| document type = Meeting Briefing Package/Handouts
| document type = Meeting Briefing Package/Handouts
| page count = 7
| page count = 7
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:Westinghouse Non
{{#Wiki_filter:Westinghouse Non-Proprietary Class 3           © 2018 Westinghouse Electric Company LLC. All Rights Reserved.
-Proprietary Class 3
Farley 1 and 2 MUR Power Uprate Jim Smith November 13, 2018 1
© 2018 Westinghouse Electric Company LLC. All Rights Reserved.
1 Jim Smith November 13, 2018 Farley 1 and 2 MUR Power Uprate


2 Westinghouse Non
Westinghouse Non-Proprietary Class 3   © 2018 Westinghouse Electric Company LLC. All Rights Reserved.
-Proprietary Class 3
Agenda
© 2018 Westinghouse Electric Company LLC. All Rights Reserved.
* Purpose
Agenda Purpose Scope Special Considerations Schedule Questions 3 Westinghouse Non
* Scope
-Proprietary Class 3
* Special Considerations
© 2018 Westinghouse Electric Company LLC. All Rights Reserved.
* Schedule
Purpose Inform NRC of plans to submit a power uprate
* Questions 2
- Measurement Uncertainty Recovery  Discuss Special Consideration and obtain NRC feedback Provide the important milestones for success 4 Westinghouse Non
-Proprietary Class 3
© 2018 Westinghouse Electric Company LLC. All Rights Reserved.
Project Scope
- NSSS Design Input Core/NSSS power increasing from current 2775/2785 MWt by ~1.6-1.7%. Depends on calculated power uncertainty by Cameron with LEFM NSSS analyses will be performed at 2% increase (2831 core/2841 NSSS)
Bounds possible actual power levels Consistent with previous MUR programs Assessment of NSSS components, systems, and accident analyses will require a combination of evaluations and more detailed analyses depending on whether a 2% power uncertainty was part of the current analysis basis BOP assessments will consist mostly of evaluations


5 Westinghouse Non
Westinghouse Non-Proprietary Class 3   © 2018 Westinghouse Electric Company LLC. All Rights Reserved.
-Proprietary Class 3
Purpose Inform NRC of plans to submit a power uprate -
© 2018 Westinghouse Electric Company LLC. All Rights Reserved.
Measurement Uncertainty Recovery Discuss Special Consideration and obtain NRC feedback Provide the important milestones for success 3
Special Considerations PAD5 will be included in effort Fuel rod temperatures/pressures generated with PAD5 Incorporated into affected "Not
-LOCA" analysis areas (Chapter 15 transients, containment, fuel rod design criteria, fuel nuclear design and thermal/hydraulic design)
Spent Fuel Pool Criticality As discussed, the SFP criticality analysis is to be updated The impact on the spent fuel for the MUR uprate will also be reflected in the analysis As this SFP criticality analysis LAR review will be performed in parallel with the MUR LAR review, SNC is requesting feedback regarding this logistic


6 Westinghouse Non
Westinghouse Non-Proprietary Class 3                     © 2018 Westinghouse Electric Company LLC. All Rights Reserved.
-Proprietary Class 3
Project Scope - NSSS Design Input
© 2018 Westinghouse Electric Company LLC. All Rights Reserved.
* Core/NSSS power increasing from current 2775/2785 MWt by ~1.6-1.7%.
Schedule MUR LAR  Pre-submittal meeting is planned for August 2019 LAR is targeted for submittal in October 2019 NRC approval is requested by July 2020 to support a Fall 2020 Unit 2 implementation
Depends on calculated power uncertainty by Cameron with LEFM
* NSSS analyses will be performed at 2% increase (2831 core/2841 NSSS)
Bounds possible actual power levels Consistent with previous MUR programs
* Assessment of NSSS components, systems, and accident analyses will require a combination of evaluations and more detailed analyses depending on whether a 2%
power uncertainty was part of the current analysis basis
* BOP assessments will consist mostly of evaluations 4


SFP Criticality LAR Pre-submittal meeting is planned for July 2019 LAR is targeted for submittal in September 2019 NRC approval is requested by September 2020 (well before offloading a MUR impacted spent fuel assembly - Spring 2022)
Westinghouse Non-Proprietary Class 3        © 2018 Westinghouse Electric Company LLC. All Rights Reserved.
Special Considerations
* PAD5 will be included in effort Fuel rod temperatures/pressures generated with PAD5 Incorporated into affected Not-LOCA analysis areas (Chapter 15 transients, containment, fuel rod design criteria, fuel nuclear design and thermal/hydraulic design)
* Spent Fuel Pool Criticality As discussed, the SFP criticality analysis is to be updated The impact on the spent fuel for the MUR uprate will also be reflected in the analysis As this SFP criticality analysis LAR review will be performed in parallel with the MUR LAR review, SNC is requesting feedback regarding this logistic 5


