ML23324A447 | 14 November 2023 | 302 Exam Approval Letter |
IR 05000261/2021301 | 19 November 2021 | NRC Operator License Examination Report 05000261/2021301 |
IR 05000354/2021011 | 30 September 2021 | Temporary Instruction 2515/194 Inspection Report 05000354/2021011 |
IR 05000333/2021005 | 1 September 2021 | Updated Inspection Plan for the James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2021005) |
IR 05000244/2021005 | 1 September 2021 | Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, Llc (Report 05000244/2021005 |
IR 05000238/2021001 | 10 August 2021 | U.S. Department of Transportation, N.S. Savannah - NRC Inspection Report 05000238/2021001 |
ML21187A223 | 29 July 2021 | Temporary Instruction 2515/194 Inspection Documentation Request |
ML21176A049 | 28 July 2021 | NRC Investigation Report I-2020-007; NRC Inspection Report 05000219/2021402 & 07200015/2021401 |
ML21088A268 | 30 March 2021 | Notification of Conduct of a Fire Protection Team Inspection |
ML21074A324 | 15 March 2021 | LLC - Licensed Operator Positive Fitness-For-Duty Test |
ML21069A143 | 10 March 2021 | Senior Reactor and Reactor Operator Initial License Examinations |
ML21041A193 | 10 February 2021 | Request for Information for a Triennial Baseline Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Inspection; Inspection Report (05000333/2021011) |
ML21032A102 | 1 February 2021 | Operator Licensing Examination Approval |
ML21019A447 | 20 January 2021 | Senior Reactor and Reactor Operator Initial License Examinations |
IR 05000244/2020301 | 1 December 2020 | R. E. Ginna Nuclear Power Plant, Initial Operator Licensing Examination Report 05000244/2020301 |
IR 05000333/2020402 | 16 September 2020 | Security Baseline Inspection Report 05000333/2020402 |
IR 05000244/2020402 | 30 July 2020 | R. E. Ginna Nuclear Power Plant: Security Baseline Inspection Report 05000244/2020402 |
IR 05000220/2020401 | 29 July 2020 | Security Baseline Inspection Report 05000220/2020401 and 05000410/2020401 |
IR 05000272/2020401 | 23 July 2020 | Nuclear Generating Station, Units 1 and 2 and Hope Creek Generating Station: Security Baseline Inspection Report 05000272/2020401, 05000311/2020401, and 05000354/2020401 (Letter Only) |
ML20188A331 | 6 July 2020 | U.S. Nuclear Regulatory Commission (NRC) Acknowledgement of Receipt of Entergy'S Response Letter to the NRC, Dated June 24, 2020, Regarding the Algonquin Incremental Market Project Pipeline |
ML20113F066 | 23 April 2020 | Safety Evaluation and Supporting Analysis Regarding the Algonquin Incremental Market Project Pipeline Near the Indian Point Energy Center, Units 2 and 3 |
ML20107F834 | 16 April 2020 | (EA-19-122) Response to Contested Notice of Violation Documented in U.S. Nuclear Regulatory Commission R.E. Ginna Inspection Report 05000244/2019010 |
IR 05000333/2020301 | 1 April 2020 | Initial Operator Licensing Examination Report 05000333/2020301 |
IR 05000443/2020401 | 10 March 2020 | Security Baseline Inspection Report 05000443/2020401 and Independent Spent Fuel Storage Installation Security Inspection Report 07200063/2020401(Letter Only) |
ML20274A092 | 7 February 2020 | NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) |
ML20274A136 | 7 February 2020 | Final Written Examination and Operating Test Outlines (Folder 3) |
ML20279A331 | 7 February 2020 | Handouts to Applicants (Folder 3) |
ML19344D023 | 9 December 2019 | Ti 2515/194 Inspection Documentation Request |
ML19322A009 | 14 November 2019 | U.S. Nuclear Regulatory Commission Acknowledgement of Disputed Cited Violation 05000244/2019010-02 |
ML19261A083 | 18 September 2019 | R. E. Ginna Nuclear Power Plant: Design Bases Assurance Inspection (Teams) Report 05000244/2019010 and Notice of Violation |
IR 05000334/2019410 | 13 August 2019 | Security Inspection Report 05000334/2019410 and 05000412/2019410 (Letter Only) |
ML19189A352 | 8 July 2019 | LLC Licensed Operator Positive Fitness-For-Duty Test |
IR 05000269/2019011 | 3 July 2019 | NRC Evaluation of Changes, Tests, and Experiments Report Number 05000269/2019011 and 05000270/2019011 and 05000287/2019011 |
ML19151A813 | 31 May 2019 | Licensed Operator Positive Fitness-For-Duty Test |
ML19120A117 | 29 April 2019 | March 6, 2019, NRC Generic Fundamentals Examination Results for Seabrook Station (Cover Letter Publicly Available, Enclosures Withheld from Public) |
ML19120A126 | 29 April 2019 | March 6, 2019, NRC Generic Fundamentals Examination for Salem Nuclear Generating Station (Cover Letter Publicly Available, Enclosures Withheld from Public) |
ML19120A135 | 29 April 2019 | March 6, 2019, NRC Generic Fundamentals Examination Results for R. E. Ginna Nuclear Power Plant, LLC (Cover Letter Publicly Available, Enclosures Withheld from Public) |
ML19079A023 | 19 March 2019 | Licensed Operator Positive Fitness-For-Duty Test |
ML19058A028 | 26 February 2019 | Response to Disputed Non-Cited Violation Documented in Salem, Units 1 and 2, Inspection Report 05000272/2018403, and 05000311/2018403 |
IR 05000293/2018501 | 6 December 2018 | Evaluated Emergency Preparedness Exercise Inspection Report 05000293/2018501 |
IR 05000220/2018411 | 20 November 2018 | NRC Security Baseline Inspection Report 05000220/2018411 and 05000410/2018411 (Letter Only) |
IR 05000317/2018010 | 19 October 2018 | Design Bases Assurance Inspection (Teams) Report 05000317/2018010 and 05000318/2018010 |
ML18285A285 | 12 October 2018 | Response to Disputed Notice of Non-Cited Violation 05000272 and 05000311/2018403-01 (Acknowledgement Letter) |
IR 05000289/2018410 | 18 September 2018 | Baseline Security Inspection Report 05000289/2018410 (Letter Only) |
ML18222A292 | 10 August 2018 | Follow-Up of Alkali Silica Reaction Open Item License Renewal Inspection Report 05000443/2018011 |
IR 05000334/2018411 | 24 July 2018 | Security Inspection Report 05000334/2018411 and 05000412/2018411 (Letter Only) |
IR 05000334/2018501 | 20 June 2018 | Evaluated Emergency Preparedness Exercise Inspection Report 05000334/2018501 and 05000412/2018501 |
ML18169A355 | 18 June 2018 | Response to Disputed Non-Cited Violation 05000334 and 05000412/2018403-02 (Acknowledgement Letter to FENOC) |
ML18150A149 | 30 May 2018 | Licensed Operator Positive Fitness-For-Duty Letter |
ML18149A055 | 25 May 2018 | Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information |