| number = ML15316A563
| number = ML15316A563
| issue date = 11/13/2015
| issue date = 11/13/2015
| title = Susquehanna Steam Electric Station, Units 1 and 2 - Request for Additional Information Regarding Proposed Relief Requests for the Third 10-Year Inservice Inspection Interval(Cac Nos. MF6302 Through MF6307)
| title = Request for Additional Information Regarding Proposed Relief Requests for the Third 10-Year Inservice Inspection Interval(Cac Nos. MF6302 Through MF6307)
| author name = Whited J A
| author name = Whited J
| author affiliation = NRC/NRR/DORL/LPLI-2
| author affiliation = NRC/NRR/DORL/LPLI-2
| addressee name = Franke J A
| addressee name = Franke J
| addressee affiliation = Susquehanna Nuclear, LLC
| addressee affiliation = Susquehanna Nuclear, LLC
| docket = 05000387, 05000388
| docket = 05000387, 05000388
| license number = NPF-014, NPF-022
| license number = NPF-014, NPF-022
| contact person = Whited J A, NRR/DORL/LPLI-2
| contact person = Whited J, NRR/DORL/LPLI-2
| case reference number = CAC MF6302, CAC MF6303, CAC MF6304, CAC MF6305, CAC MF6306, CAC MF6307
| case reference number = CAC MF6302, CAC MF6303, CAC MF6304, CAC MF6305, CAC MF6306, CAC MF6307
| document type = Letter, Request for Additional Information (RAI)
| document type = Letter, Request for Additional Information (RAI)
| page count = 4
| page count = 4
| project = CAC:MF6302, CAC:MF6303, CAC:MF6304, CAC:MF6305, CAC:MF6306, CAC:MF6307
| project = CAC:MF6302, CAC:MF6303, CAC:MF6304, CAC:MF6305, CAC:MF6306, CAC:MF6307
| stage = RAI
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Jon A. Franke Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467 November 13, 2015 SUBJECT: SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED RELIEF REQUESTS FOR THE THIRD 10-YEAR INSERVICE INSPECTION INTERVAL (CAC NOS. MF6302 THROUGH MF6307) Dear Mr. Franke: By letter dated May 28, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 15148A774), Susquehanna Nuclear, LLC (the licensee) requested the U.S. Nuclear Regulatory Commission (NRC) to authorize relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code. The proposed relief requests are associated with the third 10-year inservice inspection interval. The relief requests pertain to the examination coverage of the welds at the Susquehanna Steam Electric Station, Units 1 and 2. The NRC staff determined that the licensee's relief requests (Nos. 3RR-19, 3RR-20, and 3RR-21 ), and basis for relief that supports the change requested did not include sufficient detail to enable the NRC staff to make an independent assessment regarding the acceptability of the proposal in terms of regulatory requirements and the protection of public health and safety. The NRC staff requested supplemental information, dated July 10, 2015 (ADAMS Accession No. ML 15183A396), to complete its review. In response to the NRC staff's request, the licensee replaced its May 28, 2015, submittal in its entirety with letter submittal dated August 6, 2015 (ADAMS Accession No. ML 15233A089). The NRC staff has reviewed the information submitted by the licensee, and based on this review, determined additional information is required to complete the assessment of the relief requests. Enclosed is copy of the NRC staff's request for additional information. The draft questions were sent to Mr. Richard Mcintosh to ensure that they were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. Please respond to the enclosure within 30 days of the date of this letter.
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 13, 2015 Mr. Jon A. Franke Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467
J. Franke -2 -If you have any questions, please contact me at (301) 415-4090 or Jeffrey.Whited@nrc.gov. Docket Nos. 50-387 and 50-388 Enclosure: Request for Additional Information cc w/enclosure: Distribution via Listserv Sincerely, Jeffrey A. Whited, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR REACTOR REGULATION RELIEF REQUESTS NUMBERS 3RR-19, 3RR-20, AND 3RR-21 SUSQUEHANNA NUCLEAR, LLC ALLEGHENY ELECTRIC COOPERATIVE, INC. SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 DOCKET NOS. 50-387 AND 50-388 By letter dated May 28, 2015, 1 Susquehanna Nuclear, LLC (the licensee)2 requested the U.S. Nuclear Regulatory Commission (NRC) to authorize relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code. The proposed relief requests are associated with the third 10-year inservice inspection (ISi) interval. The relief requests pertain to the examination coverage of the welds at the Susquehanna Steam Electric Station (SSES), Units 1 and 2. The NRC staff determined that the licensee's relief requests (Nos. 3RR-19, 3RR-20, and 3RR-21 ), and basis for relief that supports the change requested, did not include sufficient detail to enable the NRC staff to make an independent assessment regarding the acceptability of the proposal in terms of regulatory requirements and the protection of public health and safety. The NRC staff requested supplemental information, dated July 10, 2015,3 to complete its review. In response to the NRC request, the licensee replaced the May 28, 2015, submittal in its entirety with letter submittal dated August 6, 20154. The NRC staff determined that the following additional information is required to complete its review of the relief requests. In Relief Request No. 3RR-20, the achieved examination coverage for weld DG-DH is 7.7 percent for SSES, Unit 1, during the third 10-year ISi interval. The NRC staff notes that the DG-DH achieved examination coverage is 23.7 percent for both SSES units for all previous 10-Year ISi Intervals for this weld. Please explain why the achieved examination coverage decreased from 23.7 percent to 7.7 percent for weld DG-DH for SSES, Unit 1, during the third 10-year ISi interval. 1 Agencywide Documents Access and Management System (ADAMS) Accession No. ML 15148A774. 2 PPL Susquehanna, LLC submitted this relief request. However, on June 1, 2014, the NRC staff issued an amendment changing the name of the licensee for the Susquehanna Steam Electric Station, Units 1 and 2, from PPL Susquehanna, LLC to Susquehanna Nuclear, LLC. 3 ADAMS Accession No. ML 15183A396. 4 ADAMS Accession No. ML 15233A089. Enclosure J. Franke -2 -If you have any questions, please contact me at (301) 415-4090 or Jeffrey.Whited@nrc.gov. Docket Nos. 50-387 and 50-388 Enclosure: Request for Additional Information Sincerely, IRA/ Jeffrey A. Whited, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation cc w/enclosure: Distribution via Listserv DISTRIBUTION: PUBLIC LPLl-2 R/F RidsACRS_MailCTR Resource RidsNrrDeEpnb Resource RidsNrrDeEvib Resource RidsNrrDorl Resource RidsNrrDorlDpr Resource RidsNrrDorllpll-2 Resource RidsNrrLALRonewicz Resource RidsNrrPMSusquehanna Resource RidsRgn1 MailCenter Resource ARezai, NRR DDijamco, NRR ADAMS Accession No.: ML15316A563 OFFICE DORL/LPLl-2/PM DORL/LPLl-2/LA DE/EPNB/BC DE/EVIB/BC NAME THood LRonewicz DAiiey JMcHale KHoffman for GCheruvenki for DATE 11/12/15 11/13/15 11/13115 11/13/15 OFFICIAL RECORD COPY DORL/LPLl-2/BC DBroaddus TWengert for 11/13/15 DORL/LPLl-2/PM JWhited 11/13/15
 