7 Westinghouse Non
Westinghouse Non-Proprietary Class 3             © 2018 Westinghouse Electric Company LLC. All Rights Reserved.
-Proprietary Class 3
Schedule
© 2018 Westinghouse Electric Company LLC. All Rights Reserved.
* MUR LAR Pre-submittal meeting is planned for August 2019 LAR is targeted for submittal in October 2019 NRC approval is requested by July 2020 to support a Fall 2020 Unit 2 implementation
* SFP Criticality LAR Pre-submittal meeting is planned for July 2019 LAR is targeted for submittal in September 2019 NRC approval is requested by September 2020 (well before offloading a MUR impacted spent fuel assembly - Spring 2022) 6


Questions?}}
Westinghouse Non-Proprietary Class 3        © 2018 Westinghouse Electric Company LLC. All Rights Reserved.
Questions?
7}}

Latest revision as of 11:10, 20 October 2019

November 13, 2018, Joseph M. Farley Nuclear Power Plant, Public Meeting Slides Regarding Spent Fuel Pool Criticality Analyses and Measurement Uncertainty Recovery (Mur) Pre-Application Meeting
ML18311A182
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 11/07/2018
From: James Smith
Southern Nuclear Operating Co, Westinghouse
To:
Division of Operating Reactor Licensing
Williams S
References
Download: ML18311A182 (7)


Text

Westinghouse Non-Proprietary Class 3 © 2018 Westinghouse Electric Company LLC. All Rights Reserved.

Farley 1 and 2 MUR Power Uprate Jim Smith November 13, 2018 1

Westinghouse Non-Proprietary Class 3 © 2018 Westinghouse Electric Company LLC. All Rights Reserved.

Agenda

  • Purpose
  • Scope
  • Special Considerations
  • Schedule
  • Questions 2

Westinghouse Non-Proprietary Class 3 © 2018 Westinghouse Electric Company LLC. All Rights Reserved.

Purpose Inform NRC of plans to submit a power uprate -

Measurement Uncertainty Recovery Discuss Special Consideration and obtain NRC feedback Provide the important milestones for success 3

Westinghouse Non-Proprietary Class 3 © 2018 Westinghouse Electric Company LLC. All Rights Reserved.

Project Scope - NSSS Design Input

  • Core/NSSS power increasing from current 2775/2785 MWt by ~1.6-1.7%.

Depends on calculated power uncertainty by Cameron with LEFM

  • NSSS analyses will be performed at 2% increase (2831 core/2841 NSSS)

Bounds possible actual power levels Consistent with previous MUR programs

  • Assessment of NSSS components, systems, and accident analyses will require a combination of evaluations and more detailed analyses depending on whether a 2%

power uncertainty was part of the current analysis basis

  • BOP assessments will consist mostly of evaluations 4

Westinghouse Non-Proprietary Class 3 © 2018 Westinghouse Electric Company LLC. All Rights Reserved.

Special Considerations

  • PAD5 will be included in effort Fuel rod temperatures/pressures generated with PAD5 Incorporated into affected Not-LOCA analysis areas (Chapter 15 transients, containment, fuel rod design criteria, fuel nuclear design and thermal/hydraulic design)
  • Spent Fuel Pool Criticality As discussed, the SFP criticality analysis is to be updated The impact on the spent fuel for the MUR uprate will also be reflected in the analysis As this SFP criticality analysis LAR review will be performed in parallel with the MUR LAR review, SNC is requesting feedback regarding this logistic 5

Westinghouse Non-Proprietary Class 3 © 2018 Westinghouse Electric Company LLC. All Rights Reserved.

Schedule

  • MUR LAR Pre-submittal meeting is planned for August 2019 LAR is targeted for submittal in October 2019 NRC approval is requested by July 2020 to support a Fall 2020 Unit 2 implementation
  • SFP Criticality LAR Pre-submittal meeting is planned for July 2019 LAR is targeted for submittal in September 2019 NRC approval is requested by September 2020 (well before offloading a MUR impacted spent fuel assembly - Spring 2022) 6

Westinghouse Non-Proprietary Class 3 © 2018 Westinghouse Electric Company LLC. All Rights Reserved.