanna, RII ADAMS Accession - |
| | No'.. MI 12045A062 OFFICE LPWB\PM LPWB\LA LPWB\BC NAME JPoole BClayton SCampbell DATE 03/07/12 03/07/12 03/13/12 OFFICIAL RECORD COpy}} |
|
---|
Category:Meeting Summary
MONTHYEARML24292A1832024-10-30030 October 2024 Summary of Meeting with Tennessee Valley Authority, October 16, 2024, to Discuss Proposed License Amendment Regarding Implementation of an Online Monitoring Methodology ML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24228A2652024-08-20020 August 2024 Summary of Public Pre-Submittal Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant and Watts Bar Nuclear Plant LAR Related to TS 3.5.2. ECCS - Operating ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24173A2122024-06-27027 June 2024 Summary of Public Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding Adoption of TSTF-276-A, Revision 2 to Clarify Requirements for Diesel Generator Testing ML24158A3002024-06-11011 June 2024 Summary of May 6, 2024, Public Meeting with Tennessee Valley Authority to Discuss the Potential for a License Amendment Request Regarding the Control Room Envelope and Selective Use of an Alternative Source Term ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24057A0582024-02-27027 February 2024 Summary of February 15, 2024, Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23265A1512023-09-28028 September 2023 Summary of September 12, 2023, Partially Closed Meeting with Tennessee Valley Authority to Discuss Proposed License Amendment Request ML23198A3102023-07-20020 July 2023 July 10, 2023, Summary of Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML23068A1532023-03-16016 March 2023 Summary of February 22, 2023, Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request to Increase Allowable Number of Tritium Producing Burnable Absorber Rods at Watts Bar Nuclear Plant, Units 1 and 2 ML23055A4562023-03-0909 March 2023 Summary of February 15, 2023, Public Meeting with Tennessee Valley Authority Regarding Proposed Expedited License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML22329A1382022-12-0505 December 2022 Summary of Meeting with Tennessee Valley Authority Related to Planned Alternative Request WBN-2-ISI-01 for Watts Bar Nuclear Plant, Unit 2 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22104A2252022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Exemption Request for Watts Bar Nuclear Plant, Unit 2 ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22042B3262022-02-14014 February 2022 Summary of February 8, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed License Amendment Request to Revise the Allowable Value for Trip of Turbine-Driven Main Feedwater Pump at Watts Bar Nuclear Plant, Unit 1 ML22025A3112022-02-0909 February 2022 Summary of January 19, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed Schedule for Development of a License Amendment Request for Increased Tritium Production ML21349A3642022-01-0404 January 2022 Summary of December 14, 2021, Teleconference with Tennessee Valley Authority Regarding a Proposed Change to the Capsule Withdrawal Schedule for Watts Bar Nuclear Plant, Unit 2 ML21279A0902021-11-0303 November 2021 Summary of Conference Calls Regarding the Fall 2021, Mid-Cycle Steam Generator Tube Inspections ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21245A4252021-09-15015 September 2021 Summary of August 19, 2021, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to the Watts Bar Nuclear Plant, Units 1 and 2 ML21253A0872021-09-15015 September 2021 Summary of August 19, 2021, Partially Closed Meeting with Tennessee Valley Authority to Discuss Mid-Cycle Outage Contingencies for Watts Bar Nuclear Plant, Unit 2 ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML21120A2192021-05-0404 May 2021 April 28,2021, Summary of Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, to Remove from Technical Specifications Redundant Units of Measurement for Control ML21099A2072021-04-13013 April 2021 Summary of April 7, 2021, Meeting with Tennessee Valley Authority Related to a Planned Relief Request from ASME Code Testing Requirements ML21060B0532021-03-0303 March 2021 Summary of February 11, 2021, Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2, to Apply a Temperature Adjusted Steam Generator Tube Flaw Growth Rate Methodology ML21033A5952021-02-23023 February 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar Nuclear Plant, Unit 2 Steam Generator Replacement ML20351A4212021-01-19019 January 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar, Unit 2, Steam Generator Replacement ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20351A2192021-01-11011 January 2021 Summary of Conference Calls Regarding the Fall 2020 Steam Generator Tube Inspections ML20337A0402020-12-15015 December 2020 Summary of November 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification 5.9.9, Steam Generator Tube Inspection Report ML20323A0662020-11-27027 November 2020 Summary of October 28, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification Surveillance Requirement 3.6.15.4, Shield Building ML20244A1892020-09-11011 September 2020 Summary of Teleconference Call with Tennessee Valley Authority Regarding a Proposed Change to the Containment Leakage Rate Testing Program ML20213C7112020-08-25025 August 2020 Summary of July 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned Alternative Request for Watts Bar Nuclear Plant, Unit 1 ML20233A8352020-08-25025 August 2020 Summary of August 11, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20211L8222020-08-10010 August 2020 Summary of Teleconference Call with the Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20150A4162020-06-24024 June 2020 Summary of May 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20153A3622020-06-22022 June 2020 Summary of May 27, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20143A1692020-05-28028 May 2020 Summary of May 14, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2 ML20135H2702020-05-28028 May 2020 Summary of May 5, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20034F5232020-02-12012 February 2020 Summary of Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 2024-09-23
[Table view] |
Text
...~",I\ REGu~ UNITED STATES
~~v ~o." NUCLEAR REGULATORY COMMISSION
! ~0 WASHINGTON, D.C. 20555-0001
<C
~
~
""1-" ~ March 13, 2012
~o
- i' LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Power Plant, Unit 2
SUBJECT:
SUMMARY
OF NOVEMBER 3,2010, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNIT 2, FINAL SAFETY ANALYSIS REPORT SUBMITTALS On November 3,2010, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss outstanding issues relating to TVA's Final Safety Analysis Report (FSAR) submittals.
The NRC staff and TVA discussed information regarding the review of the Fire Protection Report, outstanding issues in FSAR Section 9 Auxiliary Systems, and the Individual Plant Examination for External Events (IPEEE) report review.
During the discussion on the Fire Protection Report (FPR), the NRC and TVA staff discussed a new version of the FPR changes table and whether it contained an adequate level of detail.
TVA stated that they would submit to the NRC the TVA generated summary of each of the changes for each revision of the FPR, as well as the summary and conclusions of the TVA documents justifying the changes (i.e., Safety Analyses-Safety Evaluations, License Condition Impact Evaluations).
For the discussions on FSAR Section 9, TVA provided additional information on the design of the spent fuel pool cooling, component cooling water, and essential raw cooling water systems for duel unit operation as a followup to the meeting held on October 12, 2010.
The NRC staff and TVA went over proposed requests for additional information on IPEEE.
-2 Members of the public did not participate in the meeting.
Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.
Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391 cc: Distribution via Listserv
- 2 Members of the public did not participate in the meeting.
Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.
IRAJ Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsRgn2MailCenter Resource LPWB R/F PMNS Resources RidsNrrlLABClayton (Hard copy) RidsOpaMail Resource RidsNrrPMWattsBar2 Resource RidsAcrsAcnw_MailCTR Resource MKotzala, EDO RidsNrrDorlLp_WB Resource RidsOgcMailCenter Resource RidsNrrOd Resource RidsNrrDorl Resource JLedford, RII CSteger, N RR RHanna, RII ADAMS Accession -
No'.. MI 12045A062 OFFICE LPWB\PM LPWB\LA LPWB\BC NAME JPoole BClayton SCampbell DATE 03/07/12 03/07/12 03/13/12 OFFICIAL RECORD COpy