IR 05000317/2018010

From kanterella
Jump to navigation Jump to search
Design Bases Assurance Inspection (Teams) Report 05000317/2018010 and 05000318/2018010
ML18292A579
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 10/19/2018
From: Mel Gray
Division of Reactor Safety I
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2018010
Download: ML18292A579 (13)


Text

October 19, 2018

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT - DESIGN BASES ASSURANCE INSPECTION (TEAMS) REPORT 05000317/2018010 AND 05000318/2018010

Dear Mr. Hanson:

On October 5, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Calvert Cliffs Nuclear Power Plant (CCNPP), Units 1 and 2. The NRC inspectors discussed the results of this inspection with Mr. Todd Tierney, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any findings or more-than-minor violations.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRCs Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Mel Gray, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 50-317 and 50-318 License Nos. DPR-53 and DPR-69

Enclosure:

Inspection Report 05000317/2018010 and 05000318/2018010

Inspection Report

Docket Numbers: 50-317 and 50-318 License Numbers: DPR-53 and DPR-69 Report Numbers: 05000317/2018010 and 05000318/2018010 Enterprise Identifier: I-2018-010-0013 Licensee: Exelon Generation Company, LLC Facility: Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Location: Lusby, MD Inspection Dates: September 17, 2018, through October 5, 2018 Inspectors: J. Schoppy, Senior Reactor Inspector, Division of Reactor Safety (DRS), Team Leader J. Lilliendahl, Senior Emergency Response Coordinator, DRS M. Orr, Reactor Inspector, DRS S. Pindale, Senior Reactor Inspector, DRS C. Baron, NRC Mechanical Contractor S. Kobylarz, NRC Electrical Contractor Approved By: M. Gray, Chief Engineering Branch 1 Division of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelons performance at

Calvert Cliffs Nuclear Power Plant Units 1 and 2 by conducting a design bases assurance inspection in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

No findings or more-than-minor violations were identified.

INSPECTION SCOPES

This inspection was conducted using the appropriate portions of the inspection procedure in effect at the beginning of the inspection unless otherwise noted. Currently approved inspection procedures with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the inspection procedure requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase. The team reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The team evaluated the following components, permanent modifications, and operating experience during the weeks of September 17, 2018, and October 1, 2018.

For the components, the team reviewed the attributes listed in IP 71111.21M, Appendix A, Component Review Attributes, such as those listed below. Specifically, the team evaluated these attributes as per 71111.21M, Appendix B, Component Design Review Considerations and 71111.21M, Appendix C, Component Walkdown Considerations. Specific documents reviewed are listed in the Documents Reviewed section.

Components ===

  • Unit 2 No. 21 High Pressure Safety Injection Pump o Material condition and installed configuration (e.g., visual inspection/walkdown)o Normal, abnormal, and emergency operating procedures o Consistency among design and licensing bases and other documents/procedures o System health report, maintenance effectiveness and records, and corrective action history o Equipment/environmental controls and qualification o Design calculations o Surveillance testing and recent test results o System and component level performance monitoring o Equipment protection from fire, flood, and water intrusion or spray o Heat removal cooling water and ventilation The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
  • Unit 1 No. 11 125 Vdc Battery o Material condition and installed configuration (e.g., visual inspection/walkdown)o Normal, abnormal, and emergency operating procedures o Consistency among design and licensing bases and other documents/procedures o System health report, maintenance effectiveness and records, and corrective action history o Operator actions o Design calculations o Surveillance testing and recent test results o Environmental conditions o Contactor and fuse ratings; Component adequacy for minimum voltage o Equipment protection from fire, flood, and water intrusion or spray o Heat removal cooling water and ventilation The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electric Loads, and As-Built System.
  • Unit 1 No. 14 4160V Bus o Material condition and installed configuration (e.g., visual inspection/walkdown)o Normal, abnormal, and emergency operating procedures o Consistency among design and licensing bases and other documents/procedures o System health report, maintenance effectiveness and records, and corrective action history o Control logic o Design calculations o Surveillance testing and recent test results o Equipment protection (sealing of cable and conduits)o Environmental conditions o Protection coordination; Load in-rush and full load current o Range, accuracy, and setpoint of installed relays o Equipment protection from fire, flood, and water intrusion or spray The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electric Loads, and Motor Control Centers (MCCs).
  • Unit 1 Containment Sump Recirculation Valve 1-MOV-4144 o Material condition and installed configuration (e.g., visual inspection/walkdown)o Normal, abnormal, and emergency operating procedures o Consistency among design and licensing bases and other documents/procedures o System health report, maintenance effectiveness and records, and corrective action history o Equipment/environmental controls and qualification o Operator actions o Design calculations o Surveillance testing and recent test results o Equipment protection (sealing of cable and conduits)o Equipment protection from fire, flood, and water intrusion or spray The team used Appendix B guidance for Valves, Instrumentation, Cables, Electric Loads, and As-Built System.

