Line 2: |
Line 2: |
| | number = ML18019A071 | | | number = ML18019A071 |
| | issue date = 01/18/2018 | | | issue date = 01/18/2018 |
| | title = 2018/01/18 NRR E-mail Capture - Request for Additional Information - St. Lucie Inop AFW Steam Supply LAR (L-2017-LLA-0296) | | | title = Request for Additional Information - St. Lucie Inop AFW Steam Supply LAR (L-2017-LLA-0296) |
| | author name = Buckberg P H | | | author name = Buckberg P H |
| | author affiliation = NRC/NRR/DORL/LPLII-2 | | | author affiliation = NRC/NRR/DORL/LPLII-2 |
|
---|
Category:E-Mail
MONTHYEARML24290A0442024-10-15015 October 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for September 2024 ML24281A1592024-10-0707 October 2024 Acceptance Review for FPL LAR - St. Lucie Unit 2 - Fuel Methodology Changes in Support of Transition to 24- Month Fuel Cycles ML24254A2562024-09-0606 September 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for August 2024 ML24248A2422024-09-0404 September 2024 Acceptance Review for St. Lucie, Unit 2 - Relief Request (RR) 14: Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval ML24246A0152024-08-12012 August 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for July 2024 ML24194A1222024-07-11011 July 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for June 2024 ML24192A2302024-07-10010 July 2024 003 Radiation Safety Baseline Inspection Information Request ML24176A1612024-06-15015 June 2024 NRR E-mail Capture - (External_Sender) May 2024 FPL Marine Turtle Removal Monthly Report ML24150A2192024-05-29029 May 2024 (E-Mail) St. Lucie, Unit 2 - License Amendment Request, Updated Spent Fuel Pool Criticality Analysis - Acceptance Review ML24149A3532024-05-24024 May 2024 Change in Estimated Review Schedule for Nextera Common Emergency Plan Amendment ML24134A0142024-05-10010 May 2024 NRR E-mail Capture - (External_Sender) Pasl Monthly Turtle Report for April 2024 ML24122C6922024-05-0101 May 2024 NextEra Fleet EP Amendment - Demonstration Drill ML24113A0372024-04-22022 April 2024 NRR E-mail Capture - Acceptance Review - Turkey Point 3 and 4 and St. Lucie 2 - Request to Use Later Code of ASME (L-2024-LLR-0024) ML24101A2202024-04-0808 April 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for March 2024 ML24074A4262024-03-12012 March 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for February 2024 ML24177A2512024-02-12012 February 2024 Acceptance Review for RR 7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years ML24036A2152024-02-0505 February 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for January 2024 ML24031A5472024-01-13013 January 2024 NRR E-mail Capture - (External_Sender) December 2023 FPL Marine Turtle Removal Monthly Report ML24002A7272023-12-16016 December 2023 NRR E-mail Capture - (External_Sender) November 2023 FPL Marine Turtle Removal Monthly Report ML23332A0352023-11-27027 November 2023 Conversion to Improved Technical Specifications Change in Estimated Review Schedule ML23326A0252023-11-20020 November 2023 NRR E-mail Capture - (External_Sender) October 2023 FPL Marine Turtle Removal Monthly Report ML24008A1582023-11-14014 November 2023 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for October 2023 ML23254A2852023-09-11011 September 2023 NRR E-mail Capture - (External_Sender) August 2023 FPL Marine Turtle Removal Monthly Report ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23243A9182023-08-31031 August 2023 NRR E-mail Capture - Re Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23228A1482023-08-16016 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PSL2-I5-RR-01 (L-2023-LLR-0038) ML23226A0762023-08-14014 August 2023 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Units 1 and 2 - Adopt 10 CFR 50.69 (L-2022-LLA-0182) ML23226A0692023-08-12012 August 2023 NRR E-mail Capture - (External_Sender) July 2023 FPL Marine Turtle Removal Monthly Report ML23223A0152023-08-11011 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PR-10 (L-2023-LLR-0039) ML23191A1952023-07-10010 July 2023 NRR E-mail Capture - (External_Sender) June 2023 FPL Marine Turtle Removal Monthly Report ML23216A1412023-06-30030 June 2023 August 2023 RP Inspection Document Request ML23248A1292023-06-29029 June 2023 NRR E-mail Capture - St Lucie 50.69 - Additional Audit Questions ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23198A0662023-06-22022 June 2023 NRR E-mail Capture - (External_Sender) Green Turtle Nest on Canal Bank, June 2023 ML23198A0642023-06-12012 June 2023 NRR E-mail Capture - (External_Sender) Loggerhead Nest on Canal Bank, May 2023 ML23163A1732023-06-10010 June 2023 NRR E-mail Capture - (External_Sender) May 2023 FPL Marine Turtle Removal Monthly Report ML23163A1222023-05-30030 May 2023 NRR E-mail Capture - (External_Sender) Nest on Intake Canal Bank ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23137A0942023-05-17017 May 2023 NRR E-mail Capture - Audit Plan - St Lucie Plant, Units 1 and 2 - 10 CFR 50.69 LAR ML23135A0292023-05-12012 May 2023 NRR E-mail Capture - (External_Sender) April 2023 FPL Marine Turtle Removal Monthly Report ML23129A8312023-05-0808 May 2023 NRR E-mail Capture - Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23198A1592023-04-0707 April 2023 NRR E-mail Capture - (External_Sender) March 2023 FPL Marine Turtle Removal Monthly Report ML23074A2292023-03-15015 March 2023 NRR E-mail Capture - (External_Sender) February 2023 FPL Marine Turtle Removal Monthly Report ML23041A2262023-02-10010 February 2023 NRR E-mail Capture - (External_Sender) January 2023 FPL Marine Turtle Removal Monthly Report ML23065A1142023-02-0101 February 2023 NRR E-mail Capture - (External_Sender) FPL St. Lucie Plant Biological Opinion SERO-2019-03494 - Submittal ML23254A4022023-01-24024 January 2023 RP Inspection_2023-001_Document Request ML23019A0142023-01-18018 January 2023 NRR E-mail Capture - (External_Sender) Regarding St. Lucie Olive Ridley Capture 1/3/2023 ML23006A1822023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) Psl Smalltooth Sawfish Capture 1/5/23 ML23006A1882023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) December 2022 FPL Marine Turtle Removal Monthly Report 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24192A2302024-07-10010 July 2024 003 Radiation Safety Baseline Inspection Information Request ML24108A0632024-04-18018 April 2024 – Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24177A2512024-02-12012 February 2024 Acceptance Review for RR 7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years ML24177A2532024-02-12012 February 2024 Request for Additional Information Relief Request RR 7, Alternative Examination of Reactor Vessel Welds for Florida Power & Light Company, St. Lucie Nuclear Plant, Unit 1 ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23226A0762023-08-14014 August 2023 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Units 1 and 2 - Adopt 10 CFR 50.69 (L-2022-LLA-0182) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23254A4022023-01-24024 January 2023 RP Inspection_2023-001_Document Request ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22325A0692022-11-18018 November 2022 RAI Set 4 ML22270A1482022-09-26026 September 2022 SLRA Second Round RAI Letter 2 - Class 1 Fatigue (Final) ML22217A0032022-08-0404 August 2022 SLRA Second Round RAI Letter 1) ML22217A0022022-08-0404 August 2022 Email from Brian Harris (NRC) to Robert Coffey (FPL) - St. Lucie SLRA Second Round RAI Letter 1) ML22193A0872022-07-11011 July 2022 Letter RAI Set 3 (Final) ML22133A0032022-05-12012 May 2022 SLRA Rai'S Set 1 ML22101A2322022-05-0202 May 2022 Summary of the Environmental Remote Audit Related to the Review of the Subsequent License Renewal Application Enclosure RCIs and RAIs ML22094A1672022-04-0101 April 2022 2022 St. Lucie POV Inspection Information Request ML22075A1212022-03-16016 March 2022 Stl Problem Identification and Resolution (Pi&R) Information Request Final