(One intermediate revision by the same user not shown) |
Line 16: |
Line 16: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:July 19, 2018 ATTN: Document Control Desk Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards U.S Nuclear Regulatory Commission Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-026, 50-301 and 72-005 License Nos. DPR-24 and DPR-27 Registration of NUHOMS-32PT Casks WNHOMS-32-046, WNHOMS-32-048, and WNHOMS-32-050 NEXT era NRC 2018-0036 10 CFR 72.212 POINT BEACH In accordance with the requirements of 10 CFR 72.212(b)(2), NextEra Energy Point Beach, LLC, is providing the enclosed information to register the use of three approved spent fuel storage casks at the Point Beach Nuclear Plant (PBNP) Independent Spent Fuel Storage Installation (ISFSI). This letter contains no new commitments and no revisions to existing commitments. | | {{#Wiki_filter:NEXTera ENERGY ~ |
| Sincerely, NextEra Energy Point Beach, LLC Eric Schultz Licensing Manager Enclosure cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW NextEra Energy Point Beach , LLC 6610 Nuclear Road, Two Rivers, WI 54241 ENCLOSURE REGISTRATION OF NUHOMS-32PT CASKS WNHOMS-32-046, WNHOMS-32-048, and WNHOMS-32-050 Licensee's Name: Licensee's Address: Reactor License Nos.: Reactor Docket Nos.: ISFSI Docket No.: Cask Certificate No.: Cask Model No.: Contact: Cask Identification Number WNHOMS-32-046 WNHOMS-32-048 WNHOMS-32-050 CASK REGISTRATION INFORMATION NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241 DPR-24 and DPR-27 50-266 and 50-301 72-005 1 004, Amendment 14 Mr. Brian Smith Project Manager 920/7 55-7344 Horizontal Dry Shielded Storage Canister Module Number Number WHSM-030 WDSC-32-029 WHSM-032 WDSC-32-030 WHSM-034 WDSC-32-031 Dry Shielded Canister Heat Load 13.98 kW 14.94 kW 15.82 kW Date Placed in Service June21,2018 June 28, 2018 July 12, 2018}} | | POINT BEACH July 19, 2018 NRC 2018-0036 10 CFR 72.212 ATTN: Document Control Desk Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards U.S Nuclear Regulatory Commission Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-026, 50-301 and 72-005 License Nos. DPR-24 and DPR-27 Registration of NUHOMS-32PT Casks WNHOMS-32-046, WNHOMS-32-048, and WNHOMS-32-050 In accordance with the requirements of 10 CFR 72 .212(b)(2), NextEra Energy Point Beach, LLC, is providing the enclosed information to register the use of three approved spent fuel storage casks at the Point Beach Nuclear Plant (PBNP) Independent Spent Fuel Storage Installation (ISFSI). |
| | This letter contains no new commitments and no revisions to existing commitments. |
| | Sincerely, NextEra Energy Point Beach, LLC Eric Schultz Licensing Manager Enclosure cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW NextEra Energy Point Beach, LLC 6610 Nuclear Road, Two Rivers, WI 54241 |
| | |
| | ENCLOSURE REGISTRATION OF NUHOMS-32PT CASKS WNHOMS-32-046, WNHOMS-32-048, and WNHOMS-32-050 CASK REGISTRATION INFORMATION Licensee's Name: NextEra Energy Point Beach, LLC Licensee's Address : 6610 Nuclear Road Two Rivers, WI 54241 Reactor License Nos.: DPR-24 and DPR-27 Reactor Docket Nos.: 50-266 and 50-301 ISFSI Docket No.: 72-005 Cask Certificate No.: 1004, Amendment 14 Cask Model No.: |
| | |
| | ==Contact:== |
| | Mr. Brian Smith Project Manager 920/7 55-7344 Cask Horizontal Dry Shielded Dry Shielded Date Identification Storage Canister Canister Heat Placed in Number Module Number Load Service Number WNHOMS-32-046 WHSM-030 WDSC-32-029 13.98 kW June21,2018 WNHOMS-32-048 WHSM-032 WDSC-32-030 14.94 kW June 28, 2018 WNHOMS-32-050 WHSM-034 WDSC-32-031 15.82 kW July 12, 2018}} |
|
---|
Category:Letter type:NRC
