 Issue dateTitleTopic
ML23241A00225 August 2023Paragon Final Part 21 Report on Defect with Eaton/Cutler Hammer Size 4 and 5 Freedom Series Contactors Modified by Paragon with Special Coils And/Or with RTV to Improve the Securing of Shading Coils
ML23221A3703 August 2023Paragon Energy Solutions, 10CFR Part 21 Initial Notification: P21-08032023-IN, Rev. 0
ML19347A42610 December 2019General Atomics - Reportable Occurrence Under 10CFR21: Reported Failure in Analog High Range Radiation Monitor (RP-2C)Post Accident Monitoring
ML19317D09325 October 2019Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0127, Rev. 0, Emd Fuel Injectors - Seized Plunger and Bushing
ML19087A25221 March 2019Engine Systems, Inc. - 10 CFR 21 Reportable Notification on Excitation Transformers for Vickers Voltage Regulator SystemDedication package
ML19091A05021 March 2019Engine Systems, Inc. 10 CFR 21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0124, Rev. 0, Excitation Transformers for Vickers Voltage Regulator SystemDedication package
ML19042A08025 January 2019Part 21 Report No. 10CFR21-0124-INT; Rev. 0 - Saturable Reactor (Magnetic Amplifier) for Vickers Voltage Regulator System, P/N 8408218-ESI
ML19002A20421 December 2018to Engine Systems, Inc., Part 21 Report Re Emd Fuel and Soakback Pumps - Potentially Undertorqued Cover Bolts
ML18353A42830 November 2018Engine Systems, Inc., 10CFR21-0123, Rev. 0, for a 10CFR21 Reportable Condition on Emd Fuel and Soakback Pumps
ML17114A07013 April 2017Part 21 Notification - Identified Fisher 546S Electro-Pneumatic Transducers Standard Mounting Brackets Failed Seismic Testing Standards
ML17104A28813 April 2017Emerson Process Management, LLC - Fisher Information Notice, (FIN) 2017-02
ML16278A47122 September 2016Notification of 10 CFR Part 21 Condition, Masterpact Breaker Fail to Close
ML16281A27022 September 2016Part 21 - Initial Notification of Masterpact Breaker Fail to Close
ML16209A05013 July 2016Part 21 - Furmanite Nuclear Grade Leak Seal Material FSC-N-1B
ML16196A06410 July 2016Part 21 Report - Materials Not Properly Dedicated
ML16188A37621 June 2016Part 21 Interim Evaluation of Deviation - Contractor FailureCommercial Grade
ML16154A20520 May 2016Part 21 Interim Evaluation of a Deviation - Contactor Failure
ML16139A83213 May 2016Part 21 - Initial Notification of Masterpact Breaker Fail to Close
ML16139A83313 May 2016Part 21 - Initial Notification of Masterpact Breaker Fail to Close
ML16061A01127 February 2016Nuclear Logistics, Inc. - Part 21 Contactor Making Noise, Per Turkey PointCondition Adverse to Quality
Commercial Grade
ML16061A01019 February 2016Nuclear Logistics, Inc. - Part 21 - Contractor Making NoiseCondition Adverse to Quality
ML15345A3908 December 2015Part 21 Report - 2 Motors Were Not Properly Prepared Before Small Steel Shot Blasting
ML15089A43720 March 2015Part 21 - Dual Alarm Modules That May Contain Faulty Diodes in Single State RelaysExclusive Use
ML14217A34731 July 2014Part 21 Interim Report - Temperature Switch Set Points Out of Calibration
ML14101A34210 April 2014Notification of Part 21 - Potential Defect in General Electric SB1 Switches and Hea Relays
ML14069A46726 February 2014Part 21 Report Involving a Potential Manufacturing Defect in Replacement Masterpact Cradles
ML14071A47726 February 2014Report of Potential Defect Per 1OCFR Part 21 Primary Disconnect Assembly
ML14042A2025 February 2014Part 21 Report Regarding Unqualified Material Used in Electrical Penetration AssembliesStress corrosion cracking
ML13277A01023 September 2013Interim Report Update for Component ASME Material Supplied by Mirion Technologies (Conax Nuclear), Inc. (Mtcn), as Part of Containment Electric Penetration Assemblies (EPA)Stress corrosion cracking
ML13246A08423 August 2013Notification of Potential Defect & Interim Report Regarding a Potential Defect of Materials Supplied to Operating Us Nuclear Power Plants by Mirion Technologies (Conax Nuclear) Inc. (Mtcn) with Containment Electric Penetration Assemblies
ML13165A34212 June 201360-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers
ML13095A01125 March 2013Update to Event Number 48798: 10 CFR Part 21 Notification, Dual Alarm Modules and Single Alarm Modules
ML13063A4431 March 201310 CFR Part 21 Report Notification, Dual Alarm Modules and Single Alarm Modules
ML12348A13613 December 2012Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers
ML12352A12313 December 201260-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers
ML12318A0408 November 2012Part 21 - Report of Potential Grounding Pathway Between Heat Sink and Chassis of Control Modules
ML12094A3712 April 2012Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations
ML12058A14123 February 2012Part 21 Report - Rosemount Nuclear Instruments, Inc., Pressure Transmitter with Nonzero Based Calibrations
ML09259024211 September 2009Notification of Potential Part 21 Problem with Seismic Soil Structure Analysis SoftwareUltimate heat sink
ML09076118811 March 2009Part 21 Notification - Defective Hk and K-Line Circuit Breaker Tension Springs
ML0904007485 February 2009Update to Part 21 Report Notification, Texas Instruments Operational Amplifier, P/N: OPA 2111
ML08333018721 November 2008Notification of Potential Part 21 Re Tyco Electronics, Transfer of Information - CII-012
ML08319001712 November 2008Notification of Potential Part 21 on All Dimensionally Verified Commercial Grade Items Processed Per Fisher Manufacture Procedure Fmp 2K28Commercial Grade
ML08239010625 August 2008Notification of Potential Part 21 on Failure of F and G SwitchesTest box
ML08183052327 June 2008Part 21 Notification - Performance Affected on 3 CL150 Fisher V150 Valve Assemblies
ML0809906344 April 2008Part 21 Notification Regarding Failure to Comply with the Requirements for Dedication of Commercial Grade ItemsCommercial Grade
ML0734402117 December 2007Deficiency Report Part 21 Potential Insufficient Thread Engagement for Certain Pressure Transmitters
ML0713703097 March 2007Velan, Inc., Piston Check Cv Information
ML06277022427 September 2006Part 21 Report from Tyco Valves & Controls LP, Improper Valve Springs in Pressure Relief Valves
ML06083011421 March 200610 CFR Part 21 Notification Ref: FP&L Tpn Supplied Ingersall Rand Auxiliary Feed Pump No. 0601 001 FP&L Po No. 67845