RS-14-206, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

From kanterella
Jump to navigation Jump to search

Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
ML14248A229
Person / Time
Site: Byron  Constellation icon.png
Issue date: 08/28/2014
From: Kaegi G
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, RS-14-206
Download: ML14248A229 (51)


Text

Amp-Agnia*P' Exelon Generation Order No. EA-12-049 RS-14-206 August 28, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455

Subject:

Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

References:

1. NRC Order Number EA-12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012
2. NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," Revision 0, dated August 29, 2012
3. NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide,"

Revision 0, dated August 2012

4. Exelon Generation Company, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated October 25, 2012
5. Exelon Generation Company, LLC Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013 (RS-13-018)
6. Exelon Generation Company, LLC First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049), dated August 28, 2013 (RS-13-115)
7. Exelon Generation Company, LLC Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049), dated February 28, 2014 (RS-14-008)

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-049 August 28, 2014 Page 2

8. NRC letter to Exelon Generation Company, LLC, Byron Station, Units 1 and 2 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC Nos. MF0893 and MF0894), dated December 17, 2013 On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGC). Reference 1 was immediately effective and directs EGC to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the EGC initial status report regarding mitigation strategies. Reference 5 provided the Byron Station, Units 1 and 2 overall integrated plan.

Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. References 6 and 7 provided the first and second six-month status reports, respectively, pursuant to Section IV, Condition 0.2, of Reference 1 for Byron Station. The purpose of this letter is to provide the third six-month status report pursuant to Section IV, Condition 0.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any. The enclosed report also addresses the NRC Interim Staff Evaluation Open and Confirmatory Items contained in Reference 8.

This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2014.

Respectfully submitted, Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1. Byron Station, Units 1 and 2 Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-049 August 28, 2014 Page 3 cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Byron Station, Units 1 and 2 NRC Project Manager, NRR - Byron Station, Units 1 and 2 Ms. Jessica A. Kratchman, NRR/JLD/PMB, NRC Mr. Jack R. Davis, NRR/DPR/MSD, NRC Mr. Eric E. Bowman, NRR/DPR/MSD, NRC Mr. Jeremy S. Bowen, NRR/DPR/MSD/MSPB, NRC Mr. Robert L. Dennig, NRR/DSS/SCVB, NRC Mr. John D. Hughey, NRR/DPR/MSD/MSPB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety

Enclosure Byron Station, Units 1 and 2 Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (47 pages)

Byron Station, Units 1 and 2 Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events 1 Introduction Byron Station developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the diverse and flexible strategies (FLEX), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the last status report, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2 Milestone Accomplishments The following milestone(s) have been completed since February 28, 2014 and are current as of July 31, 2014.

  • None 3 Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

Site: Byron Original Target Activity Status Revised Target Completion Date Completion Date Submit 60 Day Status Report Complete Submit Overall Integrated Complete Implementation Plan Contract with Strategic Alliance Complete for FLEX Emergency Response National SAFER Response Center Submit Six (6) month Updates Aug 2013 Update 1 Complete Feb 2014 Update 2 Complete Aug 2014 Update 3 Complete with Page 1 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 this submittal Feb 2015 Update 4 Not Started Aug 2015 Update 5 Not Started Unit 1 Unit 2 Modification Development Unit 1 Unit 2 Aug Dec 2013

  • Phase 1 modifications Started April Aug 2014 2015 2014 Aug Dec 2013
  • Phase 2 modifications Started April Aug 2014 2015 2014 Aug Dec 2013
  • Phase 3 modifications Complete 2014 modifications are not required Unit 1 Unit 2 Modification Implementation Sept Oct 2014
  • Phase 1 modifications Started 2015 Sept Oct 2014
  • Phase 2 modifications Started 2015 Sept Oct 2014
  • Phase 3 modifications Complete 2015 modifications are not required Procedure Development Unit 1 Unit 2 Oct 2014
  • Strategy procedures Started Sept 2015
    • Validate Procedures (NEI Started Sept Sept Apr 2014 12-06, Sect. 11.4.3) 2015 2014 Oct 2014
  • Maintenance procedures Started Jun 2014 Staffing analysis Complete Oct 2014 Storage Plan and construction Started Oct 2014 FLEX equipment acquisition Started Oct 2014 Training completion Started Aug 2014 National SAFER Response Started Center Operational Sept 2015 Unit 1 Implementation date Started Oct 2014 Unit 2 Implementation date Started Page 2 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 4 Changes to Compliance Method Change 1 Section: General Integrated Plan Elements PWR Key site assumptions to implement NEI 12-06 strategies.

Reason for Change: Site FLEX storage locations have been identified.

Change: The site storage building will consist of one robust building housing "N" FLEX equipment and a commercial building housing "+1" FLEX equipment. Both buildings will be located outside the protected area north of the main parking lot. In addition, the site strategy will have several strategic temporary hoses and electrical cables staged within robust structures in the plant.

Change 2 Section: General Integrated Plan Elements PWR - Provide a sequence of events and identify any time constraint required for success including the technical basis for the time constraint.

Reason for Change: Site calculations are being refined as parts of the FLEX strategy development.

Change:

1. Change RCS cool down setpoint to 260 psig based on calculation BYR99-010/BRW 0017-1, Documentation of the Basis of the Emergency Operating Procedures (EOP)

Setpoints. (Ref.7)

2. Adjusted the timeline limit for DC load shed completion to 65 minutes based on calculation BYR14-060/BRW-14-0080-E, Unit 1(2) 125 VDC Battery FLEX Coping Calculation Common Calc Beyond Design Basis (Ref. 8).
3. Adjusted the timeline limit for restoration of division 2 125 volt DC charger AC power to be completed within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> to ensure the 8-hour requirement is met based on calculation BYR14-060/BRW-14-0080-E, Unit 1(2) 125 VDC Battery FLEX Coping Calculation Common Calc Beyond Design Basis (Ref. 8).
4. Adjusted the timeline and timeline limit for deploying hoses in the fuel handling building to 6 - 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> and 10.94 hours0.00109 days <br />0.0261 hours <br />1.554233e-4 weeks <br />3.5767e-5 months <br /> respectively, based on BYR13-240/BRW-13-0222-M, Spent Fuel Pool Boil Off Analysis during an ELAP Event (Ref. 9).
5. Added an additional action to setup high pressure FLEX pump and hoses at 12 to 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> to ensure they are available to supply borated make-up to the RCS and inject prior to entering Ref lux Cooling. Injection must take please within 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> of the event based on calculation BYR13-239/BRW-13-0221-M, RCS Boration Analysis during an ELAP Event (Ref. 10) and Dave Flahive letter, (Ref. 24).
6. Added an additional activity in the time line to repower a UHS 480v Substation to establish make up before 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> to the UHS, based on the calculation BYR14-119 UHS Volume Analysis during an ELAP Event (Ref. 23).
7. Adjusted the timeline for the activity of staging and connecting the med head flex pump to allow for hose deployment time Page 3 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014

