ML18222A292

From kanterella
Jump to navigation Jump to search
Follow-Up of Alkali Silica Reaction Open Item License Renewal Inspection Report 05000443/2018011
ML18222A292
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 08/10/2018
From: Mel Gray
Division of Reactor Safety I
To: Nazar M
NextEra Energy Seabrook
References
IR 2018011
Download: ML18222A292 (14)


See also: IR 05000443/2018011

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BOULEVARD, SUITE 100

KING OF PRUSSIA, PA 19406-2713

August 10, 2018

Mr. Mano Nazar

President and Chief Nuclear Officer

Nuclear Division

NextEra Energy Seabrook, LLC

Mail Stop: EX/JB

700 Universe Blvd.

Juno Beach, FL 33408

SUBJECT: SEABROOK STATION, UNIT NO. 1 - FOLLOW-UP OF ALKALI SILICA

REACTION OPEN ITEM LICENSE RENEWAL INSPECTION REPORT

05000443/2018011

Dear Mr. Nazar:

On May 3, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an on-site team

inspection at Seabrook Station, Unit No. 1 as part of the license renewal review process. The

scope of this inspection was to examine plant activities and documents that support the

application for a renewed license at Seabrook Station as they relate to managing the effects of

aging due to alkali silica reaction (ASR) in concrete structures. The NRC inspectors discussed

the results of this inspection with Mr. Christopher Domingos, Site Director, and other members

of your staff via a teleconference exit on June 27, 2018. The results of this inspection are

documented in the enclosed report.

The presence of ASR in Seabrook Station concrete structures was identified in 2010. The NRC

completed a license renewal team inspection in 2011, which determined that except for the ASR

issue, the inspection results supported a conclusion of reasonable assurance with respect to

managing the effects of aging in systems, structures and components identified in NextEras

license renewal application for the Seabrook Station. The team noted, at that time, NextEra

was developing programs to manage the effects of ASR on Seabrook Station concrete

structures and that additional NRC inspection was warranted once these programs were

finalized. The NRC subsequently completed two team inspections on this technical issue, and

since 2013, conducted inspections approximately every six months to evaluate NextEras

activities to develop and implement your structural aging management programs. This

inspection follows-up on the 2011 license renewal inspection.

The inspectors reviewed procedures and records related to your monitoring of the effects of

ASR in Seabrook concrete structures, observed activities, interviewed personnel, and

conducted plant walk downs of several areas to independently assess structural condition. No

findings or violations of NRC requirements were identified during this inspection.

The inspection team concluded that for the ASR issue, your staff adequately performed scoping

and screening of structures, systems, and components as required in 10 CFR 54.4(a) and

54.21, respectively, and established aging management programs as described in the license

renewal application. The inspection further concluded the documentation supporting the

application was in an auditable and retrievable form. The inspection results support the

conclusion that there is reasonable assurance that the effects of aging due to ASR in the

Seabrook systems, structures, and components will be managed through implementation of

M. Nazar 2

these programs as described in the application for a renewed license currently under review by

the NRC Office of Nuclear Reactor Regulation.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Sincerely,

/RA/

Mel Gray, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-443

License No. NPF-86

Enclosure:

Inspection Report 05000443/2018011

cc w/encl: Distribution via ListServ

ML18222A292

Non-Sensitive Publicly Available

SUNSI Review

Sensitive Non-Publicly Available

OFFICE RI/DRS RI/DRP RI/DRS

NAME NFloyd via email FBower via email MGray

DATE 8/7/18 8/7/18 8/10/18

1

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number: 50-443

License Number: NPF-86

Report Number: 05000443/2018011

Enterprise Identifier: I-2018-011-0039

Licensee: NextEra Energy Seabrook, LLC (NextEra)

Facility: Seabrook Station, Unit No. 1 (Seabrook)

Location: Seabrook, NH

Inspection Dates: 04/30/2018 - 05/03/2018 (on-site)

05/23/2018 - 06/27/2018 (in-office)

Team Lead: Niklas Floyd, Senior Reactor Inspector, Region I, DRS

Inspector: Angela Buford, Structural Engineer, NRR, DE

Approved By: Mel Gray, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) conducted a license renewal follow-up

inspection at the Seabrook Station in accordance with the Reactor Oversight Process. The