}}
==SUBJECT:==
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED RELIEF REQUESTS FOR THE THIRD 10-YEAR INSERVICE INSPECTION INTERVAL (CAC NOS. MF6302 THROUGH MF6307)
 
==Dear Mr. Franke:==
 
By letter dated May 28, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15148A774), Susquehanna Nuclear, LLC (the licensee) requested the U.S. Nuclear Regulatory Commission (NRC) to authorize relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code. The proposed relief requests are associated with the third 10-year inservice inspection interval. The relief requests pertain to the examination coverage of the welds at the Susquehanna Steam Electric Station, Units 1 and 2.
The NRC staff determined that the licensee's relief requests (Nos. 3RR-19, 3RR-20, and 3RR-21 ), and basis for relief that supports the change requested did not include sufficient detail to enable the NRC staff to make an independent assessment regarding the acceptability of the proposal in terms of regulatory requirements and the protection of public health and safety. The NRC staff requested supplemental information, dated July 10, 2015 (ADAMS Accession No. ML15183A396), to complete its review. In response to the NRC staff's request, the licensee replaced its May 28, 2015, submittal in its entirety with letter submittal dated August 6, 2015 (ADAMS Accession No. ML15233A089).
The NRC staff has reviewed the information submitted by the licensee, and based on this review, determined additional information is required to complete the assessment of the relief requests. Enclosed is copy of the NRC staff's request for additional information. The draft questions were sent to Mr. Richard Mcintosh to ensure that they were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. Please respond to the enclosure within 30 days of the date of this letter.
 
