Issue date | Title | Topic | |
---|---|---|---|
ML20249C849 | 30 September 1999 | 1999 Third Quarter Rept of Completed Changes,Tests & Experiments Evaluated,Per 10CFR50.59(b)(2), for Dresden Nuclear Power Station. with | Temporary Modification High Energy Line Break Feedwater Heater Unidentified leakage |
ML20217A169 | 22 September 1999 | Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers | |
ML20210R608 | 31 July 1999 | Monthly Operating Repts for July 1999 for Dresden Nuclear Power,Units 1,2 & 3.With | |
ML20209E129 | 30 June 1999 | Monthly Operating Repts for June 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With | |
ML20209J348 | 30 June 1999 | 1999 Second Quarter Rept of Completed Changes,Tests & Experiments, Per 10CFR50.59.With | Safe Shutdown Temporary Modification |
ML20210D307 | 30 June 1999 | Corrected Page 8 to MOR for June 1999 for DNPS Unit 3 | |
ML20195G638 | 31 May 1999 | Monthly Operating Repts for May 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With | Enforcement Discretion |
ML20195B259 | 19 May 1999 | Rev 66a to CE-1-A,consisting of Proposed Changes to QAP for Dnps,Qcs,Znps,Lcs,Byron & Braidwood Stations | Offsite Dose Calculation Manual Process Control Program |
ML20206N282 | 30 April 1999 | Monthly Operating Repts for Apr 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With | |
ML20206B190 | 31 March 1999 | First Quarter Rept of Completed Changes,Tests & Experiments Per 10CFR50.59 for Dresden Nuclear Power Station. with | Shutdown Margin Fire Barrier Temporary Modification Feedwater Heater Operability Determination Severe Accident Management Guideline |
ML20205N749 | 31 March 1999 | Monthly Operating Repts for Mar 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With | |
ML20207M692 | 28 February 1999 | Monthly Operating Repts for Feb 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With | Hydrostatic Overspeed |
ML20207E931 | 26 February 1999 | Part 21 Rept Re Sprague Model TE1302 Aluminum Electrolytic Capacitors with Date Code of 9322H.Caused by Aluminum Electrolytic Capacitors.Affected Capacitors Replaced | |
ML20199M089 | 22 January 1999 | Part 21 Rept Re Failure of Square Root Converters.Caused by Failed Aluminum Electrolytic Capacitory Spargue Electric Co (Model Number TE1302 with Mfg Date Code 9322H).Sent Square Root Converters Back to Mfg,Barker Microfarads,Inc | |
ML20199D326 | 31 December 1998 | 10CFR50.59 SER for 1998-04 Quarter, of Changes,Tests & Experiments.With | Safe Shutdown Process Control Program |
ML20199C895 | 31 December 1998 | Monthly Operating Repts for Dec 1998 for Dnps,Units 1,2 & 3 | |
ML20205M706 | 31 December 1998 | Unicom Corp 1998 Summary Annual Rept. with | |
ML20197G859 | 30 November 1998 | Monthly Operating Repts for Nov 1998 for Dresden Nuclear Power Station.With | |
ML20196A419 | 19 November 1998 | Safety Evaluation Accepting QA TR CE-1-A,Rev 66 Re Changes in Independent & Onsite Review Organization by Creating NSRB | |
ML20196J006 | 19 November 1998 | Rev 66 to Topical Rept CE-1-A, QA Program | Offsite Dose Calculation Manual Coatings Process Control Program Commercial Grade Fire Protection Program |
ML20195D286 | 31 October 1998 | Monthly Operating Repts for Oct 1998 for Dresden Nuclear Power Station.With | |
ML20154L368 | 30 September 1998 | Monthly Operating Repts for Sept 1998 for Dresden Nuclear Power Station,Units 1,2 & 3.With | |
ML20154N413 | 30 September 1998 | 1998 Third Quarter 10CFR50.59 Rept, for Dresden Nuclear Power Station of Completed Changes,Tests & Experiments | Safe Shutdown Half scram Emergency Lighting Test box Scram Discharge Volume Fire Protection Program Operability Assessment |
ML20153C506 | 21 September 1998 | SER Accepting Qualified Unit 1 Supervisor Initial & Continuing Training Program for Dresden Nuclear Power Station,Unit 1 | |
ML20151Y271 | 31 August 1998 | Monthly Operating Repts for Aug 1998 for Dresden Nuclear Power Station,Units 1,2 & 3.With | |