Reactor Oversight Process is the NRCs program for overseeing the safe operation of

commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

NRC inspectors from Region I and the Office of Nuclear Reactor Regulation performed on-site

inspections of the applicants license renewal activities, specifically those related to alkali-silica

reaction (ASR). The team performed the evaluations in accordance with Manual Chapter 2516,

Policy and Guidance for the License Renewal Inspection Programs, and Inspection Procedure 71002, License Renewal Inspection. With regards to ASR, the team concluded the applicant

adequately performed scoping and screening of structures, systems, and components as

required in 10 CFR 54.4(a) and 54.21, respectively, and established aging management

programs as described in the license renewal application. The team concluded that the

applicant provided documentation that supported the application and inspection process in an

auditable and retrievable form. The inspection results support the conclusion that there is

reasonable assurance that the effects of aging due to ASR in the Seabrook systems, structures,

and components will be managed through implementation of these programs as described in

the application for a renewed license currently under review by the NRC Office of Nuclear

Reactor Regulation.

No findings or more-than-minor violations were identified.

3

INSPECTION SCOPE

This inspection was conducted using the appropriate portions of the applicable inspection

procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently

approved IPs with their attached revision histories are located on the public website at

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel to assess NextEras performance and compliance with Commission rules and

regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT, AND ABNORMAL

71002 - License Renewal

Scope of Review

The NRC performed an inspection of NextEras license renewal and aging management

activities to address concrete degradation due to the effects of ASR. The purpose of this

inspection was to determine whether the actions taken by NextEra since the previous

IP 71002 inspection in 2011 were adequate to manage the effects of aging in concrete

structures due to ASR at the Seabrook Station by meeting the following three objectives:

  • To verify the applicants license renewal program, including supporting activities, are

planned or implemented in accordance with the requirements of 10 CFR 54 and the

applicants license renewal application.

  • To verify the applicant has adequate programs planned or in place to implement

aging management for the structures, systems, and components that require an

aging management review.

  • To verify the information and documentation required are retrievable, auditable and

consistent with the license renewal application and approved programs and

procedures.

Background

On May 25, 2010, NextEra submitted to the NRC its application for renewal of its operating

license for Seabrook Station, Unit No. 1 (ADAMS Accession Number ML101590099).

NextEra requested renewal of the operating license for an additional 20 years beyond the

current 40-year license, which expires on March 15, 2030. During preparations for license

renewal in the 2009 to 2010 timeframe, NextEra identified that the intrusion of moisture into

sections of walls in certain below-grade structures at the Seabrook Station could cause

potential degradation of some of the concrete as evidenced by pattern cracking. The

petrographic examination of concrete core samples subsequently confirmed that the pattern

cracking occurring in Seabrook Station structures was due to ASR. The reaction forms a gel

that can expand and cause micro-cracks in the concrete. The Seabrook Station was the

first nuclear power plant in the United States to identify the presence of the ASR in its

concrete structures.

4

On April 8, 2011, the NRC completed a license renewal inspection (ML111360432) utilizing

NRC IP 71002 as part of the review process for the license renewal application. The

inspection was conducted by a team of NRC regional experts with materials and license

renewal backgrounds. The inspection team concluded scoping and screening of non-safety

related systems, structures, and components were implemented as required in 10 CFR 54.4(a)(2), and the aging management portions of the license renewal activities were

planned or implemented as described in the license renewal application. The team further

concluded that except for the ASR issue, the inspection results supported a conclusion of

reasonable assurance with respect to managing the effects of aging in the systems,

structures, and components identified in the application. The inspection team noted that

NextEra staff were developing an initial response to the aging effects of ASR and that

investigation and testing were ongoing. As a result, the inspection team was unable to

arrive at a conclusion about the adequacy of the aging management review for the ASR

issue.

Consistent with this conclusion, the NRC staff reviewing the license application designated

as Open Item, OI 3.0.3.2.18-1, in the Seabrook Station license renewal draft Safety

Evaluation Report (ML12160A374), NRC staff concerns that NextEra had not adequately

enhanced the Structures Monitoring Program to manage the effects of ASR. NextEra

communicated plans to submit additional information to the NRC to provide for an

acceptable program to manage the effects of ASR.