J. Franke                                 If you have any questions, please contact me at (301) 415-4090 or Jeffrey.Whited@nrc.gov.
Sincerely,
                                            ~//Ud Jeffrey A. Whited, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388
 
==Enclosure:==
 
Request for Additional Information cc w/enclosure: Distribution via Listserv
 
REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR REACTOR REGULATION RELIEF REQUESTS NUMBERS 3RR-19, 3RR-20, AND 3RR-21 SUSQUEHANNA NUCLEAR, LLC ALLEGHENY ELECTRIC COOPERATIVE, INC.
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 DOCKET NOS. 50-387 AND 50-388 By letter dated May 28, 2015, 1 Susquehanna Nuclear, LLC (the licensee)2 requested the U.S. Nuclear Regulatory Commission (NRC) to authorize relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code. The proposed relief requests are associated with the third 10-year inservice inspection (ISi) interval. The relief requests pertain to the examination coverage of the welds at the Susquehanna Steam Electric Station (SSES), Units 1 and 2.
The NRC staff determined that the licensee's relief requests (Nos. 3RR-19, 3RR-20, and 3RR-21 ), and basis for relief that supports the change requested, did not include sufficient detail to enable the NRC staff to make an independent assessment regarding the acceptability of the proposal in terms of regulatory requirements and the protection of public health and safety. The NRC staff requested supplemental information, dated July 10, 2015, 3 to complete its review. In response to the NRC request, the licensee replaced the May 28, 2015, submittal in its entirety with letter submittal dated August 6, 20154 .
The NRC staff determined that the following additional information is required to complete its review of the relief requests.
In Relief Request No. 3RR-20, the achieved examination coverage for weld DG-DH is 7.7 percent for SSES, Unit 1, during the third 10-year ISi interval. The NRC staff notes that the DG-DH achieved examination coverage is 23.7 percent for both SSES units for all previous 10-Year ISi Intervals for this weld. Please explain why the achieved examination coverage decreased from 23.7 percent to 7.7 percent for weld DG-DH for SSES, Unit 1, during the third 10-year ISi interval.
1 Agencywide Documents Access and Management System (ADAMS) Accession No. ML15148A774.
2 PPL Susquehanna, LLC submitted this relief request. However, on June 1, 2014, the NRC staff issued an amendment changing the name of the licensee for the Susquehanna Steam Electric Station, Units 1 and 2, from PPL Susquehanna, LLC to Susquehanna Nuclear, LLC.
3 ADAMS Accession No. ML15183A396.
4 ADAMS Accession No. ML15233A089.
Enclosure
 
ML15316A563 OFFICE     DORL/LPLl-2/PM     DORL/LPLl-2/LA DE/EPNB/BC     DE/EVIB/BC     DORL/LPLl-2/BC DORL/LPLl-2/PM NAME       THood             LRonewicz       DAiiey         JMcHale         DBroaddus      JWhited KHoffman for   GCheruvenki for TWengert for DATE       11/12/15           11/13/15       11/13115       11/13/15       11/13/15       11/13/15}}

Latest revision as of 04:30, 31 October 2019

Request for Additional Information Regarding Proposed Relief Requests for the Third 10-Year Inservice Inspection Interval(Cac Nos. MF6302 Through MF6307)
ML15316A563
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 11/13/2015
From: Jeffrey Whited
Plant Licensing Branch 1
To: Franke J
Susquehanna
Whited J, NRR/DORL/LPLI-2
References
CAC MF6302, CAC MF6303, CAC MF6304, CAC MF6305, CAC MF6306, CAC MF6307
Download: ML15316A563 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 13, 2015 Mr. Jon A. Franke Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED RELIEF REQUESTS FOR THE THIRD 10-YEAR INSERVICE INSPECTION INTERVAL (CAC NOS. MF6302 THROUGH MF6307)

Dear Mr. Franke:

By letter dated May 28, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15148A774), Susquehanna Nuclear, LLC (the licensee) requested the U.S. Nuclear Regulatory Commission (NRC) to authorize relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code. The proposed relief requests are associated with the third 10-year inservice inspection interval. The relief requests pertain to the examination coverage of the welds at the Susquehanna Steam Electric Station, Units 1 and 2.

