Responds to NRC 791031 Ltr Re Violations Noted in IE Insp Repts 50-491/79-18,50-492/79-18 & 50-493/79-18.Corrective Actions:Const Procedure CKP-8 Revised Re Electrode Stubs. Personnel Involved Have Been Instructed
ML19269F484
Person / Time
Site: Cherokee  Duke Energy icon.png
Issue date: 11/16/1979
From: Dail L
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19269F481 List:
References
NUDOCS 7912210145
Download: ML19269F484 (1)


Text

. 'n DUIm POWEIt COMI'ANY ELECTitlC CENTElt. IIOX !! 1180. Cll Altl.01TE, N. C. 2N242 ullik! $L t

November 16, 1979

~

Mr. J. P. O'Reilly, Dircetor U. S. fluclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 Re: Cherokee liuclear Station RII: PKV Inspection Reports: 50-491, 492, 493/79-18 Duke File: CK-1412.11-1

Dear Mr. O'Reilly:

In the referenced inspection reports, certain items of non-compliance were identified. Duke Power's response to these items is enclosed.

Duke Power does not consider any of the information contained in these reports to be proprietary.

Very truly yours, 1

Y

.C. Dail, Vice-President Design Engineering 2167 OH EKM/ cam Attachment qqolA5

.. ace 7912239 f

Duke's Response to Deficiencies 50-491/79-18-01 (Failure to Document Welding Surveillance) and 50-491/79-18-02 (Failure to Follow Procedure For Control of Welding Filler Material)

During his inspection on October 9-12, 1979, Mr. Van Doorn identified two deficiencies involving welding. Below is Duke's response to each deficiency.

A. Failure to Document Welding Surveillance This situation was corrected at the time of the inspection. All personnel involved were irstructed in the proper documentation of welding surveillance. Full compliance was attained by October 12, 1979.

B. Failure to Follow Procedure for Control of Welding Filler Material Construction Procedure CKP-8 has been revised and the requirement removed that required the electrode stubs be returned to the issue station. This allows the placement of marked containers in the areas where they are needed rather than at the issue station. All personnel involved have been instructed to the requirements of the procedure. Full compliance was attained on October 19, 1979.

2167 094