8. Updated the timeline for the name change of the National SAFER Response Center.
9. Added an additional activity in the time line to Set up and Establish ventilation in the AEER and the MCR within 5.15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />, based on calculation BYR13-236/BRW-13-218-M Control Room and Auxiliary Electric Equipment Room heat up and Ventilation during an ELAP, dated June 2014 DRAFT, (Ref.15).
10. Added additional information to Timeline for the Phase 2 High Head Pump to establish makeup prior to entering ref lux cooling, based on WCAP 17601-P and Westinghouse Letter LTR-FSE-14-61 Rev.0-A dated July 17, 2014 (Ref .24)

Change 3 Section: General Integrated Plan Elements PWR Identify how strategies will be deployed in all modes Reason for Change: Site FLEX storage locations and deployment routes have been identified.

Change: The deployment paths from the FLEX storage building to the FLEX equipment staging area have been identified. At least two deployment routes are available to most staging areas providing travel options in the event one path becomes unavailable as a result of the BDBEE.

In areas where only one deployment path is available, consideration has been given for debris removal as part of the FLEX deployment strategy.

Change 4 Section: Maintain Core Cooling & Heat Removal PWR Installed Equipment Phase 1 and Maintain RCS Inventory Control - PWR Installed Equipment Phase 1.

Reason for Change: Calculation BYR99-010/BRW-99-0017-1, Documentation of the Basis of the Emergency Operating Procedures (EOP) Setpoints (Ref. 7), has determined the SG pressure at which the RCS cool down will stop to prevent safety injection accumulator nitrogen addition into the RCS.

Change: Change second paragraph to the following:

Within 90 minutes, operators will commence cooling down the plant at approximately 75°F/hr to a steam generator (SG) pressure of 260 psig. RCS temperature will stabilize between 420°F and 410°F at this SG pressure. SG pressure of 260 psig corresponds to RCS pressure necessary to inject a majority of the borated water in the SI accumulators. This will ensure RCS pressure is above the minimum pressure to preclude injection of accumulator nitrogen into the RCS.

Change 5 Section: Maintain Core Cooling & Heat Removal PWR Installed Equipment Phase 1 Identify Modifications.

Reason for Change: Gap 3 pipe routing has changed as part of the standardized modification design process.

Page 4 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Change: Gap 3 will be resolved by modifying the DDAF pump SX cooling water flow path. The modification consists of installing a piping tee on the discharge of both unit 1 and 2 "B" SX pump discharge lines on the 330' elevation in the auxiliary building (AB). These tees will be connected by a header and routed vertically through the AB to the 364' elevation. On the 364' elevation this line will tee into two separate lines and be routed vertically into the DDAF pump rooms. In the DDAF pump rooms, it will be connected via a tee to the 1/2 B DDAF pump SX booster pump suction. This new line will be isolated during normal operation. In the event of an ELAP, this new line will be unisolated and the normal SX cooling supply to the DDAF pump SX booster pump will be isolated.

Change 6 Section: Maintain Core Cooling & Heat Removal PWR Portable Equipment Phase 1, 2 and 3 -

Key Reactor parameters, Maintain RCS Inventory Control - PWR Portable Equipment Phase 1, 2 and 3 - Key Reactor parameters, Maintain Spent Fuel Pool Cooling PWR Portable Equipment Phase 1, 2 and 3 - Key SFP parameters, and Safety Support Function PWR Portable Equipment Phase 1, 2 and 3 - Key Parameters.

Reason for Change: All the key parameters supporting FLEX Strategy have been determined.

Change: All key parameters are listed in Attachment A of this document.

Change 7 Section: Maintain Core Cooling and Heat Removal, PWR Portable Equipment Phase 2 -

Deployment Conceptual Design Strategy, Maintain RCS Inventory Control PWR Portable Equipment Phase 2 - Deployment Conceptual Modifications Strategy, Maintain Spent Fuel Pool Cooling PWR Portable Equipment Phase 2 - Deployment Conceptual Design Strategy, and Safety Function Support PWR Portable Equipment Phase 2 - Deployment Conceptual Design Strategy.

Reason for Change: The FLEX equipment deployment strategy has been refined.

Change: (replace section with the following).

The "N" FLEX equipment will be stored in one robust building and the "+1" FLEX equipment will be stored in a commercial building. The robust and commercial buildings will be located adjacent to each other outside the protected area, North of the main parking lot. Primary and alternate deployment routes for FLEX equipment have been identified and are being recorded within the site program document.

  • The site maximum flood water level is at elevation 870.9 feet resulting from a probable maximum precipitation (PMP) event. Byron plant grade elevation is at 869.0 feet and does not vary significantly across the site. The FLEX storage building floor will be constructed above the flood level to an elevation of 872 feet. A majority of the travel path elevations are between elevation 869 feet and 870 feet (Ref. 11). Some travel path locations may be covered by a small amount of water. Since the FLEX pumps and generators are trailer mounted, they should be maintained available when being deployed to different locations at the site.

Page 5 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014

  • Debris removal impacts of the travel routes have been evaluated. The primary or alternate travel route will be utilized in the event one path becomes unavailable due to debris. In addition, the site has purchased an F-750 with a snow plow to assist in debris removal.
  • Extreme hot and cold temperatures should have little impact on the site travel paths. Snow removal will be addressed as part of the site snow removal plan. Post event snow removal will be accomplished with a snowplow equipped FLEX truck.

Change 8 Section: Maintain Core Cooling and Heat Removal, PWR Portable Equipment Phase 2 -

Deployment Conceptual Design Modifications, Maintain RCS Inventory Control PWR Portable Equipment Phase 2 - Deployment Conceptual Modifications Modifications, Maintain Spent Fuel Pool Cooling PWR Portable Equipment Phase 2 - Deployment Conceptual Design Modifications, and Safety Function Support PWR Portable Equipment Phase 2 -

Deployment Conceptual Design Modifications.

Reason for Change: The FLEX equipment storage building build is in progress.

Change: The FLEX storage buildings will consist of one robust building housing "N" FLEX equipment and one commercial building housing the "+1" FLEX equipment.

Change 9 Section: Maintain Containment PWR Installed Equipment Phase 1 Reason for Change: Calculation BYR13-235/BRW-13-0217-M, Containment Pressure and Temperature Response during an ELAP Event (Ref. 12), and BYR99-010/BRW-99-0017-1, Documentation of the Basis of the Emergency Operating Procedures (EOP) Setpoints (Ref. 7),

results.