Report ML21350A4262021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Licensing Amendment Request Concerning Technical Specification Conversion to NUREG-1432, Revision 5 ML21119A3142021-04-28028 April 2021 Requests for Additional Information Regarding License Amendment Requests to Apply Risk Informed Completion Times (RICT) for the 120-Volt AC (EPID L-2020-LLA-0283) (Email) ML21063A3192021-03-0404 March 2021 Request for Additional Information Regarding Relief Request RR 15 - Extension of RPV Welds from 10 to 20 Years ML20092G3442020-04-0101 April 2020 RAIs for LAR to Revise Technical Specifications 6.8.4.o, Reactor Coolant Pump Flywheel Inspection Program ML20094G2022020-03-30030 March 2020 Request for Additional Information Regarding License Amendment Request to Adopt EAL Schemes Pursuant to NEI 99-01 (L-2019-LLA-0210) ML19225D3152019-08-13013 August 2019 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106) ML19218A2742019-08-0606 August 2019 Notification of Inspection and Request for Information ML19193A1982019-07-12012 July 2019 Emailed St. Lucie Heat Sink RFI ML19192A1372019-07-11011 July 2019 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Unit No. 2, Fall 2018 Refueling Outage Steam Generator Tube Inspection Report ML19192A1352019-06-25025 June 2019 NRR E-mail Capture - Draft Request for Additional Information - St. Lucie Plant, Unit No. 2, Fall 2018 Refueling Outage Steam Generator Tube Inspection Report ML19151A8312019-05-31031 May 2019 NRR E-mail Capture - St. Lucie Plant, Unit Nos. 1 and 2, Request for Additional Information Regarding Emergency Diesel Generator Surveillance Requirement Amendment Request ML19151A5092019-05-21021 May 2019 NRR E-mail Capture - Draft Request for Additional Information - St. Lucie Plant, Unit Nos. 1 and 2 Emergency Diesel Generator Surveillance Requirement Amendment Request ML19109A1392019-04-18018 April 2019 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding the License Amendment Request Pertaining to the Iodine Removal System ML19053A2242019-02-0101 February 2019 NRR E-mail Capture - St. Lucie Plant Unit No. 1 - Draft Request for Additional Information Related to Relief Request 6 Regarding the Refueling Water Tank Bottom Liner ML18296A2052018-10-22022 October 2018 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181) L-2018-018, St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181)2018-10-22022 October 2018 St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181) ML18197A4112018-08-0101 August 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Reduce the Number of Control Element Assemblies ML18019A0712018-01-18018 January 2018 NRR E-mail Capture - Request for Additional Information - St. Lucie Inop AFW Steam Supply LAR (L-2017-LLA-0296) ML17331B1532017-11-27027 November 2017 NRR E-mail Capture - Request for Additional Information - St. Lucie IST Relief Request #5 - PR-01 (L-2017-LLR-0113) ML17277A3692017-10-0404 October 2017 NRR E-mail Capture - Request for Additional Information - St. Lucie Rict LAR - MF5372/MF5373 ML17152A1842017-06-0101 June 2017 Request for Additional Information - RPS Rate of Change and LCO Change LAR (CACs MF9119 9120) ML16356A1432016-12-20020 December 2016 Notification of Inspection and Request for Information ML16326A0092016-11-18018 November 2016 NRR E-mail Capture - Request for Additional Information Re. Nextera/Fpl LAR to Adopt TSTF-545 - CACs MF8203, MF8204, MF8208, and MF8209 ML16308A3232016-11-0303 November 2016 NRR E-mail Capture - Request for Additional Information - St. Lucie EDG Day Tank LAR - MF8006 ML16292A8212016-10-14014 October 2016 Emergency Preparedness Inspection and Request for Information ML17003A0452016-10-11011 October 2016 NRR E-mail Capture - (External_Sender) FW: St. Lucie Response to RAI on SL2-22 SG Tube Inspection Report (MF7604) ML16244A2602016-08-26026 August 2016 Notification of Inspection and Request for Information ML16155A3502016-06-0303 June 2016 Notification of Inspection and Request for Information ML16089A0052016-03-28028 March 2016 NRR E-mail Capture - Request for Additional Information - St. Lucie Srxb Mtc Surv - MF7269 & MF7270 ML16077A1062016-03-17017 March 2016 NRR E-mail Capture - Request for Additional Information - St Lucie Vacuum Gothic LAR - MF6980/MF6981 ML16068A2612016-03-0808 March 2016 NRR E-mail Capture - Request for Additional Information - St Lucie TSTF-422 - MF6683/MF6684 2024-07-12