At an April 23, 2012, public meeting with NextEra, NRC staff discussed their focus on the

long-term operability of the affected structures. Subsequently, by letters dated May 3 and

May 10, 2012 (ML12125A022 and ML12131A479), NextEra described the actions it would

take to address the degraded conditions as well as to ensure that Seabrook Station

continued to meet its current licensing basis as a result of the ASR issue. The NRC issued

a Confirmatory Action Letter (CAL) to confirm the actions committed to by NextEra

(ML12125A172). The NRC conducted two team inspections that comprehensively reviewed

selected procedures and records, observed activities, and interviewed station personnel

regarding the adequacy of NextEra's actions to address the impact of ASR on reinforced

concrete structures, which was documented in inspection reports dated December 3, 2012

and August 9, 2013 (ML12338A283 and ML13221A172). Based on the reviews of

NextEras actions to complete these commitments, the NRC issued a CAL closure letter on

October 9, 2013 (ML13274A670). Further significant corrective actions were in progress at

the time of the closure letter, including a planned test program of ASR-affected large scale

concrete specimens at the University of Texas, Ferguson Structural Engineering Laboratory.

On September 3, 2013, the NRC documented in a mid-cycle performance review letter to

NextEra (ML13246A107) NRC plans to continue to provide focused oversight of the testing

being conducted at the Ferguson Structural Engineering Laboratory and the continual

assessment of ASR progression in the on-site Seabrook Station concrete structures. The

NRC inspection activities were conducted using focused Problem Identification and

Resolution samples in accordance with NRC IP 71152 on a semi-annual frequency. The

following table provides a list of these inspections completed to date:

5

Inspection Report ADAMS

Date Number Accession

Number

01/30/2014 05000443/2013005 ML14030A509

05/06/2014 05000443/2014002 ML14127A376

02/06/2015 05000443/2014005 ML15037A172

08/05/2015 05000443/2015002 ML15217A256

02/12/2016 05000443/2015004 ML16043A391

05/06/2016 05000443/2016008 ML16127A155

02/08/2017 05000443/2016004 ML17040A220

08/14/2017 05000443/2017002 ML17227A018

02/12/2018 05000443/2017004 ML18043A821

05/14/2018 05000443/2018001 ML18134A222

During a plant tour on May 23, 2014, NRC inspectors identified several instances of large,

discrete cracks in the residual heat removal equipment vaults. The NRC issued a finding of

very low safety significance in an inspection report dated August 5, 2014 (ML14212A458)

because NextEra did not perform an adequate technical evaluation when it was determined

the crack sizes exceeded the quantitative limits specified in NextEra procedures. Later in

2015, NRC inspectors observed degraded seismic and fire seals that appeared to have

been caused by differential movement between adjoining concrete buildings. NextEra staff

initiated a root cause that confirmed some of the structures affected by ASR had evidence of

bulk expansion (macro-cracking and some reinforced concrete wall displacements) due to

the aggregate effect of induced micro-cracking. The bulk expansion due to ASR resulted in

building deformation and impacted some structures, systems, and components attached to

the adjoining structures as evident by deformed flexible conduit couplings and reduced

seismic isolation gaps. The building deformation (observed in structures such as the

residual heat removal equipment vaults and the containment enclosure building) and its

impact to equipment were considered a new phenomenon related to the effects of ASR, and

NextEra subsequently developed an additional plant-specific aging management program to

manage this effect.

In a report dated December 17, 2015 (ML15337A047), NRC staff from the Office of Nuclear

Reactor Regulation, Division of License Renewal, documented the results of an audit

performed at the Ferguson Structural Engineering Laboratory at the University of Texas at

Austin. The purpose of the audit was for staff to establish a clear understanding of

NextEras large-scale test program and its use as a technical basis for developing elements

of the plant-specific aging management program. Prior to the audit, the NRC staff issued

requests for additional information pertaining to various staff concerns with the current aging

management program. One of those concerns included addressing recent operating

experience concerning building deformation caused by bulk ASR expansion. Based on this

audit, the NRC staff found that additional information was still needed in order for the NRC

staff to complete its review of the aging management programs as part of the license

renewal application.