Change: Update this section with the following:

There are no Phase 1 actions required.

Calculation BYR13-235/BRW-13-0217-M, Containment Pressure and Temperature Response during an ELAP Event (Ref. 12) shows it will take > 30 days for containment pressure to exceed 54.7 psia and 13.7 days for the containment temperature to exceed 200°F. The 54.7 psia and 200°F values are FSG setpoint limits.

The data also shows it would take > 30 days for the containment pressure to exceed 64.7 psia and > 30 days for the containment temperature to exceed 280°F. The 64.7 psia and 280°F values are design basis limits.

Change 10 Section: Maintain Spent Fuel Pool Cooling PWR Installed Equipment Phase 1 Reason for Change: Calculation BYR13-240/BRW-13-0222-M, Spent Fuel Pool Boil Off Analysis during an ELAP Event (Ref. 9), results and elimination of the need to route the alternate high pressure injection path hose within the FHB.

Page 6 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Change: Update this section with the following:

The worst case SFP Heat Load during non-outage conditions is 32.5 Mbtu/hr. Loss of SFP cooling with this heat load results in a time to boil of 10.94 hours0.00109 days <br />0.0261 hours <br />1.554233e-4 weeks <br />3.5767e-5 months <br /> and 90.98 hours0.00113 days <br />0.0272 hours <br />1.62037e-4 weeks <br />3.7289e-5 months <br /> to the top of active fuel. 1/2BCA 0.0, Loss of All AC, directs spent fuel pool make-up at 420' elevations which will occur 24.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> into the event. The equipment line-up for initiating SFP make-up needs to be completed prior to the SFP Boil time of 10.94 hours0.00109 days <br />0.0261 hours <br />1.554233e-4 weeks <br />3.5767e-5 months <br /> into the event to ensure adequate cooling of the spent fuel is maintained.

The worst case SFP heat load during an outage is 62.9 Mbtu/hr. Loss of SFP cooling with this heat load results in a time to boil of 2.72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and 43.96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> to the top of active fuel. With the entire core being located in the SFP, manpower resources normally allocated to aligning core cooling along with the Operations outage shift manpower can be allocated to aligning SFP make-up.1/2 BCA 0.0, Loss of All AC, directs spent fuel pool make-up at 420' elevations which will occur 9.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> into the event. Therefore, completing the equipment line-up for initiating SFP make-up 9.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> into the event ensures adequate cooling of the spent fuel is maintained.

A Spent Fuel Pool vent path will be provided by opening the Fuel Handling building trackway roll-up door. The site has manual actions within the Fuel Handling building, which include aligning the alternate SFP make-up flow path. The site plans to perform these manual actions prior to the onset of SFP boiling. The actions will be directed by OBFSG-5, Initial Assessment and FLEX Equipment Strategy.

Change 11 Section: Maintain Spent Fuel Pool Cooling PWR Installed Equipment Phase 2.

Reason for Change: Elimination of the need to route the alternate high pressure injection path hose within the FHB Change: (Delete this paragraph)

A Spent Fuel Pool Vent path will be provided by opening the FHB trackway roll-up door. The site does have manual actions within the spent fuel pool building to setup pool make-up temporary hoses and the route the RCS inventory alternate connection hoses. The site plans to perform these manual actions prior to the onset of SFP boiling. The actions will be directed by the FSGs being developed.

(Add this paragraph)

A Spent Fuel Pool vent path will be provided by opening the Fuel Handling building trackway roll-up door. The site has manual actions within the Fuel Handling building to align the alternate SFP make-up flow path. The site plans to perform these manual actions prior to the onset of SFP boiling. The actions will be directed by OBFSG-5, Initial Assessment and FLEX Equipment Strategy.

Change 12 Section: Maintain Spent Fuel Pool Cooling PWR Portable Equipment Phase 2 Identify modifications.

Page 7 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Reason for Change: Site strategy can be successfully implemented without the FLEX hoses stored in the fuel handling building (FHB).

Change: Delete this sentence.

The temporary hose / spray nozzle required to be routed within the FHB will be stored in that building and deployed prior to the onset of SFP boiling.

Change 13 Section: Safety Function Support PWR Portable Equipment Phase 1 Reason for Change: Calculation BYR14-060/BRW-14-0080-E results Change: (replace section with the following):

DC power is required to maintain control of ESF equipment and vital instrumentation. Battery chargers are de-energized during a BDBEE leading to loss of DC and associated functions.

The 125VDC battery coping time is approximately 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> with load shedding. The load shedding needs to occur within 65 minutes of the event. Load shedding guidance is provided in 1/2BFSG-4, ELAP DC Bus Load Shed/Management.

Change 14 Section: Safety Function Support PWR Portable Equipment Phase 2 Reason for Change: Calculation results and elimination of the need to route the alternate high pressure injection path hose within the FHB.

Change: Update this section with the following:

A portable diesel generator will provide power to one (1) division of the 480V ESF busses. Repowering at this level will permit the recovery of one division of station battery chargers, DDAFP battery chargers, MCC's powering critical equipment such as Diesel fuel oil transfer pumps, and other ESF equipment beneficial in mitigating the event.

Exelon Generation Company, LLC (Exelon) intends to maintain Operational command and control within the Main Control Room (MCR). Habitability conditions within the MCR and other areas of the plant will be maintained with a tool box approach limiting the impact of high temperatures with methods such as supplemental cooling, personnel rotation and/or availability of fluids.

The fuel handling building habitability should be maintained until the SFP begins to boil. The site has manual actions within the Fuel Handling Building, which include aligning the alternate SFP make-up flow path. The site plans to perform these manual actions prior to the onset of SFP boiling. The actions will be directed by OBFSG-5, Initial Assessment and FLEX Equipment Strategy.

Room temperatures for component with a direct FLEX function are being evaluated to ensure critical component survivability. The following calculations summarize the results:

Page 8 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014

  • Calculation BYR13-234/BRW-13-0216-M, Auxiliary FW Pump Room Temperature Analysis during and ELAP Event (Ref. 13), shows room temperature is maintained within acceptable limits and supplemental room cooling is not required. Procedure guidance for setup of alternate cooling was developed to provide additional options to the operators and is controlled by OBFSG-5, Initial Assessment of FLEX Equipment.
  • Calculation BYR13-237/BRW-13-0219-M, MEER and Battery Room Conditions Flowing ELAP (Ref. 14), shows room doors must be opened when the battery charge is started and forced ventilation is required within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. OBFSG-5, Initial Assessment of FLEX Equipment, provides operators with the necessary guidance to establish alternate ventilation.
  • Calculation BYR13-236/BRW-13-0218-M, Control Room and Auxiliary Electric Equipment Room heat up and Ventilation during an ELAP (Ref. 15), shows the Unit 2 auxiliary electric room portion of the MAC boundary reaching temperature limits first within approximately 5.15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />. OBFSG-51, Alternate Control Room Ventilation, provides operators with the necessary guidance to establish alternate ventilation.

