ML20098G627 | 27 September 1984 | Forwards Responses to 840617 Request for Addl Info in Order to Complete Review of Facility Site Stabilization Plan.W/Two Oversize Maps.Aperture Cards Available in PDR | |
ML20095E397 | 16 August 1984 | Forwards Duke Power Co & North Carolina Municipal Power Agency 1 1983 Annual Repts | |
LG-84-332, Forwards Most Recent Aerial Photographs of Site for Review of Stabilization Plan.W/O Encl | 24 April 1984 | Forwards Most Recent Aerial Photographs of Site for Review of Stabilization Plan.W/O Encl | |
ML20078C203 | 21 September 1983 | Requests Cancellation of CPPR-167,CPPR-168 & CPPR-169 Based on Current & Predicated Economic Conditions.Stabilization Plan Encl | |
LG-83-314, Responds to NRC Requiring Detailed Analysis of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pumps. Analysis Will Not Be Submitted,Due to Indefinite Delay in Const of Facility | 7 April 1983 | Responds to NRC Requiring Detailed Analysis of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pumps. Analysis Will Not Be Submitted,Due to Indefinite Delay in Const of Facility | |
LG-83-163, Forwards Amend 19 to Duke Power Nuclear Guides.Amend 20 Will Be Forwarded in Apr 1983 | 18 February 1983 | Forwards Amend 19 to Duke Power Nuclear Guides.Amend 20 Will Be Forwarded in Apr 1983 | |
LG-83-049, Forwards Response to 821210 Request for Addl Info on IE Bulletin 81-03, Flow Blockage of Cooling Water to Safety Sys Components by Corbicula Sp (Asiatic Clam) & Mytilus Sp (Mussel). Monitoring Program for Clams to Be Established | 17 January 1983 | Forwards Response to 821210 Request for Addl Info on IE Bulletin 81-03, Flow Blockage of Cooling Water to Safety Sys Components by Corbicula Sp (Asiatic Clam) & Mytilus Sp (Mussel). Monitoring Program for Clams to Be Established | |
ML20063E652 | 24 August 1982 | Forwards Util & Nc Municipal Power Agency Annual Financial Repts for 1981 | |
ML20062K387 | 20 May 1982 | Forwards First Quarter 1982 Yellow Book Updates Re Const Status | Hydrostatic |
ML20038D136 | 3 November 1981 | Responds to NRC 811014 Ltr Re Violations Noted in IE Insp Repts 50-491/81-03,50-492/81-03 & 50-493/81-03.Corrective Actions:Gas Cans Have Been Emptied & Placed in Motor Pool Storage Area | |
ML20009D900 | 8 July 1981 | Responds to IE Bulletin 81-03 Re Blockage of Cooling Water to Safety Sys Components by Clams & Mussels.Provisions Will Be Made to Minimize Introduction of Clams Into Raw Water Sys.Fifteen Manhours Expended in Preparation of Bulletin | |
ML20004C256 | 28 May 1981 | Requests Authorization to Use ASME Code Cases 1481-2,1592-14 & 1644-8 in Fabrication of Primary Sys Components for Facilities | |
ML19347D349 | 12 March 1981 | Responds to NRC 810223 Request for Addl Info Re Util Plans for Facilities.Completion of Cherokee 1 & 2 Has Been Indefinitely Delayed.Commercial Operating Dates for Cherokee 3 & Perkins 1,2 & 3 Have Not Been Determined | |
ML19347D031 | 4 March 1981 | Forwards 810224 Press Release Re Delay of Facility Completion.Financial Situation Has Pushed Facility Completion Into Indefinite Future | |
ML20008E762 | 24 February 1981 | Forwards PWR Const Milestones & Activities for McGuire 1 & 2,Catawba 1 & 2 & Cherokee 1.Key Event Dates Provided | |
ML20003C289 | 11 February 1981 | Responds to IE Bulletin 80-23, Failures of Solenoid Valves Mfg by Valcor Engineering Corp. Bulletin Does Not Apply | |