In February 2016, NextEra completed its testing of large-scale ASR-affected test specimens

at the Ferguson Structural Engineering Laboratory, and based on results from the testing

program, NextEra enhanced its Structures Monitoring Aging Management Program for both

the Alkali-Silica Reaction Monitoring and the Building Deformation Monitoring programs. On

August 9, 2016, the NRC received NextEra's updated license renewal application submittal

6

which included these updates to the aging management programs (ML16224B079). The

NRC sent several requests for additional information to which NextEra subsequently

responded. Further NRR audits were conducted as documented in reports dated

December 21, 2016 (ML16333A247), and July 26, 2017 (ML17199T383). The NRC

completed an audit of the license renewal application in March 2018 and documented the

results in a site audit report (ML18135A046).

The inspectors recognized the significant passage of time between the previous license

renewal inspection and this current inspection with regard to issues outside of ASR.

Therefore, the inspectors coordinated with NRC staff in the Division of Materials and License

Renewal to review the license renewal application supplements and the annual update

letters submitted since the 2011 inspection to identify any significant changes that would

warrant re-inspection and inclusion in the scope of this IP 71002 inspection. No issues

requiring re-inspection were identified; therefore, the scope of this inspection was focused

on the review of the open item from the license renewal inspection conducted in 2011

related to managing the aging effects of ASR at the Seabrook Station.

INSPECTION RESULTS

Observation 71002

License Renewal

NextEra staff completed activities as part of a long-term corrective action plan to address the

aging effects of ASR to include identification, evaluation, structural monitoring and corrective

actions including modifications. A significant part of NextEras activities included completion

of a large-scale testing program to better understand the impact of ASR on structural

performance and enhancements to the on-site monitoring programs through the use of

various tools such as crack gauges and through-wall expansion measurements. The NRC

conducted previous inspections of NextEras testing program and periodic on-site visits to

review the ongoing structures monitoring program implementation and results, which were

documented in publicly-available NRC inspection reports. These inspections also provided

insights into staff review of Seabrook Stations License Amendment Request 16-03, "Revise

Current Licensing Basis to Adopt a Methodology for the Analysis of Seismic Category I

Structures with Concrete Affected by Alkali-Silica Reaction," that NextEra submitted on

August 1, 2016. The NRC verified during those previous inspections that operating

experience from testing and on-site observations at the Seabrook Station were appropriately

considered for input into applicable aging management programs.

During this license renewal inspection, the inspectors reviewed the following Seabrook

Station aging management programs: Structures Monitoring, Alkali-Silica Reaction, and

Building Deformation. The inspectors noted the programs were organized such that the

Alkali-Silica Reaction and Building Deformation Aging Management Programs were both

implemented under the Structures Monitoring Program. The Structures Monitoring Aging

Management Program is the parent program to monitor the condition of structures and

structural components within the scope of the Maintenance Rule and license renewal, such

that there is not a loss of intended safety function. The Alkali-Silica Reaction Aging

Management Program monitors cracking due to expansion and reaction with aggregates in

concrete structures to evaluate the impact of ASR on the structural strength and anchorage

capacity. The Building Deformation Aging Management Program monitors location-specific

criteria, based on initial crack measurements and a building-specific structural evaluation, to

evaluate the impact of deformation on the structural function. This program also monitors and

7

evaluates the impact to functionality of systems and components that are connected and/or

adjoining to the affected structures.

The inspectors reviewed Seabrook Stations procedures for monitoring and evaluating

reinforced concrete structures susceptible to ASR degradation to verify that parameters to be

monitored and monitoring frequencies specified were being implemented in accordance with

the license renewal application. For the ASR program, the inspectors reviewed a sample of

results from in-plane expansion measurements, which were trended using combined crack

indexing and embedded pins. The frequency was verified for Tier II locations (cracking > 0.5

mm/m) to be every 30 months and for Tier III locations (cracking > 1.0mm/m) to be every

6 months. The inspectors further verified that all Tier III locations were being monitored for

through-thickness expansion, measured via borehole extensometers. The inspectors also

verified the in-plane and through-thickness expansion for all structures remained below the

established limits described in the procedure and based on the results from NextEras

large-scale testing program.