Additionally, a backup water source for core cooling and inventory make-up will be established with a portable FLEX DG feeding one of two SX Tower 480v substations and the local powering of a station deep well pump. The discharge of the deep well pump can be directed into the SX basin or be fed through temporary hoses from the UHS north valve house to the suction of the FLEX pumps.

Change 15 Section: Modification Safety Function Support PWR Portable Equipment Phase 2 Identify Modifications.

Reason for Change: Modifications design details have been refined as parts of the standardized modification design process.

Change: The following modifications will be installed to support the FLEX generator for repowering Division II of station DC batteries:

The primary FLEX connection uses a Bus Connection Device, BCD, installed in a cubicle of BUS 132X and 232X.

The BCD will have the line side connections extending through the breaker frame to standard TPC FLEX electrical connections. Temporary cables will be routed from the TPC connections to the associated units FLEX generator at the 401' turbine building trackway entrance. The BCD and cables will be stored within the associated 4Kv switchgear room to improve operator response time. Once the BUS is energized, appropriate breakers will be closed to provide power to the safety related batteries.

The alternate strategy utilizes the existing site DC crosstie. In the event either unit primary FLEX strategy is unable to be implemented, DC busses 112 and 212 will be crosstied to provide power to the site B train safety related batteries. Critical 480v electrical loads will be powered from the AB TPU to the affected MCCs as called out in 1/2BFSG-5 attachment D. The power will be via deployable extension cords from the TPU to predesigned MCC buckets modified with a new feed breaker and fitted with a short pigtail type connector allowing back feeding of the MCC.

Page 9 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Change 16 Section: PWR Portable Equipment Phase 3 Reason for Change: The phase 3 equipment being supplied by the National SAFER Response Center as part of the site response plan has been refined.

Change: Phase 3 equipment is listed in Attachment B of this document.

Change 17 Section: Phase 3 Response Equipment/Commodities Reason for Change: The phase 3 equipment/commodities being supplied by the National SAFER Response Center as part of the site response plan has been refined.

Change: The National SAFER Response Center will not be providing radiation protection equipment or commodities. These will be requested from other sites or utilities. Additionally, the heavy equipment section has been deleted.

Change 18 Section: Attachment 1A, Sequence of Events time line.

Reason for Change: Site calculations are being refined as part of the FLEX strategy development.

Change:

1. Change RCS cool down setpoint to 260 psig based on calculation BYR99-010/BRW 0017-1, Documentation of the Basis of the Emergency Operating Procedures (EOP)

Setpoints (Ref. 7).

2. Adjusted the timeline limit for DC load shed completion to 65 minutes based on calculation BYR14-060/BRW-14-0080-E, Unit 1(2) 125 VDC Battery FLEX Coping Calculation Common Calc Beyond Design Basis (Ref. 8).
3. Adjusted the timeline limit for restoration of division 2 125 volt DC charger AC power to be completed within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> to ensure the 8-hour requirement is met based on calculation BYR14-060/BRW-14-0080-E, Unit 1(2) 125 VDC Battery FLEX Coping Calculation Common Calc Beyond Design Basis (Ref. 8).
4. Adjusted the timeline and timeline limit for deploying hoses in the fuel handling building to 6

- 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> and 10.94 hours0.00109 days <br />0.0261 hours <br />1.554233e-4 weeks <br />3.5767e-5 months <br /> respectively, based on BYR13-240/BRW-13-0222-M, Spent Fuel Pool Boil Off Analysis during an ELAP Event (Ref. 9).

5. Added an additional action to setup high pressure FLEX pump and hoses at 12 to 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> to ensure they are available to supply borated make-up to the RCS and inject prior to entering Ref lux Cooling. Injection must take please within 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> of the event based on calculation BYR13-239/BRW-13-0221-M, RCS Boration Analysis during an ELAP Event (Ref. 10) and Dave Flahive letter, (Ref. 24).
6. Changed the B DDAF pump overheating time due to SX cooling from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> based on calculation BYR13-026/BRW-13-0031-M, Transient Analysis of SX System Following Loss of A-C Power (Ref. 16).

Page 10 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014

7. Adjusted the timeline for the activity of staging and connecting the med head flex pump to allow for hose deployment time.
8. Added an additional activity in the time line to set up and establish ventilation in the AEER and the MCR within 5.15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />, based on calculation BYR13-236/BRW-13-218-M, Control Room and Auxiliary Electric Equipment Room heat up and Ventilation during an ELAP (Ref .15).
9. Added additional information to timeline for the Phase 2 high head pump to establish makeup prior to entering ref lux cooling, based on WCAP 17601-P and Westinghouse Letter LTR-FSE-14-61 (Ref.24).
10. Adjusted the timeline for setting up the medium pressure FLEX pump to 16 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> based on operator judgment.
11. Adjusted the timeline for initiation of SFP Make up via OA FC Purification pump to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> based on calculation BYR13-240/BRW-13-0222-M, Spent Fuel Pool Boil Off Analysis during an ELAP Event (Ref. 9).
12. Added an additional activity in the time line to repower a UHS 480v Substation to establish make up before 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> to the UHS, based on the calculation BYR14-119 UHS Volume Analysis during an ELAP Event (Ref. 23).

Updated timeline is in Attachment lA of this document Change 19 Section: Attachment 3 Conceptual Sketches Reason for Change: Updated sketches as a result of refining the site strategy.

Change: Updated sketches are in Attachment 3 of this document.

Change 20 Section: Maintain Core Cooling and Heat Removal PWR Portable Equipment Phase 3, Maintain RCS Inventory Control PWR Portable Equipment Phase 3, Maintain Spent Fuel Pool Cooling PWR Portable Equipment Phase 3, and Safety Function Support PWR Portable Equipment Phase 3.

Reason for Change: Updated phase 3 equipment use as a result of refining the site strategy.

Change: (replace section with the following):

Phase 3 equipment for this site includes a water purification skid, a boration skid, portable pumps, generators, diesel fuel handling equipment, cables, hoses and lighting equipment. The portable pumps will be capable of providing the necessary flow and pressure as outlines in Phase 2 response for Core Cooling & Heat Removal, RCS Inventory Control and Spent Fuel Pool Cooling. The portable generators will be capable of providing the necessary 480 volt power requirements as outlined in Phase 2 response for Safety Functions Support. The water purification skid will treat the site make up water used in core cooling. The boration skid will provide long term boration source for additional RCS inventory. The Phase 3 equipment will also provide operations and the ERO flexibility in addressing other issues created by the BDBEE.