Component, Large Early Release Frequency (1 Sample)

  • Unit 2 Containment Penetration Room Ventilation System o Material condition and installed configuration (e.g., visual inspection/walkdown)o Normal, abnormal, and emergency operating procedures o Consistency among design and licensing bases and other documents/procedures o Maintenance effectiveness and records, and corrective action history o Operator actions o Design calculations o Surveillance testing and recent test results o Environmental conditions o Equipment protection from fire, flood, and water intrusion or spray o Heat removal cooling water and ventilation The team used Appendix B guidance for Instrumentation, Motor Control Centers (MCCs),and As-Built System.

Permanent Modifications (5 Samples)

  • ECP-14-000064; ESR-13-000829 - 4kV Normal Incoming Supply Feeder Breaker Modification
  • ECP-14-000159: AFW Emergency Ventilation System Upgrade
  • ECP-15-000727: ESR-15-002466 - Provide Engineering to Raise RAS Setpoint
  • ECP-16-000353: ESR-16-000050 - Enable RWT Outlet MOVs 4142 and 4143 to Close Automatically on a RAS
  • ECP-16-000462: Update Fairbanks Morse Trip Circuit Design

Operating Experience (3 Samples)

  • Prairie Island 2 10CFR21 (2017-45-00), EDG High Crankcase Pressure Switch Mounting Bracket Fastener System Failure, dated September 14, 2017
  • Report of Defect per 10CFR21, Basler Electric SBSR Automatic Voltage Regulator Card Solder Joints, dated September 21,

INSPECTION RESULTS

No findings or more-than-minor violations were identified.

EXIT MEETINGS AND DEBRIEFS

The team verified no proprietary information was retained or documented in this report.

  • On October 5, 2018, the team presented the Design Bases Assurance Inspection (Teams)results to Mr. Todd Tierney, Plant Manager, and other members of Exelon staff.

DOCUMENTS REVIEWED

71111.21M - DESIGN BASES ASSURANCE INSPECTION (TEAMS)

Audits and Self-Assessments

04058864, Readiness Review for 2018 NRC Design Bases Assurance Inspection Self

Assessment, dated 6/1/18

Calculations

95-0188, Seismic II/I Evaluation of ILRT Piping to Containment Penetration #50, Revision 0

A01080.F02-002, Pressure Locking Thrust Calculation, Revision 1

CA0772, AC Load Flow Study, Revision 2

CA04079, Comparison of Available and Required NPSH for the Safety Injection and

Containment Spray Pumps during Post-RAS Operation, Revision 0

CA04691, Circulating Water Flooding in the Turbine Building through a Ruptured Expansion

Joint, Revision 0

CA07773, AFW Pump Room Cooler Sizing, Revision 0

CA10206, Refueling Water Tank Level RAS Setpoint Determination, Revision 0

E-85-010, 125VDC Battery 01, 11, 12, 21 and 22 Fault Current Calculation, Revision 2