MONTHYEARNRC 2024-0007, Ile Post-Exam Submittal Letter2024-03-18018 March 2024 Ile Post-Exam Submittal Letter NRC-2024-0026, Ile Proposed Exam Submittal Letter2023-12-20020 December 2023 Ile Proposed Exam Submittal Letter NRC 2023-0013, Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-07-0707 July 2023 Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations NRC 2023-0006, Post-Exam Submittal Cover Letter2023-03-0101 March 2023 Post-Exam Submittal Cover Letter NRC 2023-0005, Report of Changes to Emergency Plan2023-02-21021 February 2023 Report of Changes to Emergency Plan NRC 2022-0032, Sixth 10-Year Interval Inservice Testing (1ST) Program Plan2022-09-30030 September 2022 Sixth 10-Year Interval Inservice Testing (1ST) Program Plan NRC 2022-0025, License Amendment Request 295, Beacon Power Distribution Monitoring System2022-09-26026 September 2022 License Amendment Request 295, Beacon Power Distribution Monitoring System NRC 2022-0019, Report of Changes to Emergency Plan2022-07-13013 July 2022 Report of Changes to Emergency Plan NRC 2022-0022, Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2,2022-07-11011 July 2022 Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, NRC 2022-0015, Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report2022-04-27027 April 2022 Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report NRC 2022-0014, 2021 Annual Monitoring Report2022-04-14014 April 2022 2021 Annual Monitoring Report NRC 2021-0012, Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41)2022-04-0707 April 2022 Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41) NRC 2022-0003, License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process2022-03-25025 March 2022 License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process NRC 2022-0006, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2022-02-22022 February 2022 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections NRC 2022-0004, Report of Changes to Emergency Plan2022-02-0909 February 2022 Report of Changes to Emergency Plan NRC 2022-0005, Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2022-02-0101 February 2022 Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2022-0001, Report of Changes to Emergency Plan2022-01-11011 January 2022 Report of Changes to Emergency Plan NRC 2021-0046, Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40)2021-10-28028 October 2021 Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40) NRC 2021-0031, Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-0562021-07-15015 July 2021 Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-056 NRC 2021-0027, Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-0532021-06-30030 June 2021 Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-053 NRC 2021-0028, Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism2021-06-23023 June 2021 Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism NRC 2021-0021, 2020 Annual Monitoring Report2021-04-29029 April 2021 2020 Annual Monitoring Report NRC 2021-0019, Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations NRC-2021-0010, CFR 50.59 Evaluation and Commitment Change Summary Report2021-04-0202 April 2021 CFR 50.59 Evaluation and Commitment Change Summary Report NRC-2021-0011, Technical Specification Bases and Technical Requirement Manual Change Summary2021-04-0202 April 2021 Technical Specification Bases and Technical Requirement Manual Change Summary NRC 2021-0006, Report of Changes to Emergency Plan2021-03-18018 March 2021 Report of Changes to Emergency Plan NRC 2021-0005, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-022021-02-11011 February 2021 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-02 NRC 2021-0002, Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2021-01-21021 January 2021 Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2021-0003, Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report2021-01-21021 January 2021 Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report NRC 2021-0001, Report of Changes to Emergency Plan2021-01-13013 January 2021 Report of Changes to Emergency Plan NRC 2020-0044, Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise2020-12-0808 December 2020 Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise NRC 2020-0032, Application for Subsequent Renewed Facility Operating Licenses2020-11-16016 November 2020 Application for Subsequent Renewed Facility Operating Licenses NRC 2020-0039, Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40)2020-11-0202 November 2020 Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40) NRC 