ML20237E233 | 21 August 1998 | Revised Pages of Section 20 of Rev 66 to CE-1-A, QA Topical Rept | Offsite Dose Calculation Manual Process Control Program Fire Protection Program |
ML20237A716 | 31 July 1998 | Monthly Operating Repts for July 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 | |
ML20236Q585 | 30 June 1998 | 1998 Second Quarter 10CFR50.59 Rept, for Dresden Nuclear Power Station of Completed Changes,Tests & Experiments | Safe Shutdown Half scram Emergency Lighting Test box Overspeed |
ML20236F813 | 30 June 1998 | Rev 0 to Defueled SAR Dresden Nuclear Power Station Unit 1 Commonwealth Edison Co | Safe Shutdown Offsite Dose Calculation Manual Fire Barrier Zebra Mussel Emergency Lighting Intergranular Stress Corrosion Cracking License Renewal Earthquake Fuel cladding Backfit Siren Overspeed Water rod Water hammer Control Room Habitability |
ML20236T833 | 30 June 1998 | COLR for Dresden Station Unit 3,Cycle 15 | Shutdown Margin Anticipated operational occurrence Feedwater Heater |
ML20236T839 | 30 June 1998 | Rev 1 to EMF-96-141, Dresden Unit 3 Cycle 15 Reload Analysis Rept | Stroke time Anticipated operational occurrence Feedwater Heater Feedwater Controller Failure Fuel cladding Water rod |
ML20236M604 | 30 June 1998 | Monthly Operating Repts for June 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 | |
ML20248M302 | 31 May 1998 | Monthly Operating Repts for May 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 | |
ML20248F353 | 21 May 1998 | Part 21 Rept Re Electronic Equipment Repaired or Reworked by Integrated Resources,Inc from Approx 930101-980501.Caused by 1 Capacitor in Each Unit Being Installed W/Reverse Polarity. Policy of Second Checking All Capacitors Is Being Adopted | Reverse polarity |
ML20247F339 | 30 April 1998 | Monthly Operating Repts for Apr 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 | |
ML20217D028 | 22 April 1998 | Part 21 Rept Re Additive Constants Used in MCPR Determination for Siemens ATRIUM-9B Fuel by Core Monitoring Sys Were Found to Be non-conservative.SPC Personnel Notified All Customers w/ATRIUM-9B Lead Test Assemblies | Fitness for Duty Operability Assessment |
ML20216D441 | 31 March 1998 | First Quarter Rept of Completed Changes,Tests & Experiments for 10CFR5059 | Half scram Feedwater Heater Accidental discharge |
ML20216C965 | 31 March 1998 | Monthly Operating Repts for Mar 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 | Scram Discharge Volume |
ML20216E253 | 28 February 1998 | Monthly Operating Repts for Feb 1998 for Dresden Nuclear Power Station | |
ML20202F783 | 31 January 1998 | Monthly Operating Repts for Jan 1998 for Dresden Nuclear Power Station | |
ML20199K165 | 23 January 1998 | Rev 65h to Topical Rept CE-1-A, Comm Ed QA Tr | Safe Shutdown Shutdown Margin Non-Destructive Examination Offsite Dose Calculation Manual Hydrostatic Coatings Nondestructive Examination Temporary Modification Process Control Program Commercial Grade Fire Protection Program |
ML20198P532 | 31 December 1997 | Monthly Operating Repts for Dec 1997 for Dresden Nuclear Power Station | Half scram |
ML20198P702 | 31 December 1997 | Fourth Quarter Rept of Completed Changes,Tests & Experiments Per 10CFR50.59 | Safe Shutdown |
ML20216D361 | 31 December 1997 | Unicom Corp 1997 Summary Annual Rept | |
ML20203F878 | 30 November 1997 | Monthly Operating Repts for Nov 1997 for Dresden Nuclear Power Station | |
ML20199B070 | 31 October 1997 | Monthly Operating Repts for Oct 1997 for Dresden Nuclear Power Station | |
ML20217H720 | 30 September 1997 | Monthly Operating Repts for Sept 1997 for Dresden Nuclear Power Station,Units 1,2 & 3 | |
ML20210V240 | 19 September 1997 | Rev 65g to Topical Rept CE-1-A, Comm Ed QA Manual | Non-Destructive Examination Nondestructive Examination Temporary Modification Commercial Grade |
ML20216J378 | 31 August 1997 | Monthly Operating Repts for Aug 1997 for DNPS | |
ML20210H551 | 31 July 1997 | Monthly Operating Repts for July 1997 for DNPS IAW RG 1.16 & GL 97-02 |