Page 11 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Byron Station, Units 1 and 2 expects to comply with the order implementation date and no relief/relaxation is required at this time.

6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the Draft Safety Evaluation (SE) and the status of each item.

Section Reference Overall Integrated Plan Open Item Status Key Site assumptions (p.4) Primary and secondary storage Started - The FLEX storage locations have not been selected yet; buildings will consist of one once locations are finalized robust building housing "N" implementation strategies and routes FLEX equipment and one will be assessed for hazard impact. commercial building housing the "+1" FLEX equipment.

The robust and commercial buildings will be located adjacent to each other outside the protected area, north of the main parking lot.

Primary and alternate deployment routes for FLEX equipment have been identified and are being recorded within the site program document Snow removal will be addressed as part of the site snow removal plan. Post event snow removal will be accomplished with a snowplow equipped FLEX truck.

The site maximum flood water level is at elevation 870.9 feet resulting from a probable maximum precipitation (PMP) event. Byron plant grade elevation is at 869.0 feet and does not vary significantly Page 12 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 across the site. The FLEX storage building floor will be constructed above the flood level to an elevation of 872 feet. A majority of the travel path elevations are between elevation 869 feet and 870 feet (Ref. 11). Some travel path locations may be covered by a small amount of water.

Since the FLEX pumps and generators are trailer mounted, they should be maintained available when being deployed to different locations at the site.

Debris removal impacts of the travel routes have been evaluated. The primary or alternate travel route will be utilized in the event one path becomes unavailable due to debris. In addition, the site has purchased an F-750 with a snow plow to assist in debris removal.

Extreme hot and cold temperatures should have little impact on the site travel paths.

Liquefaction evaluation of the travel routes has been drafted.

Conditions do not exist at Byron for soil liquefaction during a severe seismic event and equipment deployment will not be impeded.

Sequence of events (p.5) The final timeline will be time Started validated once detailed designs are completed and procedures are developed.

Identify how strategies will Identification of storage area and Started - The robust and be deployed (p.7) creation of the administrative commercial buildings will be program. located adjacent to each other Page 13 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 outside the protected area, north of the main parking lot.

Site program document draft has been developed.

Programmatic controls (p.8) Develop an administrative program Started - Site program for FLEX responsibilities, and testing document draft has been

& maintenance. developed.

Testing and maintenance procedures will be developed based on the EPRI FLEX equipment templates.

National SAFER Response Development of Byron Station's Started - Byron Station draft Center plan (p.9) response plan. site response plan (playbook) has been developed.

Key Reactor Parameters Identify additional parameters that Complete - All key parameters are needed in order to support key have been identified and (p. multiple) actions identified in the plant placed in attachment A.

procedures/guidance or to indicate imminent or actual core damage.

Deployment Conceptual Develop the storage structure Complete - The FLEX storage Design (p. multiple) conceptual design. buildings will consist of one robust building housing "N" FLEX equipment and one commercial building housing the "+1" FLEX equipment. The robust building will be a 140 feet x 60 feet. The commercial building will be a 60 feet x 60 feet.

Detailed building designs have been issued and construction is in progress.

Maintain RCS Inventory A calculation will be required for the Started - Calculation BYR13-Control, Phase 2 (p.23) timing of the boration and quantity 239/BRW-13-0221-M (Ref. 10) required. identifies the timing and quantity of boration required.

Specifically, boration will need to start prior to 17.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> into the event and require 15,240 gallons of water injected at 40 gallons per minute.

Maintain Containment, Additional calculations will be Started - Calculation BYR13-Page 14 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Phase 1 (p.31) performed to evaluate containment 235/BRW-13-0217-M (Ref. 12) response. and BYR14-046/BRW 0058 (Ref. 17) evaluate containment response in all modes. Containment pressure and temperature will reach the FSG set point limits in >30 days and 13.7 days respectively. In addition, containment pressure and temperature will reach design basis pressure and temperature limits in > 30 days.

Maintain Spent Fuel Pool Procedure development for Initial Complete Procedures will Cooling, Phase 1 (p.39) Spent fuel pool make-up with gravity not be developed for SFP drain from the RWST. make-up with gravity drain.

The primary method for SFP make-up will be repowering the installed OA refueling water purification pump utilizing the 480V Flex generator connection described in the Safety Functions Support section of Reference 1. The RWST with the installed piping will be used as the suction source.

The discharge will use the existing OA refueling water purification pump discharge piping directly to the SFP. This method is outlined in OBFSG-11, Alternate SFP Makeup and Cooling.

Maintain Spent Fuel Pool Initial calculations were used to Started - Calculation BYR13-Cooling, Phase 1 (p.39) determine the fuel pool timelines. 240/BRW-13-0222-M (Ref. 9)

Formal calculations will be performed determined the spent fuel pool to validate this information during timeline.

development of the spent fuel pool With both units at power, time cooling strategy detailed design.

to boil = 10.94 hours0.00109 days <br />0.0261 hours <br />1.554233e-4 weeks <br />3.5767e-5 months <br /> and time to TAF = 90.98 hours0.00113 days <br />0.0272 hours <br />1.62037e-4 weeks <br />3.7289e-5 months <br />. EP procedure set point for requiring makeup is SFP Page 15 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 elevation of 420 foot, which should be reached in approximately 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

With one unit in a refueling outage, time to boil = 2.72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and time to TAF = 43.96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br />.

Maintain Spent Fuel Pool Evaluation of the spent fuel pool area Complete - A Spent Fuel Pool Cooling, Phase 1, (p.39 for steam and condensation will be (SFP) vent path will be and p.42) performed and used to determine if provided by opening the Fuel vent path strategy is needed. Handling (FH) building trackway roll-up door per OBFSG-11, Alternate SFP Makeup and Cooling. The site plans to perform required manual actions within the FH building prior to the onset of SFP boiling determined by calculation BYR13-240/BRW-13-0222-M (Ref. 9).

A formal evaluation of the spent fuel pool area for steam and condensation will not be performed.

Safety Functions Support, Habitability conditions will be Complete - Habitability Phase 2 (p.51) evaluated and a strategy will be conditions within the MCR will developed to maintain Main Control be maintained with a tool box Room. approach limiting the impact of high temperatures with methods such as supplemental cooling, personnel rotation and/or availability of fluids.

