UNITED STATES NUCLEAR REGULATORY COMMISSION ust 13, 2019

SUBJECT:

BEAVER VALLEY POWER STATION - SECURITY INSPECTION REPORT 05000334/2019410 AND 05000412/2019410

Dear Mr. Penfield:

On July 25, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Beaver Valley Power Station and discussed the results of this inspection with Mr. Michael Fox, Security Manager and other members of your staff. The results of this inspection are documented in the enclosed report.

NRC inspectors documented one finding of very low security significance (Green) in this report.

This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC resident inspector at Beaver Valley Power Station.

One cross-cutting aspect was assigned to the finding in the area of Human Performance, Avoid Complacency, because FENOC did not recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes [H.12].

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I and the NRC resident inspector at Beaver Valley Power Station.

Enclosure transmitted herewith contains Sensitive, Unclassified, Non-Safeguards Information. When separated from the Enclosure, the transmittal document is decontrolled. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRCs Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).

Sincerely,

/RA/

Fred L. Bower, III, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-334 and 50-412 License Nos. DPR-66 and NPF-73 Enclosure:

Non-Public Inspection Report 05000334/2019410 and 05000412/2019410 cc w/o encl: w/o OUO-SRI: Distribution via ListServ cc w/encl: w/OUO-SRI M. Fox, Manager, Site Protection, FENOC, Beaver Valley D. Allard, State Liaison Officer, PA C. Salz, State Liaison Officer, Ohio J. Frame, State Liaison Officer, West Virginia ML19226A086 (Cover letter)

ADAMS ACCESSION NUMBER: ML19226A083 (Cover letter w/enclosure)

Cover Letter Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available Cover Letter w/ Enclosure Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRS RI/DRS RI/DRS RI/DRP RI/DRS NAME D Caron J Rey/DC J Cherubini/DC M Young F Bower DATE 08/5/2019 08/12/2019 08/12/2019 08/5/2019 08/13/2019