E-87-009, 125VDC System Short-Circuit Review, Revision 1

E-89-005, SBO & LOCA Battery Duty Cycle - Bus 11, Revision 4

E-89-042, Voltage Drop in DC Systems, Revision 4

E-90-033, Master Fault Calculation, Revision 4

E-90-038, MOV Minimum Voltages Lasting More than 5 Seconds, Revision 11

E-90-071, 4kV Bus 14 Protective Devices, Revision 6

I-94-003, Refueling Water Tank Level(s) and Capacity, Revision 4

M-91-044, MOV Weak Link Analysis, Revision 2

M-90-193, Flood Heights Resulting from a Pipe Break in the Turbine Building, Revision 0

M-91-197, Maximum Line and Differential Pressure Valves 1 & 2-MOV-4144 & 4145 May

Experience During Operation, Revision 0

Completed Surveillance, Performance, and Functional Tests

2013-29, Unit 2 Integrated Leakage Rate Test Report, dated 5/8/13

OP-6, PreStartup Checkoff, performed 3/15/18

STP-M-152-1, 11 Station Battery Weekly Check, performed 8/30/18

STP-M-352-1, 11 Station Battery Quarterly Check, performed 6/23/16, 9/22/16, 12/21/16,

3/23/17, 6/22/17, 9/21/17, 12/19/17, 3/22/18, and 6/21/18

STP M544A-2, #21 Penetration Room Exhaust Filter Test, performed 4/6/18

STP M5445-2, #22 Penetration Room Exhaust Filter Test, performed 5/8/18

STP-M-552-1, 11 Station Battery Service Test, performed 11/5/13, 4/1/16, and 4/9/18

STP M-651A-2A, SIAS B-10 Trip Bypass for 2A Diesel Generator, performed 7/31/18

STP M-651A-2B, SIAS B-10 Trip Bypass for 2B Diesel Generator, performed 1/16/15 and

5/16/17

STP M-651C-1B, SIAS B-10 Trip Bypass for 1B Diesel Generator, performed 12/6/16

STP O-4B-1, B Train Integrated Engineered Safety Features Test, performed 3/17/18

STP O-5A21-2, 21 Auxiliary Feedwater Pump Quarterly Surveillance Test, performed 7/25/18

STP O-7A-1, "A" Train Engineered Safety Features Logic Test, performed 5/1/18

STP O-7B-2, B Train Engineered Safety Features Logic Test, performed 10/20/17

STP O-7C-2, A Train Engineered Safety Features Logic Test, performed 5/3/18

STP O-14A-2, A Train Safety Injection, Containment Spray, and SDC Gas Accumulation Test,

performed 7/5/18

STP O-55-2, Unit 2 Containment Integrity Verification Mode 1-4, performed 7/30/18

STP O-70-2, Monthly Test of "A" Train Containment Cooling Units, Iodine Removal Units, &

Penetration Room Exhaust Filter, performed 5/22/18

STP O-71-2, Monthly Test of "B" Train Containment Cooling Units, Iodine Removal Units, &

Penetration Room Exhaust Filter, performed 6/4/18

STP O-73G-2, HPSI Pump Large Flow Test, performed 2/19/17

STP O-731A-2, A-Train HPSI Pump and Check Valve Operability Test, performed 8/1/18

STP XM-503-1 Calibration Check of #14 4KV Bus LOCI and Shutdown Sequencer, performed

3/15/16

TURB-04, AFW Turbine Overspeed Trip Adjustment, performed 3/17/18

Completed Preventive Maintenance, Calibrations, and Inspections

1-44-2-O-Q, Condensate Level Switch, performed 4/3/18

2-44-2-O-Q, Condensate Level Switch, performed 2/22/18

Initial Scoping Report 0027, Aging Related Degradation Inspection Check List for Identification

of Aging Effects, Unit 2 5 Fan Room, dated 1/4/11

Corrective Action Issue Reports (IRs)