OBFSG-51, Alternate MCR Ventilation, provides the necessary guidance to establish alternate ventilation within the main control room.

Safety Functions Support, Critical ventilation assets may be Started - Habitability Phase 2 (p.51) required to support DDAF pumps, conditions within the Plant will station battery rooms, miscellaneous be maintained with a tool box electric equipment rooms, and fuel approach limiting the impact of Page 16 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 handling building personnel high temperatures with habitability and/or component methods such as survivability. Specific analyses of supplemental cooling, these rooms will be performed. personnel rotation and/or availability of fluids.

Component survivability is being evaluated with the following calculations:

  • Calculation BYR13-234/BRW-13-0216-M, Auxiliary FW Pump Room Temperature Analysis during and ELAP Event, (Ref. 13), shows room temperature is maintained within acceptable limits and supplemental room cooling is not required.

Procedure guidance for setup of alternate cooling was developed to provide additional options to the operators and is controlled by OBFSG-5, Initial Assessment of FLEX Equipment.

  • Calculation BYR13-237/BRW-13-0219-M, MEER and Battery Room Conditions Flowing ELAP, (Ref. 14) shows room doors must be opened when the battery charge is started and forced ventilation is required within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. 1/2BFSG-5

/ OBFSG-5, Initial Assessment of FLEX Equipment, provides operators with the necessary guidance to establish alternate ventilation.

  • Calculation BYR13-236/BRW-13-0218-M, Page 17 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Control Room and Auxiliary Electric Equipment Room heat up and Ventilation during an ELAP (Ref. 15), shows the Unit 2 auxiliary electric room portion of the MCR boundary reaching temperature limits first within approximately 5.15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />. OBFSG-51, Alternate Control Room Ventilation, provides operators with the necessary guidance to establish alternate ventilation.

Interim Safety Evaluation Open Item Status Byron's ISE Response Line Item Description Answer Number Number 1 Open Item Core Subcriticality- The NRC staff Started- Byron will abide by the 3.2.1.8.A has not endorsed the industry- position expressed by the NRC proposed position paper regarding staff in the letter dated January 8, boron mixing. The licensee has 2014 regarding the boron mixing indicated that Byron is planning on issue for PWRs (Adams Accession following this methodology. Thus, No. ML13276A183). The NRC further resolution of this issue will be letter states that the NRC staff has necessary in the next phase of the reviewed the information submitted audit process. to date and concluded that use of the industry approach dated August 15, 2013, entitled "Westinghouse Response to NRC Generic Request for Additional Information (RAI) on Boron Mixing in Support of the Pressurized Water Reactor Owners Group (PWROG)," ML13235A135, is acceptable with clarifications listed in the letter.

Reference 10 demonstrates that the Flexible and Diverse Coping Strategies (FLEX) RCS make-up Page 18 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 pump will be deployed and capable of injecting into the RCS prior to the time when injection is required including the appropriate time margin to ensure adequate sub-criticality for both the maximum seal leakage and no seal leakage scenarios. The analyses and evaluations supporting the 01P demonstrate that the FLEX RCS make-up pump will be aligned one hour prior to the loop flow rate decreasing below the loop flow rate corresponding to single-phase natural circulation for the assumed highest applicable leakage rate at normal operating pressure and temperature for the reactor coolant pump seals and unidentified reactor coolant system leakage. Therefore, the boron mixing criteria are met.

The current site timeline shows the High pressure FLEX pump will be available for RCS boration within 12 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> of the event initiation which meets the timing requirements outlined in Reference 22.

Confirmatory Items 2 3.1.1.1.A Storage & Protection of FLEX Complete - The site FLEX equipment - Confirm final design of equipment storage structure design FLEX storage structure conforms to is complete and complies with the NEI 12-06, Sections 5.3.1, 7.3.1, requirements of 12-06, Sections and 8.3.1 for storage considerations 5.3.1, 7.3.1, and 8.3.1 storage for the hazards applicable to Byron. considerations for the hazards applicable to Byron.

The FLEX storage buildings will consist of one robust building housing "N" FLEX equipment and one commercial building housing the "+1" FLEX equipment.

3 3.1.1.3.A Procedural Interface Considerations Started - 1/2 BFSG-7, Loss of Vital Page 19 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 (Seismic) Confirm procedure for Instrumentation or Control Power measuring key instruments at draft has been developed. It containment penetrations using provides guidance for alternate portable instrument, methods to measure key instruments at appropriate locations within the plant.

4 3.1.1.4.A Off-Site Resources Confirm Complete - Site primary staging National SAFER Response Center area (Area C) location is the local staging area and method of Whiteside County Airport. The transportation to the site in future 6- Alternate staging area (Area D) month update location is DeKalb Sycamore Airport. Primary and alternate transportation routes have been identified between these locations and Byron Station. These routes are detailed within the sites National SAFER Response Center response plan (playbook). The main transportation method will be by a heavy haul vehicle utilizing any available transportation route.

If an accessible transportation route cannot be identified, helicopter transportation will be utilized.

5 3.1.5.1.A Protection of Equipment (High Started - The FLEX storage Temperature) - Confirm FLEX buildings ventilation systems will be storage structure will maintain FLEX designed as required by code and equipment at a temperature range to to maintain the FLEX equipment in ensure its likely function when called a ready state. The maximum upon. building temperature will be controlled by forced ventilation.

Temperature information from Byron's UFSAR indicates the site extreme high temperature is a maximum of 102°F.

The FLEX low pressure pump was designed to be able to operate with an outside air temperature of 176°F.

The FLEX medium head and high head pump purchase specification requires a maximum operating air temperature of 110°F.

The FLEX Generator purchase Page 20 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 specification requires a maximum operating air temperature of 122°F.

6 3.1.5.3.A Deployment of Equipment (High Started - FLEX equipment is being Temperature) - Confirm that the purchased with appropriate effects of high temperature on FLEX temperature specifications to equipment have been evaluated in ensure it will function in the the locations they are intended to extreme temperature conditions operate. applicable to the site. Temperature information from Byron's UFSAR indicates the site extreme high temperature is a maximum of 102°F.

The FLEX low pressure pump was designed to be able to operate with an outside air temperature of 176°F.

The FLEX medium head and high head pump purchase specification requires a maximum operating air temperature of 110°F.

The FLEX Generator purchase specification requires a maximum operating air temperature of 122°F.

FLEX equipment primary staging locations are located outside of buildings and therefore require no additional cooling.