[Table view] |
Text
1 NRR-DMPSPEm Resource From: Buckberg, Perry Sent: Thursday, January 18, 2018 1:39 PM To: Frehafer, Ken Cc: Snyder, Mike; Mack, Jarrett (Jarrett.Mac k@fpl.com); Catron, Steve; Shoop, Undine
Subject:
Request for Additional Information - St. Lucie Inop AFW Steam Supply LAR (L-2017-LLA-0296)Attachments:
RAI - St Lucie Inop AFW Stea m Supply SBPB (L-2017-LLA-0296).pdf Ken, By letter dated September 14, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17257A300), Florida Power and Light Company (the licensee), submitted a license amendment request (LAR) to modify the St. Lucie Unit Nos. 1 and 2 Technical Specifications (TSs) for the auxiliary feedwater (AFW) system. Specifically, the licensee proposed to modify St. Lucie Unit Nos. 1 and 2 TS 3.7.1.2, "Auxiliary Feedwater System," to add a new required action for an inoperable turbine-driven AFW pump steam supply and add a new required action for an inoperable turbine-driven AFW pump steam supply concurrent with an inoperable motor-driven AFW pump. The staff has identified areas where additional information is needed to complete the review.
The NRC staff's Request for Additional Information (RAI) related to this LAR is attached. A draft version of this RAI was provided to you on January 4, 2018, and a clarification call held earlier today resulted in no changes to the draft.
Consistent with our communications earlier today, the NRC requests that the response to the attached final RAI be issued within 30 days of this email.
Thanks, Perry Buckberg Senior Project Manager phone: (301)415-1383 perry.buckberg@nrc.gov U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Mail Stop O-8B1a Washington, DC, 20555-0001
Hearing Identifier: NRR_DMPS Email Number: 103 Mail Envelope Properties (Perry.Buckberg@nrc.gov20180118133900)
Subject:
Request for Additional Information - St. Lucie Inop AFW Steam Supply LAR (L-2017-LLA-0296) Sent Date: 1/18/2018 1:39:12 PM Received Date: 1/18/2018 1:39:00 PM From: Buckberg, Perry Created By: Perry.Buckberg@nrc.gov Recipients: "Snyder, Mike" <Mike.Snyder@fpl.com> Tracking Status: None "Mack, Jarrett (Jarrett.Mack@fpl.com)" <Jarrett.Mack@fpl.com> Tracking Status: None "Catron, Steve" <Steve.Catron@fpl.com>
Tracking Status: None "Shoop, Undine" <Undine.Shoop@nrc.gov> Tracking Status: None "Frehafer, Ken" <Ken.Frehafer@fpl.com> Tracking Status: None Post Office: Files Size Date & Time MESSAGE 1462 1/18/2018 1:39:00 PM RAI - St Lucie Inop AFW Steam Supply SBPB (L-2017-LLA-0296).pdf 85086
Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:
REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST RELATED TO MODIFICATION OF THE AUXILIARY FEEDWATER SYSTEM TECHNICAL SPECIFICATIONS EPID L-2017-LLA-0296, CAC NOS. MG0237 AND MG0238 ST. LUCIE NUCLEAR PLANT, UNIT NOS. 1 AND 2 FLORIDA POWER AND LIGHT COMPANY DOCKET NOS. 50-335 AND 50-389
By letter dated September 14, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17257A300), Florida Power and Light Company (the licensee), submitted a license amendment request (LAR) to modify the St. Lucie Unit Nos. 1 and 2 Technical Specifications (TSs) for the auxiliary feedwater (AFW) system. Specifically, the licensee proposed to modify St. Lucie Unit Nos. 1 and 2 TS 3.7.1.2, "Auxiliary Feedwater System," to add a new required action for an inoperable turbine-driven AFW pump steam supply and add a new required action for an inoperable turbine-driven AFW pump steam supply concurrent with an inoperable motor-driven AFW pump.
