ML17325B587: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:CATZaoaz 1
't                                          1I REGULATE'MFOftMLTIOMDISTRIBUTIOIIYSTEM (RIDS)
ACCESSION NBR:9905170134              DOC.DATE: 99/05/07        NOTARIZED: NO                  DOCKET  ¹ FACIL:50-315,Donald C. Cook Nuclear Power Plant,,Unit 1, Indiana                        M  05000315 50-316 Donald C. Cook'Nuclear Power Plant, Unit 2, Indiana                      M  05000316 AUTH. NAME            AUTHOR  AFFILIATION RENCHECK,M.W.        Indiana Michigan Power Co.
RECIP.NAME            RECIPIENT AFFILIATION
                            'Records Management Branch (Document            Control Desk)
 
==SUBJECT:==
Forwards current revs of expanded sys readiness review (ESSR) implementing procedures, for info purposes to support current NRC insps.Current ESRR schedule provided for info purposes, reflecting revised target dates.
DISTRIBUTION CODE: A001D        COPIES RECEIVED:LTR          ENCL          SIZE:
TITLE:  OR  Submittal: General Distribution                                                            E NOTES:
RECIPIENT            COPIES              RECIPIENT                COP1ES ID CODE/NAME          LTTR ENCL        ID  CODE/NAME            LTTR ENCL LPD3-1 LA                1      1    LPD3-1    PD                  1    1 STANG, J                  1    .1 INTERNAL: F LE CENTER          01      1      1    NRR/DE/EMCB                  1    1 R DE EMEB              1      1    NRR/DSSA/SPLB                1    '1 NRR/DSSA/SRXB            1      1    NRR/SPSB JUNG,I              1    1 NUDOCS-ABSTRACT          1      1    OGC/HDS3                      1    0 EXTERNAL: NOAC                          1      1    NRC PDR D
                                                                                                          'E Vwtr q Pgfr-ig(
1 NOTE TO ALL "RIDSM RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE LISTS DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR              13  ENCL'2
 
indiana Niichlgan "
Power Company 500 Circle Drive Buchanan, Ml 491071373 PNQM&fA MCIM6'NM PQWJFR May,'7, 1999                                                        ABP:NRC: 1328 Docket Nos: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN:                Document Control Desk Mail Stop 0-P1-17 Washington,          DC  20555-0001 Gentlemen:
 
==Subject:==
Request for Information        re: Expanded System Readiness Review (BSRR)
 
==Reference:==
: 1. Bxpanded System Readiness        Review (ESSR) Program, PMP  7200.RST.004, Revision 5 (Attachment 1)
: 2. ESRR Program for Level 2 Systems, PMP 7200'.RST.006,    Revision 1 (Attachment 2)
: 3. ESRR Schedule (Attachment 3)
The purpose          of this letter is to provide the NRC staff with a copy    of the current revisions of the BSRR implementing procedures entitled,            Bxpanded        System      Readiness    Review    Program, PMP 7200.RST.004,            Revision 5 and Expanded System Readiness Review Program for Level 2 Systems,                      PMP 7200.RST.006,    Revision 1.
Indiana Michigan Power Company (I&M) is providing these procedures          for information        purposes to support the current NRC inspections.              I&M    may    revise    these procedures    as process enhancements          or changes      are deemed necessary.      A revision to the level 2 procedure is currently in process. I&M will maintain the current procedures onsite and make these procedures available to the NRC inspectors.
Additionally,            the current BSRR schedule              is provided for informational purposes.                  The schedule depicts revised target dates since the 0350 meeting of April 15, 1999.                        The schedule provides key milestones, such as target dates for completion of systems,        ESRR    reports,      System    Readiness  Review  Board  (SRRB) review        of the        system    reports and Plant Operations          Review Committee        (PORC)    review of the system reports.
The ESRR process            and schedule    has been discussed in the February 11,    1999,      NRC    0350    Meeting and initial results have been subsequently discussed in the March 24, and April 15, 1999 NRC 0350 meetings.            As discussed in these meetings, I&M is committed to performing these reviews in a rigorous and quality manner. As
                                  -"" 032 9905i70134 990507 PDR  ADQCK 050003i5 P                    PDR
 
f ~
("t, e',
h sC
'll ~
 
U. S. Nuclea    egulatory Commission Page 2 such,  the actual completion dates may change relative to the target completion dates for the individual system. I&M does not intend to docket subsequent revisions of these documents.
However, IN will continue to provide updates of the ESRR progress and schedule to the NRC inspectors.
If you have any further questions,        please contact David F.
Kunsemiller at (616) 466-2405.
Sincerely, M. W. Rencheck Vice President,  Nuclear Engineering
~kas Attachment c:    J. E. Dyer, w/attachments MDEQ - DW 6 RPD, w/attachments NRC Resident Inspector, w/attachments R. Whale
 
Attachment  1 Expanded System Readiness  Review Procedure PMP  7200.RST.004,  Rev. 5}}

