Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML20217K94415 October 1999SER Accepting Util Alternative Proposed Relief Request RR-ENG-2-4 for Second 10-year ISI Interval at Stp,Units 1 & 2 Pursuant to 10CFR50.55a(a)(3)(i)Nondestructive Examination
ML20217K91515 October 1999SER Authorizing Util Relief Request RR-ENG-2-3 for Second 10-year ISI Interval of Stp,Units 1 & 2 Pursuant to 10CFR50.55a(a)(3)(i)Nondestructive Examination
Incorporated by reference
ML20217F15012 October 1999Special Rept:On 990929,south Plant Vent (SPV) Range Ng Monitor Was Inoperable.Monitor Was Inoperable for More than 72 H.Caused by Electronic Noise Generated from Noise Suppression Circuit.Replaced CircuitGrab sample
ML20217E8027 October 1999CPSES Unit 1 Cycle 8 ColrShutdown Margin
ML20217G41530 September 1999Monthly Operating Repts for Sept 1999 for Cpses,Units 1 & 2Coast down
L-99-154, Monthly Operating Repts for Sept 199 for Bvps,Units 1 & 2. with30 September 1999Monthly Operating Repts for Sept 199 for Bvps,Units 1 & 2. with
ML20217N65330 September 1999Monthly Operating Rept for Sept 1999 for Hope Creek Generating Station,Unit 1.WithSafe Shutdown
Temporary Modification
ML20217A99330 September 1999NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data
RBG-45144, Monthly Operating Rept for Sept 1999 for River Bend Station. with30 September 1999Monthly Operating Rept for Sept 1999 for River Bend Station. with
NOC-AE-000676, Monthly Operating Repts for Sept 1999 for South Texas Project,Units 1 & 2.With30 September 1999Monthly Operating Repts for Sept 1999 for South Texas Project,Units 1 & 2.With
ML20217D05330 September 1999Rev 1 to STP Electric Generating Station Unit 2 Cycle 7 Colr
ML20217D04830 September 1999Rev 1 to STP Electric Generating Station Unit 1 Cycle 9 Colr
ML20212F76724 September 1999SER Granting Relief Request C-4 Pursuant to 10CFR50.55a(g)(6)(i) for Unit 2,during First 10-year ISI Interval & Relief Requests B-15,B-16 & B-17 Pursuant to 10CFR50.55a(g)(6)(i)Incorporated by reference
ML20217M02120 September 1999Part 21 Rept Re Possible Deviation of NLI Dc Power Supply Over Voltage Protection Circuit Actuation.Caused by Electrical Circuit Conditions Unique to Remote Engine Panel. Travelled to Hope Creek to Witness Startup Sequence of DG
ML20216J57016 September 1999Rev 2 to CPSES Unit 2 Cycle 5 ColrShutdown Margin
ML20216G1209 September 1999Rev 3 to Rbs,Cycle 9 ColrShutdown Margin
Anticipated operational occurrence
ML20211Q6739 September 1999Safety Evaluation Accepting First 10-yr Interval ISI Program Plan Request for Relief from ASME Code Case N-498Boric Acid
Hydrostatic
VT-2
Incorporated by reference
ML20211P8419 September 1999Safety Evaluation Supporting Alternative Proposed by Licensee to Surface Exam to Perform Boroscopic VT-1 Visual Exam of Pump Casing Welds within Pump Pits for Welds Covered by Relief Request RR-ENG-24Incorporated by reference
ML20211P7819 September 1999SER Approving Second 10-year Interval Inservice Insp Program Plan Relief Request RR-ENG-2-8 (to Use Code Case N-491-2) for South Texas Project,Units 1 & 2Incorporated by reference
ML20211N5538 September 1999Safety Evaluation Supporting Amend 121 to License NPF-57Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
Annual Radiological Environmental Operating Report
Process Control Program
L-99-139, LER 99-S01-00:on 990813,uncompensated Loss of Ability to Detect within Single Intrusion Security Detection Zone Occurred.Caused by Procedure non-compliance.Involved Personnel Received Counseling Re Event.With2 September 1999LER 99-S01-00:on 990813,uncompensated Loss of Ability to Detect within Single Intrusion Security Detection Zone Occurred.Caused by Procedure non-compliance.Involved Personnel Received Counseling Re Event.With
L-99-140, Monthly Operating Repts for Aug 1999 for Bvps,Units 1 & 2. with31 August 1999Monthly Operating Repts for Aug 1999 for Bvps,Units 1 & 2. with
ML20212E51931 August 1999Rev 3 to SG-99-04-005, STP 1RE08 Outage Condition Monitoring Rept & Final Operational Assessment
NOC-AE-000643, Monthly Operating Repts for Aug 1999 for South Texas Project,Units 1 & 2.With31 August 1999Monthly Operating Repts for Aug 1999 for South Texas Project,Units 1 & 2.With
RBG-45110, Monthly Operating Rept for Aug 1999 for River Bend Station, Unit 1.With31 August 1999Monthly Operating Rept for Aug 1999 for River Bend Station, Unit 1.With
TXX-9920, Monthly Operating Repts for Aug 1999 for Cpses.With31 August 1999Monthly Operating Repts for Aug 1999 for Cpses.With
ML20211F45324 August 1999Safety Evaluation Supporting Licensee Proposed Alternative to Defer Partial First Period Exams of flange-to-shell Weld to Third Period & Perform Required Ultrasonic Exams,Both Manual & Automated,During Third PeriodNon-Destructive Examination
Incorporated by reference