7 3.2.1.A RCS cooling & RCS inventory Started The primary conditions control - Specify which analysis considered are based on the performed in WCAP-17601 is being Westinghouse reference coping applied to Byron. Additionally, justify cases described in section 5.2.1 of the use of that analysis by WCAP-17601-P (Ref. 18). The identifying and evaluating the extended loss of alternating current important parameters and (AC) power (ELAP) simulation assumptions demonstrating that parameters matrix provided in they are representative of Byron and Westinghouse correspondence appropriate for simulating the ELAP LTR-FSE-14-43 (Ref. 22) outlines transient. the comparison of items for Byron Station.

8 3.2.1.1.A NOTRUMP - Confirm that the use of Started Exelon has used generic NOTRUMP in the ELAP analysis is ELAP analysis performed in WCAP 17601-P (Ref. 18) with the limited to the flow conditions before NOTRUMP computer code to reflux condensation initiates. This Page 21 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 includes specifying an acceptable support the mitigating strategy in its definition for reflux condensation Overall Integrated Plan (01P). The use of NOTRUMP was limited to coolin g.

the thermal-hydraulic conditions before reflux condensation initiates. The initiation of reflux condensation cooling is defined when the one hour centered moving average (CMA) of the flow quality at the top of the SG U-tube bend exceeds 0.1 in any one loop.

The analyses and evaluations supporting the 01P demonstrate that the Flexible and Diverse Coping Strategies (FLEX) reactor coolant system (RCS) make-up pump will be aligned prior to the loop flow rate decreasing below the loop flow rate corresponding to the definition of the onset of reflux cooling. Calculation BYR13-239/BRW-13-0221-M (Ref. 10) demonstrates that the RCS FLEX pump will be deployed and capable of injecting into the RCS prior to the time when injection is required including the appropriate time margin to ensure adequate sub-criticality for both the maximum seal leakage and no seal leakage scenarios. Site timeline shows that the high pressure FLEX pumps are available between 12 and 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> following the beyond-design-basis external event (BDBEE) which meets the timing requirements to allow for the necessary Boron mixing.

3.2.1.1.B ELAP Analysis - Confirm Started - Calculation BYR99-calculations to verify no nitrogen 010/BRW-99-0017-1 (Ref. 7) injection into RCS during determined the minimum steam depressurization. generator (SG) pressure to preclude a significant amount of nitrogen from being injected into the RCS from the accumulator is 160 psig. This value was increased to 260 psig by adding an additional 100 psi margin, as recommended by the Westinghouse Owners Group Emergent Procedure Page 22 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 background document.

1/2BCA 0.0 provides direction to stop the RCS depressurization at a SG pressure of 260 psig and isolate the safety injection accumulators.

10 3.2.1.1.0 Confirm analysis for secondary side Started - Procedural guidance has SG fouling due to the use of been developed which follows the abnormal water sources (RWST, industry approach of prioritizing the well water, SX water) cleanest to dirtiest water sources.

The first choice of secondary makeup with the DD AF Pp is the Condensate Storage Tank (CST).

If the CST is not available, then by design, the suction will be swapped to the UHS.

At about the 10 the hour mark post event UHS makeup from Well Water, (WW), powered by a FLEX DG will be used.

The National SAFER Response Center will deliver a water purification skid within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

This skid will be installed upon arrival and used to condition the S/G cooling water indefinitely.

A quantitative analysis, to ensure this strategy is successful, is planned.

11 3.2.1.1.D Complete analysis for length of time Started The Site water source for prior to depletion of the RWST and RCS boration and inventory is the determine whether additional two (2) robust RWST's. The usable boration equipment is needed for volume of 315,000 gallons per Phase 3 coping strategy. RWST should last greater than 7 days with both units in mode 1-4.

An RWST usage calculation is in progress to determine the need and timing of additional Phase 3 boration equipment.

12 3.2.1.2.B Reactor Coolant Pump (RCP) Seal Complete Leakage - In some plant designs, (1) The Westinghouse letter LTR-the cold legs could experience Page 23 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 temperatures as high as 580°F RES-13-153, Documentation before cooldown commences. This of 7228C 0-Rings at ELAP is beyond the qualification Conditions, concludes, with a temperature (550°F) of the 0-rings high level of confidence, that used in the RCP seals. For those the integrity of the associated Westinghouse designs, a discussion 0-Rings will be maintained at should be provided to justify that (1) the temperature conditions the integrity of the associated 0- experienced during the ELAP rings will be maintained at the event.

temperature conditions experienced (2) In June 2014, Westinghouse during the ELAP event, and (2) the issued PWROG-14015-P, "No.1 Seal Flow Rate for seal leakage rate of 21 gpm/seal Westinghouse Reactor used in the ELAP is adequate and Coolant Pumps Following Loss acceptable. of All AC Power." The purpose of this report was to calculate a new number 1 seal leakage rate based on the actual leak-off line layout at Byron station versus the representative leak-off line layout assumed in WCAP-10541.

The new, lower leakage rates are being utilized in calculation revisions for Containment Pressure, Containment Temperature, and Boration.

13 3.2.1.2.E RCP Seal Leakage Rates - The Complete The Byron RCPs are licensee is requested to provide the model 93A. This aligns with the manufacturer and model number of seal leakage model listed in the RCP seals and discuss whether WCAP17601-P analysis as shown or not the RCP and seal in Table 5.3.1.7-1.

combination complies with a seal leakage model described in WCAP-17601.

14 3.2.1.3.A Decay Heat- Verify that the Started - The Westinghouse Integrated Plan update provides the nuclear steam supply system details of the WCAP 17601-P (NSSS) calculations documented in methodology to include the values of WCAP17601-P using the certain key parameters used to NOTRUMP code were performed determine the decay heat levels, with the ANS 5.1 1979 + 2 sigma Address the adequacy of the values decay heat model and assumed the used. reactor is initially operating at 100%

power (NOTRUMP reference case core power is 3723 MWt).

Implementation of this model Page 24 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 includes fission product decay heat resulting from the fission of U-235, U-238, and Pu-239 and actinide decay heat from U-239 and Np-239. The power fractions are typical values expected for each of the three fissile isotopes through a three region burn-up with an enrichment based on typical fuel cycle feeds that approach 5%. With that, a conversion ratio of 0.65 was used to derive the decay power of the two actinides U-239 and Np-239. Fission product neutron capture is treated per the ANS standard. The decay heat calculation utilizes a power history of three 540 day cycles separated by two 20 day outages that bounds initial condition 3.2.1.2 (1) of the Nuclear Energy Institute (NEI) document NEI 12-06, Section 3.2.1.2 (with a minimum assumption from NEI 12-06 that the reactor has been operated at 100%

power for at least 100 days prior to event initiation). Therefore, the decay heat curve assumed in the Westinghouse calculations in WCAP 17601-P is representative of Byron and Byron Units 1 and 2.