2020-0031, NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-0812020-10-0505 October 2020 NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-081 NRC 2020-0029, Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-09-15015 September 2020 Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0024, Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements2020-08-17017 August 2020 Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements NRC 2020-0020, License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-08-13013 August 2020 License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0023, NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations2020-08-12012 August 2020 NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations NRC 2020-0021, Response to NRC Inspection Report and Preliminary White Finding2020-08-12012 August 2020 Response to NRC Inspection Report and Preliminary White Finding NRC 2020-0018, Report of Changes to Emergency Plan2020-07-15015 July 2020 Report of Changes to Emergency Plan NRC-2020-0016, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-12012 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic NRC 2020-0012, Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2020-05-20020 May 2020 Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2020-0008, Report of Changes to Emergency Plan2020-04-0606 April 2020 Report of Changes to Emergency Plan NRC 2020-0007, Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38)2020-03-27027 March 2020 Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38) NRC 2020-0003, License Amendment Request 289: Tornado Missile Protection Licensing Basis2020-02-0606 February 2020 License Amendment Request 289: Tornado Missile Protection Licensing Basis NRC 2020-0001, Pressure Temperature Limits Report (PTLR)2020-01-0909 January 2020 Pressure Temperature Limits Report (PTLR) NRC 2019-0044, Report of Changes to Emergency Plan2019-11-0101 November 2019 Report of Changes to Emergency Plan NRC 2019-0036, Submittal of 2018 Update to Final Safety Analysis Report2019-10-18018 October 2019 Submittal of 2018 Update to Final Safety Analysis Report NRC 2019-0037, Technical Specification Bases Change Summary2019-10-18018 October 2019 Technical Specification Bases Change Summary NRC 2019-0034, Technical Requirements Manual Change Summary2019-10-18018 October 2019 Technical Requirements Manual Change Summary 2024-03-18
[Table view] |
Text
NEXTera ENERGY ~
POINT BEACH July 19, 2018 NRC 2018-0036 10 CFR 72.212 ATTN: Document Control Desk Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards U.S Nuclear Regulatory Commission Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets50-026, 50-301 and 72-005 License Nos. DPR-24 and DPR-27 Registration of NUHOMS-32PT Casks WNHOMS-32-046, WNHOMS-32-048, and WNHOMS-32-050 In accordance with the requirements of 10 CFR 72 .212(b)(2), NextEra Energy Point Beach, LLC, is providing the enclosed information to register the use of three approved spent fuel storage casks at the Point Beach Nuclear Plant (PBNP) Independent Spent Fuel Storage Installation (ISFSI).
This letter contains no new commitments and no revisions to existing commitments.
Sincerely, NextEra Energy Point Beach, LLC Eric Schultz Licensing Manager Enclosure cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW NextEra Energy Point Beach, LLC 6610 Nuclear Road, Two Rivers, WI 54241
ENCLOSURE REGISTRATION OF NUHOMS-32PT CASKS WNHOMS-32-046, WNHOMS-32-048, and WNHOMS-32-050 CASK REGISTRATION INFORMATION Licensee's Name: NextEra Energy Point Beach, LLC Licensee's Address : 6610 Nuclear Road Two Rivers, WI 54241 Reactor License Nos.: DPR-24 and DPR-27 Reactor Docket Nos.: 50-266 and 50-301 ISFSI Docket No.: 72-005 Cask Certificate No.: 1004, Amendment 14 Cask Model No.:
Contact:
Mr. Brian Smith Project Manager 920/7 55-7344 Cask Horizontal Dry Shielded Dry Shielded Date Identification Storage Canister Canister Heat Placed in Number Module Number Load Service Number WNHOMS-32-046 WHSM-030 WDSC-32-029 13.98 kW June21,2018 WNHOMS-32-048 WHSM-032 WDSC-32-030 14.94 kW June 28, 2018 WNHOMS-32-050 WHSM-034 WDSC-32-031 15.82 kW July 12, 2018