4-024-386 1856779 2580916 4033503 4154234

2009-6043 1857138 2581489 4054408 4155119

2009-6251 2010203 2581500 4056915 4161927

2009-6252 2402107 2589648 4058864 4170441*

2014-0396 2409006 2595124 4063744 4175196*

1700131 2454706 2633221 4064642 4175295*

1700348 2464168 2639867 4065747 4177713*

1786965 2482579 2644934 4090677 4178917*

1803213 2494780 2668740 4106197 4179072*

1803587 2497552 2676847 4111139 4179914*

1803588 2498947 2682276 4113435 4179941*

1803624 2528973 2689863 4113450 4180135*

1803831 2552315 2703487 4113717 4180558*

1851368 2552673 2714272 4114625 4180563*

1852812 2554032 3980419 4116170 4180608*

1855691 2555303 4007684 4130071

1856563 2574382 4025294 4144777

1856715 2574385 4029406 4149542

  • IR written as a result of this inspection

Drawings

61-076-B, Schematic Diagram High Pressure Safety Injection Pump 13, Revision 6

2083-34, Terry Steam Turbine, Revision 1

2103-0001, High Pressure Safety Injection Pump Outline Dimension, Revision 4

2103-0014, Piping-Bearing and Stuffing Box w/Seal Circulation, Revision 5

33810, High Pressure Safety Injection Pump Performance Curve, dated 12/19/69

60307, Area & Equipment Drains Containment & Aux. Bldg. Unit 1 Plan at El 27, Revision 8

60710 Sh.1, Component Cooling System, Revision 46

60722 Sh. 2, Auxiliary Building Ventilation System, Revision 48

60722 Sh. 3, Auxiliary Building Ventilation System, Revision 17

60723 Sh. 2, Ventilation Systems Containment Turbine and Penetration Rooms, Revision 38

60731 Sh. 1, Safety Injection and Containment Spray Systems, Revision 94

60733 Sh. 3, Miscellaneous Drain & Sump Piping Turbine & Diesel Bldg. and Yard, Revision 64

61001 Sh. 1, Electrical Main Single Line Diagram, Revision 48

61005, Meter and Relay Diagram 4KV System Unit Buses 11 and 14, Revision 36

61022 Sh. 1, Single Line Diagram 120VAC Vital System, Revision 57

61024 Sh. 1, Single Line Diagram 125VDC Vital System Bus 11, Revision 57

61024 Sh. 2, Single Line Diagram 125VDC Vital System Bus 14, Revision 3

61024 Sh. 3, Single Line Diagram 125VDC Vital System Bus 15, Revision 3

61071 Sh. 7, Schematic Diagram 4KV Bus 14 Feeder Breaker 152-1401, Revision 19

61071 Sh. 8, Schematic Diagram 4KV Bus 14 Feeder Breaker 152-1414, Revision 20

61076 Sh. 4, Schematic Diagram High Pressure Safety Injection Pump 12, Revision 18

61076 Sh. 7, Schematic Diagram High Pressure Safety Injection Pump 13, Revision 17

61076 Sh. 30B, Schematic Diagram Reactor Safeguards Containment Sump Discharge Valve

1MOV4144, Revision 4

61076 Sh. 31, Schematic Diagram Reactor Safeguards CS & SI Pumps Recirc Valve

1MOV659, Revision 18

61740 Sh. 1, Containment Liner Plan, Elevation and Penetrations, Revision 22

61740 Sh. 2, Containment Structure Penetrations, Revision 8

2151 Sh. 1, Appendix R Separation Requirements Aux. Bldg. & Containment Structure Floor

Plan at El. 27, Revision 10

2731 Sh. 1, Safety Injection and Containment Spray Systems, Revision 84

63076 Sh. 31, Reactor Safeguards CS and SI Pumps, Recirc Valves 2MOV659, Revision 14

63076 Sh. 31A, Reactor Safeguards CS and SI Pumps, Recirc Valves 2MOV660, Revision 2

64311, Simplified System Drawing - Safety Injection and Containment Spray, Revision 14