For the Building Deformation program, the inspectors reviewed a sample of location-specific

monitoring criteria (e.g., in-plane strain rate, crack widths/lengths, structural dimensions,

equipment offsets) at the frequency established from the individual structural evaluations.

The inspectors noted that all ASR-affected structures were to receive a structural evaluation

and that several evaluations were in progress with an estimated completion date of

September 2018. Once a structural evaluation was performed for building deformation, the

monitoring frequency was established based on the limiting criteria from the ASR and Building

Deformation programs. For components impacted by structural deformation, the inspectors

reviewed a sample of results from walk downs conducted at a minimum frequency of every

2 years focused on features including, but not limited to, distorted flexible couplings,

non-parallel HVAC joints, distortions or tears in seals, crimped tubing, offset hanger rods, and

misaligned pipe flanges.

The inspectors performed detailed walk downs of portions of the following structures:

  • Fuel Storage Building;
  • Containment Enclosure Ventilation Area.

The inspectors reviewed criteria from the applicable structures monitoring procedures as

described above to independently assess whether structural conditions and deficiencies such

as discrete cracks, pattern cracking, concrete pop-outs, scaling, spalling, water ingress,

coating separation or misalignment observed in these areas were previously identified by

NextEra staff and appropriately evaluated against the applicable acceptance criteria. The

inspectors accomplished this by comparing the results of their plant walk downs to the

records in the Seabrook Station structures monitoring program database for these particular

areas. The inspectors observed the database records included both quantitative

measurements and qualitative descriptions accompanied by dated photographic

documentation of the conditions by area. The inspectors independent walk downs and review

of the database records did not identify any deficiencies that were not previously identified

and evaluated by NextEra staff.

The inspectors further reviewed the condition of these areas as documented of the Seabrook

Station structures monitoring program database to verify the results of previous examinations,

8

including identified deficiencies, photographic records and corrective actions, were

documented, retrievable, and provided an auditable record of the conditions, trends and

action taken. Based on these reviews, the inspectors concluded that NextEra staff were

implementing their established processes in accordance with the plant procedures and

structural deficiencies were being appropriately tracked, trended, and dispositioned.

The inspectors identified the following observations that were discussed with NextEra staff:

1. The inspectors identified several instances where the aging management programs

docketed to the NRC as part of the license renewal application were not consistent with

Seabrook Stations on-site processes and procedures. For example, the docketed

Building Deformation Program in the license renewal application described the

consideration of moment redistribution and the 100-40-40 percent rule for a detailed

structural evaluation, however these methods were appropriately not utilized at Seabrook

Station or included in their implementing procedures. These differences between the

docketed aging management programs in the license renewal application and

implementing procedures reflected changes made to their procedures by NextEra staff as

a result of responses to NRC requests for information. These inconsistencies were also

identified during the NRC audit in March 2018, and required an update to the license

renewal application. The inspectors discussed the license renewal application documents

in question with NextEra staff and determined that NextEra staff was in the process of

making appropriate changes. Subsequent to the on-site inspection dates, NextEra

submitted the revised aging management programs for ASR and Building Deformation to

the NRC on May 18, 2018 (ML18141A785). The inspectors completed an in-office

inspection of the submittal and found the docketed and updated Structures Monitoring

Aging Management Programs to be consistent with the implemented processes and

procedures reviewed during the on-site inspection between April 30 and May 3, 2018.

2. The inspectors identified that raw data for the Invar rods located in the Residual Heat

Removal Vaults was being collected, but the data was not translated into units useful for

monitoring and trending (i.e., inches displacement). The rods were installed to aid in

measuring the vertical displacement of the vaults over a span of multiple building

elevations. The inspectors noted that vertical displacement of the vaults was a parameter

identified in Appendix C of the Structures Monitoring Program Manual with a threshold

limit requiring periodic monitoring. Based on discussions with NextEra staff, the

inspectors understood that there was an action being tracked (AR 02148021, Assignment

No. 22) to develop a procedure to correlate the recorded electronic data to unit length and

that the precision of the measurement technique would then be assessed against the

standard specified by the vendor. The inspectors concluded that the monitoring and

trending of the Invar data was not critical to detect degradation because a review of the

other monitored parameters for the residual heat removal vault would adequately detect

degradation in a timely manner.