RAI-LLA0296-SBPB-01 The licensee proposed a new TS ACTION for an inoperable AFW pump steam supply concurrent with an inoperable motor-driven AFW pump. The proposed change would establish a 48-hour Completion Time to restore either the inoperable steam supply or the inoperable motor-driven AFW pump to OPERABLE status. The licensee supported this change with the following statement from Section 3.2 of the Enclosure to the LAR:
A 48-hour completion time for an inoperable AFW pump steam supply concurrent with an inoperable motor-driven AFW pump is reasonable based on the remaining motor-driven AFW pump's capability to provide the requisite AFW flow credited in the respective Feedwater Line Break (FLB) and Main Steam Line Break (MSLB) safety analyses for St. Lucie Unit 1 and St. Lucie Unit [2] without assuming a concurrent single active failure. Hence, the proposed 48-hour completion time to restore either the inoperable steam supply or the inoperable motor-driven pump to OPERABLE status satisfies the condition specified in Technical Specification Task Force (TSTF) Traveler, TSTF-412, Revision 3,
["]Provide Actions for One Steam Supply to Turbine Driven AFW /EFW Pump Inoperable (Reference 6.2), ["] for plants with motor-driven AFW trains fully capable of mitigating postulated accidents in accordance with applicable accident analyses.
However, the staff found the ability of the motor-driven pump to provide the required AFW flow to mitigate the FLB or MSLB was not adequately supported, which is necessary to permit a 48-hour rather than a 24-hour completion time, consistent with the discussion in TSTF-412, Rev. 3.
Each St. Lucie Unit has two steam generators (SGs). The turbine-driven AFW pumps automatically supply feedwater to both SGs, but each motor-driven AFW pump automatically supplies feedwater only to its associated SG (e.g., "A" motor-driven AFW pump to "A" SG). The licensee described that normally-isolated cross-connection piping is available to enable either motor-driven pump to discharge flow to either SG, but the staff identified no statement in either the LAR or either units' updated final safety analysis report indicating this cross-connection could satisfy the flow rate and timing requirements of the AFW system for any limiting accident.
Without adequate cross-connect flow and with one turbine-driven pump steam supply and one motor-driven pump inoperable, the remaining operable equipment may not be able to provide adequate AFW flow to mitigate a FLB accident. For example, assuming the following conditions: "B" steam supply to the turbine-driven AFW pump inoperable, "B" motor-driven AFW pump inoperable, and "A" SG experiences a FLB accident; the remaining AFW equipment would not be able to provide AFW flow to the intact "B" SG because the operable "A" steam supply is connected to the faulted SG and the operable "A" motor-driven pump would deliver its flow to the faulted SG until isolated. Without adequate mitigation, assuming no additional single failure, the discussion in TSTF-412, Rev. 3, would call for a 24-hour completion time. Accordingly, either provide analysis indicating that the motor-driven pumps may be cross-connected to deliver adequate AFW flow at an acceptable time to the alternate SG for FLB accident mitigation or reduce the requested completion time for the new proposed action for one inoperable steam-supply to the turbine-driven AFW pump and, concurrently, one inoperable motor-driven AFW pump to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from the requested 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />.