| title = IR 05000454-07-405 (Drs); 05000455-07-405 (Drs); on 10/29/2007 - 11/02/2007; Byron Station; Routine Security Baseline Inspection - Cover Letter
| title = IR 05000454-07-405 (Drs); 05000455-07-405 (Drs); on 10/29/2007 - 11/02/2007; Byron Station; Routine Security Baseline Inspection - Cover Letter
| author name = Duncan E R
| author name = Duncan E
| author affiliation = NRC/RGN-III/DRS/PSB
| author affiliation = NRC/RGN-III/DRS/PSB
| addressee name = Pardee C G
| addressee name = Pardee C
| addressee affiliation = Exelon Generation Co, LLC
| addressee affiliation = Exelon Generation Co, LLC
| docket = 05000454, 05000455
| docket = 05000454, 05000455
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:ber 14, 2007
[[Issue date::December 14, 2007]]


Mr. Charles Chief Nuclear Officer (CNO) and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville IL 60555
==SUBJECT:==
 
BYRON STATION, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000454/2007405; 05000455/2007405
SUBJECT: BYRON STATION, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000454/2007405; 05000455/2007405


==Dear Mr. Pardee:==
==Dear Mr. Pardee:==
On November 2, 2007, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Byron Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on November 2, 2007, with Mr. D. Hoots and other members of your staff.
On November 2, 2007, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Byron Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on November 2, 2007, with Mr. D. Hoots and other members of your staff.


The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.


The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
Line 34: Line 32:
No findings of significance were identified.
No findings of significance were identified.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the  
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the EXEMPT FROM PUBLIC DISCLOSURE May be exempt from public release under the Freedom of Information Act (5 U.S.C. 552)
Exemption number: 5  Enclosure Contains Sensitive Unclassified Nuclear Regulatory Commission review required before public Non-Safeguards Information. Upon release. separation, this page is decontrolled.


EXEMPT FROM PUBLIC DISCLOSURE May be exempt from public release under the Freedom of Information Act (5 U.S.C. 552)
Gregory Hansen, RIII/DRS/PSB Name and organization of person making determination.


Exemption number: 5 Nuclear Regulatory Commission review required before public release. Gregory Hansen, RIII/DRS/PSB  Name and organization of person making determination.
Date of determination: 11/26/2007 Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Date of determination: 11/26/2007 Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.


Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.


Sincerely,/RA/ Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66  
Sincerely,
 
/RA/
===Enclosure:===
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66 Enclosure: Inspection Report 05000454/2007405(DRS);
Inspection Report 05000454/2007405(DRS); 05000455/2007405(DRS)  
05000455/2007405(DRS)
 
w/Attachment: Supplemental Information cc w/encl: D. Riffle (NSIR/DSO/DDSO)
===w/Attachment:===
State Liaison Officer, State of Illinois L. Asken, Byron Site Security Manager Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled.
Supplemental Information  
 
cc w/encl: D. Riffle (NSIR/DSO/DDSO) State Liaison Officer, State of Illinois L. Asken, Byron Site Security Manager  
 
Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled.
}}
}}

Latest revision as of 20:46, 14 November 2019

IR 05000454-07-405 (Drs); 05000455-07-405 (Drs); on 10/29/2007 - 11/02/2007; Byron Station; Routine Security Baseline Inspection - Cover Letter
ML073540538
Person / Time
Site: Byron  Constellation icon.png
Issue date: 12/14/2007
From: Eric Duncan
Plant Support Branch II
To: Pardee C
Exelon Generation Co
References
IR-07-405
Download: ML073540538 (5)


Text

ber 14, 2007

SUBJECT:

BYRON STATION, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000454/2007405; 05000455/2007405

Dear Mr. Pardee:

On November 2, 2007, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Byron Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on November 2, 2007, with Mr. D. Hoots and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the EXEMPT FROM PUBLIC DISCLOSURE May be exempt from public release under the Freedom of Information Act (5 U.S.C. 552)

Exemption number: 5 Enclosure Contains Sensitive Unclassified Nuclear Regulatory Commission review required before public Non-Safeguards Information. Upon release. separation, this page is decontrolled.

Gregory Hansen, RIII/DRS/PSB Name and organization of person making determination.

Date of determination: 11/26/2007 Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66 Enclosure: Inspection Report 05000454/2007405(DRS);

05000455/2007405(DRS)