The NRC staff determined that the licensee's relief requests (Nos. 3RR-19, 3RR-20, and 3RR-21 ), and basis for relief that supports the change requested did not include sufficient detail to enable the NRC staff to make an independent assessment regarding the acceptability of the proposal in terms of regulatory requirements and the protection of public health and safety. The NRC staff requested supplemental information, dated July 10, 2015 (ADAMS Accession No. ML15183A396), to complete its review. In response to the NRC staff's request, the licensee replaced its May 28, 2015, submittal in its entirety with letter submittal dated August 6, 2015 (ADAMS Accession No. ML15233A089).

The NRC staff has reviewed the information submitted by the licensee, and based on this review, determined additional information is required to complete the assessment of the relief requests. Enclosed is copy of the NRC staff's request for additional information. The draft questions were sent to Mr. Richard Mcintosh to ensure that they were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. Please respond to the enclosure within 30 days of the date of this letter.

J. Franke If you have any questions, please contact me at (301) 415-4090 or Jeffrey.Whited@nrc.gov.

Sincerely,

~//Ud Jeffrey A. Whited, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

Request for Additional Information cc w/enclosure: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR REACTOR REGULATION RELIEF REQUESTS NUMBERS 3RR-19, 3RR-20, AND 3RR-21 SUSQUEHANNA NUCLEAR, LLC ALLEGHENY ELECTRIC COOPERATIVE, INC.

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 DOCKET NOS. 50-387 AND 50-388 By letter dated May 28, 2015, 1 Susquehanna Nuclear, LLC (the licensee)2 requested the U.S. Nuclear Regulatory Commission (NRC) to authorize relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code. The proposed relief requests are associated with the third 10-year inservice inspection (ISi) interval. The relief requests pertain to the examination coverage of the welds at the Susquehanna Steam Electric Station (SSES), Units 1 and 2.

The NRC staff determined that the licensee's relief requests (Nos. 3RR-19, 3RR-20, and 3RR-21 ), and basis for relief that supports the change requested, did not include sufficient detail to enable the NRC staff to make an independent assessment regarding the acceptability of the proposal in terms of regulatory requirements and the protection of public health and safety. The NRC staff requested supplemental information, dated July 10, 2015, 3 to complete its review. In response to the NRC request, the licensee replaced the May 28, 2015, submittal in its entirety with letter submittal dated August 6, 20154 .

The NRC staff determined that the following additional information is required to complete its review of the relief requests.

In Relief Request No. 3RR-20, the achieved examination coverage for weld DG-DH is 7.7 percent for SSES, Unit 1, during the third 10-year ISi interval. The NRC staff notes that the DG-DH achieved examination coverage is 23.7 percent for both SSES units for all previous 10-Year ISi Intervals for this weld. Please explain why the achieved examination coverage decreased from 23.7 percent to 7.7 percent for weld DG-DH for SSES, Unit 1, during the third 10-year ISi interval.

1 Agencywide Documents Access and Management System (ADAMS) Accession No. ML15148A774.

2 PPL Susquehanna, LLC submitted this relief request. However, on June 1, 2014, the NRC staff issued an amendment changing the name of the licensee for the Susquehanna Steam Electric Station, Units 1 and 2, from PPL Susquehanna, LLC to Susquehanna Nuclear, LLC.

3 ADAMS Accession No. ML15183A396.

4 ADAMS Accession No. ML15233A089.

Enclosure

ML15316A563 OFFICE DORL/LPLl-2/PM DORL/LPLl-2/LA DE/EPNB/BC DE/EVIB/BC DORL/LPLl-2/BC DORL/LPLl-2/PM NAME THood LRonewicz DAiiey JMcHale DBroaddus JWhited KHoffman for GCheruvenki for TWengert for DATE 11/12/15 11/13/15 11/13115 11/13/15 11/13/15 11/13/15