64316, Containment and Penetration Room Ventilation SL-065A, Revision 12

84311, Safety Injection and Containment Spray System, Revision 15

ECP-16-0462-CN-001, Update Fairbanks Morse EDG Trip Circuit Design, Revision 0

ECP-16-0462-CN-006, Update Fairbanks Morse EDG Trip Circuit Design, Revision 0

ECP-16-0462-PCN-1002-CN-005, Update Fairbanks Morse EDG Trip Circuit Design, Revision 0

N2010-FCU-4-FAB Sh. 5, Auxiliary Feedwater Pump Room Emergency Cooler/Fan Coil Unit

Fabrication Drawing, Revision 1

Engineering Evaluations

1MOV4144, MIDACALC Results - AC Motor Operated GL96-05 Gate Valve, Revision 2

Comments on Calculation CA07773, AFW Pump Room SR Ventilation Gothic Evaluation and

Unit Sizing, dated 4/27/12

ECP-12-000318, AFW Pump Room Emergency Ventilation System, Revision 0

ECP-14-000064 Form 7 and 7A, Design Change Technical Evaluation, Revision 3

ECP-14-000064 Form 9, Installation Testing Instructions, Revision 4

ECP-14-000159-015-7-01, Form 7, Design Change Technical Evaluation, Revision 3

ECP-14-000159-015-7A-01, Form 7A, Design Change Technical Evaluation Continuation,

Revision 8

ECP-14-000159-5059-01, AFW Pump Room Emergency Ventilation System Upgrade 50.59

Screen, Revision 9

ECP-15-000023, Technical Evaluation for Connection Resistance Methodology, Revision 0

ECP-15-000727, Raise RAS Setpoint, Revision 2

ECP-16-000353, Enable RWT Outlet MOVs 4142 and 4143 to Close Automatically on a RAS,

Revision 0

ECP-16-000462, Update Fairbanks Morse Trip Circuit Design, Revision 0

ECP-17-000523, Vortexing in the Refueling Water Tank Technical Evaluation, Revision 0

ES-001, Flooding, Revision 5

ES-034, Electrical Device Settings, Revision 1

ES199801327, MOV Pressure Locking Evaluation, Revision 0

Operability Evaluation 17-002, 2CV5171: 21 ECCS Cooler Outlet Control Valve, Revision 0

Project No. 11562-061, AFW Pump Room Elevated Temperature Issue - NRC Comment

Resolution, Revision 0

QL00847, Barrier Function Table, Revision 2

SE00558, Automatic Closure of the RWT Outlet Valve MOVs 50.59 Evaluation, Revision 0

Maintenance Work Orders

C12023668 C91408624 C92543727 C92967907 C93609295

C20072161 C91426157 C92813807 C93110332 C93622647

C20074962 C91909242 C92935353 C93445185 C93640623

C20074963 C91910467 C92957877 C93466890 C93644323

C20083624 C91944763 C92957878 C93476179 C93644324

C90728304 C91945787 C92957879 C93509570

C90767769 C92413803 C92957880 C93549452

Miscellaneous

004, 4160 VAC Electrical Power Distribution System Description, Revision 3

2, Auxiliary Building Ventilation System Description, Revision 7

2-1401, CCNPP Protective Relaying Setting Sheet, Revision 3

2-1410/2/SB2, CCNPP Protective Relaying Setting Sheet, Revision 2

2-1414, CCNPP Protective Relaying Setting Sheet, Revision 3

A116, NRR Letter: Request for Additional Information Regarding Generic Letter 2004-02, dated

7/23/10

Fairbanks Morse Owners Group, Maintenance Guidelines, Voltage Regulator and Excitation