ML19345F363 | 5 February 1981 | Forwards Evacuation Time Estimates & Color Overlay Site Map, Per Discussions w/P81 Project Manager.W/O Site Map | Siren |
ML19345G080 | 27 January 1981 | Forwards Revision 1 to Response Re IE Bulletin 79-14 Revision 1,Suppl 2, Seismic Analysis for As-Built Safety-Related Piping Sys. Describes Program Which Will Give Assurance That Design Documents Reflect Sys Conditions | |
ML19351F985 | 27 January 1981 | Responds to IE Bulletin 80-21, Valve Yokes Supplied by Malcolm Foundry Co,Inc. No safety-related Valves Using Specified Valve Yokes Are Used | |
ML20002B917 | 11 November 1980 | Forwards Supplemental Responses to NRC 801016 Ltr Re Violations Noted in IE Insp Repts 50-369/80-08,50-370/80-05, 50-413/80-09,50-414/80-09,50-491/80-02,50-492/80-06 & 50-493/80-06.Final Rept to Be Submitted by 810131 | |
ML19344E978 | 29 August 1980 | Responds to IE Bulletin 80-19,Revision 1.No mercury-wetted Matrix Relays Are Used or Planned for Use in Reactor Protection Sys | |
ML19344F187 | 26 August 1980 | Responds to IE Bulletin 80-16.No Rosemount Models 1151 & 1152 Pressure Transmitters Are Used in safety-related Applications | |
ML19336A642 | 15 August 1980 | Responds to NRC 800718 Ltr Re Violations Noted in IE Insp Repts 50-369/80-08,50-370/80-05,50-413/80-09,50-414/80-09, 50-491/80-07,50-492/80-06 & 50-493/80-06.Corrective Actions: Records Storage Facility Constructed | |
ML19344E506 | 14 August 1980 | Responds to IE Bulletin 80-20, Failure of Westinghouse Type W-2 Spring Return to Neutral Control Switches. Review Showed No Westinghouse Type W-2 Switches Used in safety- Related Applications | |
ML19331D363 | 6 August 1980 | Submits Response to IE Bulletin 79-03A.No SA-312 or A-312, Type 300 Series Fusion Welded Pipe in Use or Planned for Use Is Subj to Design Stresses Greater than 85% of ASME Code Allowable Stresses | |
ML19338C340 | 4 August 1980 | Ack Receipt of IE Insp Repts 50-491/80-09,50-492/80-08 & 50-493/80-08 on 800611-13.No Proprietary Info | |
ML19331B611 | 4 August 1980 | Submits Const Completion & Fuel Load Target Dates,In Response to NRC 800711 Ltr.For Unit 1,const Completion & Fuel Load Target Dates Are Jul 1980 & Jul 1991 for Unit 2.OL Application to Be Submitted by Sept 1986 | |
ML19327A541 | 31 July 1980 | Responds to 800702 Request for Info Re Evacuation Times for Power Plants W/Current or Pending Cps.Cherokee & Perkins Stations Pose No Population Density Situation Which Would Cause Long Evacuation Times | |
ML19331C262 | 28 July 1980 | Ack Receipt of IE Insp Repts 50-491/80-08,50-492/80-07 & 50-493/80-07 on 800624-25.No Proprietary Info | |
ML19326E064 | 7 July 1980 | Forwards Response to IE Bulletin 80-08, Exam of Containment Liner Penetration Welds. Piping Penetrations Are Designed & Fabricated in Accordance w/1977 Edition of ASME Boiler & Pressure Vessel Code,Including Summer 1977 Addenda | Nondestructive Examination Liquid penetrant |
ML19327A008 | 25 June 1980 | Responds to NRC 790627 Ltr Re Violation Noted in IE Insp Repts 50-491/79-10,50-492/79-10 & 50-493/79-10.Corrective Actions:Corrected Procedure for Determining Bulk Density of Test Sand & Increased Testing of Filter Matl | |
ML19323G879 | 8 May 1980 | Ack Receipt of IE Insp Repts 50-491/80-05,50-492/80-05 & 50-493/80-05.No Proprietary Info | |
