DUKE POWER COMPANY ELECTRIC CENTER Box 33189. CHARLOTTE. N. C. 28242 oeE'm "'s "nIma
=
August 4,1980 Mr. Darrell G. Eisenhut, Director Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555 Re: Cherokee Nuclear Station Docket Nos: 50-491, 492, & 493 Construction Completion Schedules Duke Files: CK-1412.05, CK-1412.06
Dear Mr. Eisenhut:
In your letter of July 11, 1980, you requested that "all applicants for operating licenses and construction permit holders" provide construction completion and fuel load target dates. These dates are as follows for Cherokee Nuclear Station:
Construction' Completion Date Fuel Load Target Date Unit 1 July, 1989 July, 1989 Unit 2 July, 1991 July, 1991 Based on the safety review period of 33 months listed in your letter, we plant to submit the Cherokee Operating License Application by September,1986.
Ve truly yours, L. C. Dail, Vice-Pre nt Design Engineering EKM/pam bb!