System Maintenance Recommendations, Revision 4

Master Calibration Data Package for 2-PS-4779, dated 2/3/17

Normal and Special (Abnormal) Operations Procedures

1C10-ALM, ESFAS 13 Alarm Manual, Revision 51

1C19-ALM, 13KV & 4KV Essential Feeder Bkrs Contr Board Alarm Manual, Revision 40

1C62/2C62/2C61, 1B/2A/2B Diesel Generator Alarm Manual, Revision 10

AOP-3B, Abnormal Shutdown Cooling Conditions, Revision 30

AOP-71, Loss of 4KV, 480 Volt or 208/120 Volt Instrument Bus Power, Revision 33

EOP-3, Loss of All Feedwater, Revision 23

EOP-5, Loss of Coolant Accident, Revision 30

EOP-8, Functional Recovery Procedure, Revision 41

OI-3A, Safety Injection and Containment Spray, Unit 2, Revision 35

OI-11A, Condensate System, Revision 43

OI-21A, 2A Diesel Generator Operating Instructions, Revision 25

OI-22G, Penetration Room Exhaust System, Revision 6

OI-26A, 125 Volt Vital DC, Revision 21

OI-27C, 4.16 KV System, Revision 28

OI-32A, Auxiliary Feedwater System, Unit 1, Revision 39

OI-32A, Auxiliary Feedwater System, Unit 2, Revision 32

OP-6, PreStartup Checkoff, Revision 53

Operating Experience

NRC Information Notice 2014-03: Turbine-Driven Auxiliary Feedwater Pump Overspeed Trip

Mechanism Issues, dated 2/25/14

Report of Defect per 10CFR21, Basler Electric SBSR Automatic Voltage Regulator Card Solder

Joints, dated 9/21/07

Procedures

BUS-014K, 4 KV Buses 13 and 14 Inspection, Testing and Cleaning, Revision 1

E-10, Testing and Adjustment of Agastat Relays, Revision 5

ER-AA-200-1001, Equipment Classification, Revision 4

ER-CA-450, Structure and System Walkdowns, Revision 0

FTE-59, Periodic Maintenance, Calibration and Functional Testing of Protective Relays,

Revision 8

FTM-11, Rotating Equipment Vibration Monitoring, Revision 3

HVAC-03, Inspection and Replacement of V-Belts, Revision 8

LS-AA-104, Exelon 50.59 Review Process, Revision 10

LS-AA-104-1000, 50.59 Resource Manual, Revision 12

MN-1-209, Predictive Maintenance Program, Revision 7

NSWP-S-06, Core Drilling, Revision 1

OP-CA-102-106, Operator Response Time Program at Calvert Cliffs, Revision 6

TURB-04, AFW Turbine Overspeed Trip Adjustment, Revision 5

Risk and Margin Management

Plant Risk Information e-Book for Calvert Cliffs Nuclear Power Plant, dated 3/1/17

Risk-Informed Inspection Notebook for Calvert Cliffs Nuclear Power Plant Units 1 and 2,

Revision 2.1a

System Health Reports, System Walkdowns, & Trending

HPSI Pump IST Trend Data, dated 1/20/98 - 2/6/18

Auxiliary Feedwater (System 036) System Health Report, dated 7/25/18

High Pressure Injection (System 052) System Health Report, dated 7/23/18

MRFF/MPFF Report Data, 2013 - 2017

Unit 1 and Unit 2 AFW Pump Room Temperature Logs, 7/31/17 - 8/10/18

Vendor Technical Manuals & Specifications

2400-206-1006, GE Magne-Blast Circuit Breaker Instructions GEI-88771D, Revision 0

15138-002-1001, Installation and Operating Instructions for GNB Lead-Calcium Batteries,

Revision 8

ES200800209, Borg-Warner High Pressure Heat Exchanger, dated 11/1/84

Installation, Operation and Maintenance for Bingham Pump Type MSD, dated 11/1/84

VTD 12083-010-1017, Terry Corporation Std Instructions, Section 7, dated 12/9/91