ML19309G215 | 3 April 1980 | Ack Receipt of IE Insp Repts 50-491/80-04,50-492/80-04 & 50-493/80-04 on 800304-07.No Proprietary Info | |
ML19305D995 | 28 March 1980 | Ack Receipt of IE Insp Repts 50-491/80-02,50-492/80-02 & 50-493/80-02 on 800226-29. No Proprietary Info | |
ML19309E806 | 28 March 1980 | Ack Receipt of IE Insp Repts 50-491/80-03,50-492/80-03 & 50-493/80-03 on 800303-05.No Proprietary Info | |
ML19305E175 | 19 March 1980 | Submits Response to IE Bulletin 80-03.Review Revealed That No Charcoal Adsorber Cells Have Been Received from Manufacturers | |
ML19294B852 | 11 February 1980 | Ack Receipt of IE Insp Repts 50-491/80-01,50-492/80-01 & 50-493/80-01.No Proprietary Info | |
ML19312D130 | 5 February 1980 | Responds to IE Bulletin 79-28.No Namco EA180 Limit Switches from Affected Production Period Are Used or Planned for Use | |
ML19262C223 | 4 February 1980 | Informs of Change in Projected Commercial Operation Dates for Facilities.Units 1 & 2 Will Be Placed in Commercial Operation in Jan 1990 & Jan 1992,respectively.FSAR Will Be Filed in Jan 1987.Schedules Are Periodically Reviewed | |
ML19312D591 | 22 January 1980 | Responds to NRC 791227 Ltr Re Violations Noted in IE Insp Repts 50-491/79-20,50-492/79-20,& 50-493/79-20.Corrective Actions:Samples Taken,Nonconforming Item Report Written & Computer Tickler Sys Implemented | |
ML19305B913 | 15 January 1980 | Responds to NRC 791227 Ltr Re Violations Noted in IE Insp Repts 50-491/79-20,50-492/79-20 & 50-493/79-20.Corrective Actions:Concrete Aggregate Samples Taken,Nonconforming Item Rept Written & Computerized Tickler Sys Implemented | |
ML19257D566 | 7 January 1980 | Forwards Revision to Response to IE Bulletin 79-02,Revision 2,re Pipe Support Base Plate Designs.Will Account for Base Plate Flexibility in Calculations of Bolt Loads by Using Conservative Hand Calculation Method | Finite Element Analysis |
ML19257D380 | 4 January 1980 | Responds to IE Bulletin 79-25, Failures of Westinghouse Bfd Relays in Safety-Related Sys. No Westinghouse Bfd/Nbfd Relays Are Used in safety-related Sys | |
ML19256G134 | 20 December 1979 | Estimates Submittal Date for FSAR for Cherokee 1 as Jan 1984 | |
ML19210E851 | 29 November 1979 | Ack Receipt of IE Insp Repts 50-491/79-19,50-492/79-19 & 50-493/79-19 on 791023-26.No Proprietary Info | |
ML19269F484 | 16 November 1979 | Responds to NRC 791031 Ltr Re Violations Noted in IE Insp Repts 50-491/79-18,50-492/79-18 & 50-493/79-18.Corrective Actions:Const Procedure CKP-8 Revised Re Electrode Stubs. Personnel Involved Have Been Instructed | |
ML19210D772 | 2 November 1979 | Responds to IE Bulletin 79-23 Re Failure of Emergency Transformers.No Connections Made Between Low Kva Rated Transformers & High Kva Emergency Diesel Generators W/O Limitations on Flow of Circulatory Currents | |
ML19256F053 | 30 October 1979 | Responds to IE Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Sys. Sys Erection Has Not Progressed Far Enough to Compare Actual Configuration W/Design | |
ML19260A304 | 25 October 1979 | Ack Receipt of IE Insp Repts 50-491/79-17,50-492/79-17 & 50-493/79-17 on 790925-28.No Proprietary Info | |
ML19256E356 | 16 October 1979 | Ack Receipt of IE Insp Repts 50-491/79-16,50-492/79-16 & 50-493/79-16 on 790913-14.No Proprietary Info |