Submits Const Completion & Fuel Load Target Dates,In Response to NRC 800711 Ltr.For Unit 1,const Completion & Fuel Load Target Dates Are Jul 1980 & Jul 1991 for Unit 2.OL Application to Be Submitted by Sept 1986
ML19331B611
Person / Time
Site: Cherokee  Duke Energy icon.png
Issue date: 08/04/1980
From: Dail L
DUKE POWER CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
NUDOCS 8008120496
Download: ML19331B611 (1)


Text

-

DUKE POWER COMPANY ELECTRIC CENTER Box 33189. CHARLOTTE. N. C. 28242 oeE'm "'s

= "nIma August 4,1980 Mr. Darrell G. Eisenhut, Director Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555 Re: Cherokee Nuclear Station Docket Nos: 50-491, 492, & 493 Construction Completion Schedules Duke Files: CK-1412.05, CK-1412.06

Dear Mr. Eisenhut:

In your letter of July 11, 1980, you requested that "all applicants for operating licenses and construction permit holders" provide construction completion and fuel load target dates. These dates are as follows for Cherokee Nuclear Station:

Construction' Completion Date Fuel Load Target Date Unit 1 July, 1989 July, 1989 Unit 2 July, 1991 July, 1991 Based on the safety review period of 33 months listed in your letter, we plant to submit the Cherokee Operating License Application by September,1986.

Ve truly yours, L. C. Dail, Vice-Pre nt Design Engineering EKM/pam bb!