ML112430571: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML112430571 | | number = ML112430571 | ||
| issue date = 09/01/2011 | | issue date = 09/01/2011 | ||
| title = | | title = NRC Presentation-Watts Bar Unit 2 Construction Status Public Meeting | ||
| author name = | | author name = | ||
| author affiliation = NRC/RGN-II/DCP/CPB2 | | author affiliation = NRC/RGN-II/DCP/CPB2 | ||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:WELCOME Watts Bar Unit 2 Construction Status Public | {{#Wiki_filter:WELCOME Watts Bar Unit 2 Construction Status Public Meeting August 24, 2011 Enclosure 5 | ||
18 months) | Category 1 Public Meeting | ||
THANK YOU Watts Bar Unit 2 Construction Status Public | * Please sign in | ||
* Public invited to observe/comment | |||
* NRC available after the meeting for questions/comments | |||
* Feedback forms | |||
* Agenda, slides, meeting summary, and list of attendees in Agencywide Documents Access and Management System (ADAMS) http://www.nrc.gov/reading-rm/adams.html | |||
Purpose/Topics | |||
*TVAs schedule for project completion | |||
*TVAs transitional plans : Operational areas | |||
*TVAs open items package development | |||
*TVAs quality of corrective actions for historical issues | |||
*Heineman Circuit Breaker issue | |||
*Status of Fukushima reviews | |||
*Licensing activities | |||
*Inspection activities | |||
Licensing Status | |||
* Accomplishments | |||
* FSAR Topics - 93% complete | |||
* Fire protection and Chapter 15 Dose Consequence in progress | |||
* SSERs 21, 22, and 23 published | |||
* SSER 24 draft to be completed September 2, 2011 | |||
* Publish in late September 2011 | |||
* Major areas include accidents/transient analyses (15), cyber-security (13 6) and operational releases and dose (11 and 12) | |||
(13.6), | |||
* ACRS Subcommittee scheduled on October 5, 2011 | |||
* Materials License under Part 70 issued in June | |||
* Open Issues | |||
* SSER 23 Appendix HH | |||
* Coordination with Region II for closure | |||
* Supplement to the final Environmental Statement | |||
Inspection Program Updates | |||
* Completed the Mid-cycle assessment review | |||
* Results will be issued in a September 1,2011 letter to TVA | |||
* For the 12 month assessment period identified 12 Severity Level IV violation | |||
* Expended over 17,000 inspection related hours | |||
* Increased size of Watts Bar 2 construction projects branch in Region 2; nine inspectors assigned to project | |||
* 33 different regional inspectors during the assessment period | |||
Inspection Program Elements Historical Open items Previously (VIO,NCV,IFI..) | |||
Completed Allegations inspections Inspection Generic Program Licensing Communications issues New Or CAPs/SPs re-work | |||
Status of Inspection Program | |||
* Over 500 construction inspection items in the Inspection Planning and Scheduling (IP&S) | |||
* Completed inspections for 111 IP&S items | |||
* Many y of the remaining g IP&S items have been inspected, but require additional effort to close | |||
* Completed inspections for seven (7) CAPs and SPs | |||
Status of Inspection Program Recently Completed Team Inspections: | |||
* Independent Design Verification Program | |||
* Problem Identification and Resolution | |||
* Commercial Grade Dedication Started Pre-Operational testing inspections (IMC 2513); these inspections will increase as TVA completes construction on more safety systems | |||
NRC response to Fukushima Dai-ichi accident | |||
* NRC Commission created Japan Task Force (JTF) | |||
* JTF presented its report to the Commission on July 19, 2011, proposing 12 recommendations | |||
* The Commission has asked NRC staff for a series of papers to: | |||
: 1. Outline the JTF recommendations that should be implemented immediately (Sept. 9, 2011) | |||
: 2. Prioritize JTF recommendations (Oct. 3, 2011) | |||
: 3. Consider JTF broadest recommendation to revise NRC regulatory approach (within 18 months) | |||
THANK YOU Watts Bar Unit 2 Construction Status Public Meeting August 24, 2011}} |
Latest revision as of 01:56, 6 December 2019
ML112430571 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 09/01/2011 |
From: | NRC/RGN-II/DCP/CPB2 |
To: | Tennessee Valley Authority |
References | |
Download: ML112430571 (10) | |
Text
WELCOME Watts Bar Unit 2 Construction Status Public Meeting August 24, 2011 Enclosure 5
Category 1 Public Meeting
- Please sign in
- Public invited to observe/comment
- NRC available after the meeting for questions/comments
- Feedback forms
- Agenda, slides, meeting summary, and list of attendees in Agencywide Documents Access and Management System (ADAMS) http://www.nrc.gov/reading-rm/adams.html
Purpose/Topics
- TVAs schedule for project completion
- TVAs transitional plans : Operational areas
- TVAs open items package development
- TVAs quality of corrective actions for historical issues
- Heineman Circuit Breaker issue
- Status of Fukushima reviews
- Licensing activities
- Inspection activities
Licensing Status
- Accomplishments
- FSAR Topics - 93% complete
- Fire protection and Chapter 15 Dose Consequence in progress
- SSERs 21, 22, and 23 published
- SSER 24 draft to be completed September 2, 2011
- Publish in late September 2011
- Major areas include accidents/transient analyses (15), cyber-security (13 6) and operational releases and dose (11 and 12)
(13.6),
- ACRS Subcommittee scheduled on October 5, 2011
- Materials License under Part 70 issued in June
- Open Issues
- SSER 23 Appendix HH
- Coordination with Region II for closure
- Supplement to the final Environmental Statement
Inspection Program Updates
- Completed the Mid-cycle assessment review
- Results will be issued in a September 1,2011 letter to TVA
- For the 12 month assessment period identified 12 Severity Level IV violation
- Expended over 17,000 inspection related hours
- Increased size of Watts Bar 2 construction projects branch in Region 2; nine inspectors assigned to project
- 33 different regional inspectors during the assessment period
Inspection Program Elements Historical Open items Previously (VIO,NCV,IFI..)
Completed Allegations inspections Inspection Generic Program Licensing Communications issues New Or CAPs/SPs re-work
Status of Inspection Program
- Over 500 construction inspection items in the Inspection Planning and Scheduling (IP&S)
- Completed inspections for 111 IP&S items
- Many y of the remaining g IP&S items have been inspected, but require additional effort to close
Status of Inspection Program Recently Completed Team Inspections:
- Independent Design Verification Program
- Problem Identification and Resolution
- Commercial Grade Dedication Started Pre-Operational testing inspections (IMC 2513); these inspections will increase as TVA completes construction on more safety systems
NRC response to Fukushima Dai-ichi accident
- NRC Commission created Japan Task Force (JTF)
- JTF presented its report to the Commission on July 19, 2011, proposing 12 recommendations
- The Commission has asked NRC staff for a series of papers to:
- 1. Outline the JTF recommendations that should be implemented immediately (Sept. 9, 2011)
- 2. Prioritize JTF recommendations (Oct. 3, 2011)
- 3. Consider JTF broadest recommendation to revise NRC regulatory approach (within 18 months)
THANK YOU Watts Bar Unit 2 Construction Status Public Meeting August 24, 2011