Latest revision as of 05:36, 29 October 2019

Forwards Current Revs of Expanded Sys Readiness Review (Essr) Implementing Procedures,For Info Purposes to Support Current NRC Insps.Current Esrr Schedule Provided for Info Purposes,Reflecting Revised Target Dates
ML17325B587
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 05/07/1999
From: Rencheck M
INDIANA MICHIGAN POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML17325B588 List:
References
AEP:NRC:-1328, NUDOCS 9905170134
Download: ML17325B587 (5)


Text

CATZaoaz 1

't 1I REGULATE'MFOftMLTIOMDISTRIBUTIOIIYSTEM (RIDS)

ACCESSION NBR:9905170134 DOC.DATE: 99/05/07 NOTARIZED: NO DOCKET ¹ FACIL:50-315,Donald C. Cook Nuclear Power Plant,,Unit 1, Indiana M 05000315 50-316 Donald C. Cook'Nuclear Power Plant, Unit 2, Indiana M 05000316 AUTH. NAME AUTHOR AFFILIATION RENCHECK,M.W. Indiana Michigan Power Co.

RECIP.NAME RECIPIENT AFFILIATION

'Records Management Branch (Document Control Desk)

SUBJECT:

Forwards current revs of expanded sys readiness review (ESSR) implementing procedures, for info purposes to support current NRC insps.Current ESRR schedule provided for info purposes, reflecting revised target dates.

DISTRIBUTION CODE: A001D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: OR Submittal: General Distribution E NOTES:

RECIPIENT COPIES RECIPIENT COP1ES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL LPD3-1 LA 1 1 LPD3-1 PD 1 1 STANG, J 1 .1 INTERNAL: F LE CENTER 01 1 1 NRR/DE/EMCB 1 1 R DE EMEB 1 1 NRR/DSSA/SPLB 1 '1 NRR/DSSA/SRXB 1 1 NRR/SPSB JUNG,I 1 1 NUDOCS-ABSTRACT 1 1 OGC/HDS3 1 0 EXTERNAL: NOAC 1 1 NRC PDR D

'E Vwtr q Pgfr-ig(

1 NOTE TO ALL "RIDSM RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE LISTS DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 13 ENCL'2

indiana Niichlgan "

Power Company 500 Circle Drive Buchanan, Ml 491071373 PNQM&fA MCIM6'NM PQWJFR May,'7, 1999 ABP:NRC: 1328 Docket Nos: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop 0-P1-17 Washington, DC 20555-0001 Gentlemen:

Subject:

Request for Information re: Expanded System Readiness Review (BSRR)

Reference:

1. Bxpanded System Readiness Review (ESSR) Program, PMP 7200.RST.004, Revision 5 (Attachment 1)
2. ESRR Program for Level 2 Systems, PMP 7200'.RST.006, Revision 1 (Attachment 2)
3. ESRR Schedule (Attachment 3)

The purpose of this letter is to provide the NRC staff with a copy of the current revisions of the BSRR implementing procedures entitled, Bxpanded System Readiness Review Program, PMP 7200.RST.004, Revision 5 and Expanded System Readiness Review Program for Level 2 Systems, PMP 7200.RST.006, Revision 1.

Indiana Michigan Power Company (I&M) is providing these procedures for information purposes to support the current NRC inspections. I&M may revise these procedures as process enhancements or changes are deemed necessary. A revision to the level 2 procedure is currently in process. I&M will maintain the current procedures onsite and make these procedures available to the NRC inspectors.

Additionally, the current BSRR schedule is provided for informational purposes. The schedule depicts revised target dates since the 0350 meeting of April 15, 1999. The schedule provides key milestones, such as target dates for completion of systems, ESRR reports, System Readiness Review Board (SRRB) review of the system reports and Plant Operations Review Committee (PORC) review of the system reports.

The ESRR process and schedule has been discussed in the February 11, 1999, NRC 0350 Meeting and initial results have been subsequently discussed in the March 24, and April 15, 1999 NRC 0350 meetings. As discussed in these meetings, I&M is committed to performing these reviews in a rigorous and quality manner. As

-"" 032 9905i70134 990507 PDR ADQCK 050003i5 P PDR

f ~

("t, e',

h sC

'll ~

U. S. Nuclea egulatory Commission Page 2 such, the actual completion dates may change relative to the target completion dates for the individual system. I&M does not intend to docket subsequent revisions of these documents.

However, IN will continue to provide updates of the ESRR progress and schedule to the NRC inspectors.

If you have any further questions, please contact David F.

Kunsemiller at (616) 466-2405.

Sincerely, M. W. Rencheck Vice President, Nuclear Engineering

~kas Attachment c: J. E. Dyer, w/attachments MDEQ - DW 6 RPD, w/attachments NRC Resident Inspector, w/attachments R. Whale

Attachment 1 Expanded System Readiness Review Procedure PMP 7200.RST.004, Rev. 5