Based on the previous NRC inspections of ASR-related issues completed to date and the

results of this follow-up license renewal inspection, the NRC concluded that for the ASR

issue, NextEra staff adequately performed scoping and screening of structures, systems, and

components as required in 10 CFR 54.4(a) and 54.21, respectively, and established aging

management programs as described in the license renewal application. The inspection

further concluded the documentation supporting the application was in an auditable and

retrievable form. The inspection results support the conclusion that there is reasonable

assurance that the effects of aging due to ASR in the Seabrook systems, structures, and

9

components will be managed through implementation of these programs as described in the

application for a renewed license currently under review by the NRC Office of Nuclear

Reactor Regulation.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On May 3, 2018, the inspectors debriefed the preliminary license renewal inspection results

to Mr. Eric McCartney, Regional Vice President, and other others of NextEra Staff.

  • On June 27, 2018, the inspectors telephonically conducted an exit meeting of the license

renewal inspection results with Mr. Christopher Domingos, Site Director, and other members

of NextEra staff.

10

DOCUMENTS REVIEWED

Procedures

ES1807.031, Inservice Inspection Procedure Primary Containment Section XI IWL Program,

Revision 04

PI-AA-102-1001, Operating Experience, Revision 19

PI-AA-104-1000, Condition Reporting, Revision 17

SMP2.1, Structures Monitoring Inspections, Data Collection, and Evaluation, Revision 04

SMP3.1, ASR Monitoring Walkdowns, Data Collection, and Evaluation, Revision 02

SMP4.1, Building Deformation Monitoring Walkdowns, Data Collection, and Evaluation,

Revision 05

SMP5.1, Equipment Impacted by Structural Deformation Monitoring Walkdowns, Data

Collection, and Evaluation, Revision 03

SMPM, Structures Monitoring Program Manual, Revision 05 and 06

Condition Reports

00207755

00392697

02014325

02261159

02262440*

  • initiated in response to inspection

Work Orders

40509687

40515022

40537747

40546928

Miscellaneous

2016 ASME IWL Examination Results, dated December 8, 2016

2016 IWL Containment Concrete Examination Plan, dated September 22, 2016

Extensometer Data of Through Thickness Expansions, dated May 2, 2018

FP 101154, March 2017 - Joint Width Measurements at Twenty-Five Seismic Isolation Joint

Locations, Revision 0

FP101203, 2017 Tier 2 Inspections - ASR Inspections and Cracking Index Measurements on

Concrete Structures, Revision 0

FP101204, 2017 Tier 2 Inspections - Measurements for ASR Expansion on Concrete

Structures, Revision 0

FP101229, December 2017 Tier 3 Inspections - ASR Inspections and Cracking Index

Measurements on Concrete Structures, Revision 0

FP101230, December 2017 Tier 3 Inspections - Measurements for ASR Expansion on

Concrete Structures, Revision 0

LRAP-ASR, Aging Management Program Basis Document for Alkali-Silica Reaction (ASR)

Monitoring Program, Revision 4

LRAP-BD, Aging Management Program Basis Document for Building Deformation Monitoring

Program, Revision 1

LRAP-S002, Aging Management Program Basis Document for ASME Section XI,

Subsection IWL, Revision 2

11

LRAP-S006, Aging Management Program Basis Document for Structures Monitoring Program,

Revision 1

SBK-L-17180, Supplement 58 - Revised Alkali-Silica Reactor Aging Management Program,

dated November 3, 2017

SBK-L-18028, Supplement 60 - Response to Final Requests for Additional Information for the

Safety Review of the Seabrook Station License Renewal Application - ASME Section XI,

Subsection IWL Program, dated February 28, 2018

SMP Program Health Reports from 1QTR 2013 to 2QTR 2018

Status of Building Deformation Structural Evaluations, dated 5-23-2018

Structures Monitoring Program Inspection Reports for A/B RHR Equipment Vaults, dated

April 30, 2018