ML20211F51123 August 1999Safety Evaluation Supporting Licensee Proposed Alternative Contained in Request for Relief RR-ENG-30Nondestructive Examination
VT-2
Incorporated by reference
ML20211B37813 August 1999Special Rept 99-002:on 990730,NPV Radiation Monitoring Sys Was Declared Inoperable.Caused by Voltage Induced in Detector Output by Power Cable to Low Range Sample Pump. Separated Cables & Secured in Place to Prevent Recurrence
ML20211M2986 August 1999Rev 1 to CPSES Fuel Storage Licensing Rept, CPSES Credit for Soluble Boron & Expansion of Spent Fuel Storage Capacity, Consisting of Revised Title Page and 4-1
RBG-45087, Special Rept:On 990510,LPCI a & LPCS Injected Into Rv for Less than Two Minutes.Caused by Electrical Transient in One of ECCS Power Supplies.Operators Verified Reactor Cavity Level & Closed Injection Valves to Stop Injection6 August 1999Special Rept:On 990510,LPCI a & LPCS Injected Into Rv for Less than Two Minutes.Caused by Electrical Transient in One of ECCS Power Supplies.Operators Verified Reactor Cavity Level & Closed Injection Valves to Stop Injection
ML20210K4723 August 1999SER Accepting Licensee 180-day Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate ValvesPower-Operated Valves
Backfit
RBG-45091, Monthly Operating Rept for July 1999 for River Bend Station, Unit 1.With31 July 1999Monthly Operating Rept for July 1999 for River Bend Station, Unit 1.With
L-99-126, Monthly Operating Repts for Jul 1999 for Beaver Valley Power Station,Units 1 & 2.With31 July 1999Monthly Operating Repts for Jul 1999 for Beaver Valley Power Station,Units 1 & 2.WithZebra Mussel
ML20210U47231 July 1999Monthly Operating Rept for July 1999 for Hope Creek Generating Station,Unit 1.WithSafe Shutdown
Temporary Modification
ML20210R36331 July 1999Monthly Operating Repts for July 1999 for South Tx Project, Units 1 & 2.With
ML20210C94131 July 1999Rev 1 to SG-99-07-002, South Tx,Unit 1 Cycle 9 Voltage- Based Repair Criteria 90-Day Rept, Jul 1999
ML20210U40831 July 1999Monthly Operating Repts for July 1999 for Cpses,Units 1 & 2Downpower
ML20216D83326 July 1999Safety Evaluation Concluding That Licensee IPEEE Complete Re Info Requested by Suppl 4 to GL 88-20 & That IPEEE Results Reasonable Given HCGS Design,Operation & HistorySafe Shutdown
High winds
Tornado Missile
Safe Shutdown Earthquake
Earthquake
ML20216D87226 July 1999Review of Submittal in Response to USNRC GL 88-20,Suppl 4: 'Ipeees,' Fire Submittal Screening Review Technical Evaluation Rept:Hope Creek Rev 1:980518Hot Short
Safe Shutdown
Ultimate heat sink
Fire Barrier
Safe Shutdown Earthquake
Probabilistic Risk Assessment
Fire Protection Program
Fire Watch
ML20210D83223 July 1999Safety Evaluation Accepting Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment InspCoatings
Moisture barrier
ML20210D91623 July 1999Safety Evaluation Accepting Inservice Testing Relief Request RR-56 Re Component Cooling Water & Safety Injection Sys Containment Isolation Check Valve Closure Test FrequencyEnforcement Discretion
Probabilistic Risk Assessment
Incorporated by reference
Foreign Material Exclusion
Large early release frequency
ML20210F33322 July 1999Safety Evaluation Granting Relief Requests RR-B1,RR-C1,RR-D1 & RR-B3.Finds That Proposed Alternative for RR-B3 Provides Acceptable Level of Quality & Safety & Authorizes Alternative Pursuant to 10CFR50.55a(a)(3)(i)Fire Barrier
Incorporated by reference
Pressure Boundary Leakage
ML20210D44921 July 1999Revised Chapters to Operations QA Plan, Including Rev 9 to Chapter 1.0, Organization & Rev 6 to Chapter 16.0, Independent Technical Review
ML20210D48221 July 19991RE08 ISI Summary Rept for Steam Generator Tubing of South Texas Project Electric Generating Station Unit 1
NOC-AE-000583, LER 99-S03-00:on 990619,failure to Revitalize Sdg Number 11 Was Noted.Caused by Failure to Communicate Status of Sdg. Subject Sdg Revitalized on 990619 & Licensee Will Develop Security Force Instruction Re Sdgs.With15 July 1999LER 99-S03-00:on 990619,failure to Revitalize Sdg Number 11 Was Noted.Caused by Failure to Communicate Status of Sdg. Subject Sdg Revitalized on 990619 & Licensee Will Develop Security Force Instruction Re Sdgs.With
ML20209H76615 July 1999Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Comanche Peak Steam Electric Station,Units 1 & 2Safe Shutdown
Power-Operated Valves
ML20209H2729 July 19992RF04 Containment ISI Summary Rept First Interval,First Period,First Outage
ML20209H2639 July 19992RF04 ISI Summary Rept First Interval,Second Period,Second OutageHydrostatic
Liquid penetrant
ML20209G7508 July 1999SER Finding That Licensee Individual Plant Exam of External Events Complete with Regard to Info Requested by Suppl 4 to GL 88-20 & That IPEEE Results Reasonable Given Design, Operation & History of Comanche Peak Steam Electric StationSafe Shutdown
High winds
Fire Barrier
Safe Shutdown Earthquake
Internal Flooding
Probabilistic Risk Assessment
Earthquake