Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML23066A221 | 7 March 2023 | Velan, Inc. - Revised Part 21 Notification Re Butterfly Valves Found to Have a Number of Fasteners Loose | |
ML22301A174 | 28 October 2022 | Global Nuclear Fuel Americas, LLC (GNF) - Part 21 60-Day Interim Report Notification: GNF3 Raised Water Rod (SC-22-04 Rt) | Affidavit GNF3 Water rod |
ML22305A515 | 22 February 2022 | EN 56192 - Grand Gulf Nuclear Station Re Elevation Outer Containment Personnel Airlock Door Failed Its Technical Specification Leakage Test | Unanalyzed Condition Fitness for Duty |
ML21225A081 | 4 August 2021 | Lake Engineering Co., Final Report Per 10 CFR Part 21 Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 | |
M210077, GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors | 17 June 2021 | GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors | Operability Determination Fuel cladding |
ML21168A217 | 17 June 2021 | GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors | Operability Determination Fuel cladding |
ML21014A234 | 7 December 2020 | Fourth Interim Notification Per 10 CFR Part 21 Re Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 | |
ML20366A047 | 18 November 2020 | Curtiss-Wright 10 CFR Part 21 Notification for SF-1154 Hydraulic Fluid Batch 17BLVS293 | |
M200087, GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients | 24 June 2020 | GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients | Operability Determination Fuel cladding |
ML20176A432 | 24 June 2020 | GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients | Operability Determination Fuel cladding |
ML19253A053 | 29 August 2019 | Azz Nuclear - Report of Potential 1O CFR Part 21, Eaton Size 1 and 2 A200 Series Starters/Contactors | |
ML19120A106 | 17 April 2019 | Interim Report of Potential 10 CFR Part 21, Eaton Size 1 and 2 A200 Series Starters/Contactors | |
ML19101A097 | 4 April 2019 | Weir Valves & Controls USA, Inc. Part 21 Written Notification - Event Number: 53973 - 24 Class 150 Globe Alve for RHRSW HX Isolation MOV, E1150F068B at Detroit Edison - Fermi, Unit 2, Experienced Two Stem Failures | |
ML19080A059 | 8 March 2019 | Interim Report of Potential 10CFR Part 21, Eaton A200 Series Starters/Contactors | |
ML19002A204 | 21 December 2018 | to Engine Systems, Inc., Part 21 Report Re Emd Fuel and Soakback Pumps - Potentially Undertorqued Cover Bolts | |
ML18354A742 | 4 December 2018 | Engine Systems, Inc., Submittal of 1OCFR21 Reporting of Defects and Non-Compliance - Report No. 1OCFR21-0123, Rev. 0 - Emo Fuel and Soakback Pumps - Potentially Undertorqued Cover Bolts | |
ML18353A428 | 30 November 2018 | Engine Systems, Inc., 10CFR21-0123, Rev. 0, for a 10CFR21 Reportable Condition on Emd Fuel and Soakback Pumps | |
ML17313A471 | 3 November 2017 | Part 21 - Potentially Degraded Snubber SF1154 Hydraulic Fluid Batch 14ELVS145 Interim Report | |
ML17212A628 | 24 July 2017 | Lake Engineering Co. - Potentially Degraded Snubber SF1154 Hydraulic Fluid Second - Interim Notification Per 10 CFR Part 21 | |
ML17194A825 | 11 July 2017 | Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections | Anchor Darling |
ML17090A398 | 27 March 2017 | Engine Systems, Inc. - Part 21 Report Regarding Identification of Failed Diode Surge Suppressor with Internal Manufacturing Defect | |
ML17081A453 | 20 March 2017 | Part 21 - Plastic Jar Dedication Sampling | |
ML17026A414 | 20 January 2017 | C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling | |
ML16313A062 | 18 October 2016 | C&D Technologies, Inc. - 10 CFR Part 21 Evaluation Regarding Terminal Welding Failure in 3DCU-9 Batteries | Commercial Grade |
ML16294A264 | 18 October 2016 | Part 21 Report - Defective Current to Pressure Transducers | |
ML16252A274 | 29 August 2016 | Azz/Nli - Part 21 Report - Potential Allen Bradley Timing Relay | Commercial Grade |
ML16188A374 | 30 June 2016 | Part 21 - Inadequate Swaging and Adherence of Silicone O-Ring and Silicone PAD Soft Seat Main Disc and Pilot Disc Assemblies | |
ML16194A199 | 25 May 2016 | Azz/Nli - Update - Report of Potential 10CFR Part 21, Allen Bradley Timing Relay Model 700RTC | Commercial Grade |
ML15134A016 | 1 May 2015 | Part 21 Report Regarding Potentially Unqualified Component in Certain Allen Bradley Timing Relays | Commercial Grade |
ML15159A568 | 30 April 2015 | Report of Potential 10CFR Part 21, Allen Bradley Timing Relay Model 700RTC | Commercial Grade |
ML15022A650 | 20 January 2015 | Letter from Steven R. Eisenberg USNRC 10CFR Part 21 Notification | |
ML14274A052 | 22 September 2014 | Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities | |
ML14265A049 | 12 September 2014 | Amendment to Part 21 Report from Abb, Inc Re Deviation of K-Line Circuit Secondary Close Latch (Event #50371) | |
ML14237A121 | 15 August 2014 | Notification of Potential Part 21 Re Notice of Deviation Regarding K-Line Circuit Breaker Secondary Close Latch | |
ML14210A010 | 23 July 2014 | Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve | Safe Shutdown Shutdown Margin Scram Discharge Volume Failure to Scram Affidavit |
ML14204A707 | 23 July 2014 | Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV | Affidavit |
ML14204A708 | 23 July 2014 | Enclosure 2, Description of Closure Evaluation, Non-Proprietary Information - Class I (Public) | Safe Shutdown Shutdown Margin Scram Discharge Volume Failure to Scram |
ML14134A079 | 8 May 2014 | Part 21 - Potential Defect in NUS-710DU Trip Unit to Produce a Valid Trip Output Signal | |
ML14139A259 | 8 May 2014 | 10 CFR Part 21 Report Notification, NUS710DU Trip Units | |
ML13340A382 | 5 December 2013 | Part 21 Reportable Condition Notification: Failure of Relay Logic Card Modules in 2 Out of 4 Voters | Affidavit |
ML13284A084 | 3 October 2013 | Deficiency Report from Baldor Electric Co., on Nuclear Nonconformance Event No. 49302 | |
ML13165A342 | 12 June 2013 | 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers | |
ML13064A012 | 25 February 2013 | Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve | Anchor Darling |
ML13042A096 | 8 February 2013 | Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Error in Main Steam Line High Flow Calculational Methodology | Power Uprate |
ML13044A075 | 8 February 2013 | Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology | Power Uprate |
ML12352A123 | 13 December 2012 | 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers | |
ML12348A136 | 13 December 2012 | Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers | |
ML12347A308 | 12 December 2012 | Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology | |
ML12319A012 | 27 September 2012 | Error in Main Steam Line High Flow Calculational Methodology | |
ML12177A056 | 21 June 2012 | Part 21 - Reliability Degradation of Resistors in Trip Units and Readout Assemblies |