The primary-side transient profile assumed in the reactor coolant system (RCS) inventory control and long-term sub-criticality calculations for Modes 1 through 4 with steam generators available is based on the Westinghouse reference coping case of WCAP-17601-P and plant specific parameters such as reactor coolant system nominal temperature(s), pressures(s), and volumes, and accumulator cover gas pressures. These calculations do not, however, include any decay heat model and rely on the case Page 25 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 runs cited from WCAP-17601-P regarding decay heat related phenomenon.

15 3.2.1.4.A Initial Values for Key Plant Started - The primary system Parameters and Assumptions- conditions considered are based on the Westinghouse reference coping Confirm WCAP-17601-P analyses cases described in Section 5.2.1 of are bounding for Byron for strategy WCAP-17601-P (Ref. 18). The response or verify plant-specific extended loss of alternating current analyses if more restrictive limits are (AC) power (ELAP) simulation used due to more restrictive plant parameters matrix provided in specific limits. Westinghouse Correspondence LTR-FSE-14-43 (Ref. 22) outlines the comparison of items for Byron Station.

16 3.2.1.4.B Initial Values for Key Plant Started Calculation BYR13-Parameters and Assumptions- 238/BRW-13-220-E (Ref. 19)

Confirm calculations to validate 8 confirms the pump batteries can hours run time limit on DDAF pump operate for > 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> following ELAP batteries and DDAF room temp for event.

pump operation and human Calculation BYR13-234/BRW occupancy. Also, confirm site phase 0216-M (Ref. 13) shows room 2 staffing study confirms the temperature limit for equipment required time can be met for refilling survivability is not challenged.

diesel day tank.

Habitability conditions will be maintained with a tool box approach limiting the impact of high temperatures with methods such as supplemental cooling, personnel rotation and/or availability of fluids.

OBFSG-5, Initial Assessment and FLEX Equipment Staging, provides the necessary actions to install temporary fans to provide cooling to the DDAF pump room.

The Phase 2 staffing study was completed in April 2014. Results were submitted to the NRC by letter RS-14-129 dated May 29, 2014.

17 3.2.1.5.A Monitoring Instruments and Control- Complete - All key parameters Confirm additional parameters have been identified and placed in evaluated for use in plant Attachment A.

procedures/guidance or to indicate imminent or actual core damage.

18 3.2.1.6.A Sequence of Events - Confirm that Started - The final time line will be Page 26 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 the final timeline has been time validated as the time sensitive validated after detailed designs are actions, listed in Attachment 1A, go completed and procedures are through the validation process.

developed. The results may be Results will be provided in a future provided in a future 6-month update. update.

19 3.2.1.6.B Sequence of Events - Confirm Started - Hydraulic calculation analysis to validate Phase 2 pump BYR13-144/BRW-13-0160-M (Ref.

capacities. 20), FLEX Pump Sizing and Hydraulic Analysis, evaluates the FLEX high pressure, medium pressure and low pressure pump capacities. The calculations validate the capability of the Phase 2 pumps for their intended FLEX purpose.

20 3.2.1.9.A Use of portable pumps - Confirm Started Station FLEX strategies final design of strategies meets "use utilize 1/2BCA 0.0, loss of all AC, of portable pumps" guideline in NEI as the controlling document to 12-06 Section 3.2.2 Guideline 13. identify and implement the supporting BFSG Series procedures.

The low pressure FLEX pump connection and line-up is controlled by OBFSG-5, Initial Plant Assessment and FLEX Equipment Staging.

The medium pressure pump connection and line-up is controlled by 1/2BFSG-3, Alternate Low Pressure Feedwater.

The high pressure pump connection and line-up is controlled by 1/2BFSG-1, Long Term RCS Inventory Control, and 1/2BFSG-8, Alternate RCS Boration.

21 3.2.2.A SFP cooling -Verify procedure for Started - The Spent fuel pool make-SFP makeup via gravity drain; up via gravity drain from the RWST confirm verification of timeline for procedure guidance is not being performing the strategy; and confirm developed due to its limited make-evaluation of SFP area for steam up flow. The primary means for and condensation affects. SFP make-up utilizes the installed OA Refueling Water Purification Pump with FLEX AC power.

Page 27 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 OBFSG-11, Alternate SFP Make-up and Cooling, provides operators with the necessary guidance to execute the task.

The SFP environment has the potential to communicate with the Aux Building via the FHB supply ducting, because the FHB Supply dampers fail open on a loss of AC.

It is reasonable to assume this flow path will be isolated by fire damper OVA413Y. The fire damper will close when its fusible link melts shortly after reaching a set point of 165°F. Due to this damper arrangement and lack of motive force, minimal FHB atmosphere should be dispersed in to the AB.

OBFSG-5, Initial Assessment and FLEX Equipment Staging, or OBFSG-11, Alternate SFP make-up and Cooling, establish a Spent Fuel Pool Vent path by opening the SFP trackway roll-up door.

The site does have manual actions within the spent fuel pool building to setup temporary hose for pool make-up. The site plans to perform these manual actions prior to the onset of SFP boiling. OBFSG-5, Initial Assessment and FLEX Equipment Staging and OBFSG-11, Alternate SFP make-up and Cooling, provide the necessary guidance to execute the task.

The final time line will be validated after the detailed design is completed and will be provided in a future update.

All operator actions are completed prior to SFP boiling. The FHB trackway rollup doors are opened to provide a vent path. The only equipment in the FHB post event Page 28 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 that are required are the newly installed SFPI instruments which are designed to operate in this environment.

22 3.2.3.A Containment - Confirm containment Started Calculation BYR13-reanalysis supports no Phase 1, 2, 235/BRW-13-0217-M (Ref. 12) and 3 mitigation strategies are Containment Pressure and required because containment Temperature Response during an pressure and temperature are ELAP Event, confirms the response maintained within acceptable limits. supports Phase 1, 2, and 3 mitigation strategies. Containment pressure and temperature will reach the FSG set point limits in

>30 days and 13.7 days respectively. In addition, containment pressure and temperature will reach design basis pressure and temperature limits in

> 30 days.

23 3.2.3.B Containment - Confirm evaluation Started Calculation BYR13-performed for the need to monitor 235/BRW-13-0217-M (Ref. 18) containment temperature. shows Containment pressure and temperature will reach the FSG set point limits in >30 days and 13.7 days respectively. In addition, containment pressure and temperature will reach design basis pressure and temperature limits in

> 30 days. Even with these long timeframes, containment temperature has been added to the key parameter list to provide operators with additional tools.

Monitoring of containment temperature can be performed on an Intermittent bases and will be controlled by emergency procedures and 1/2BFSG-7, Loss of Vital Instrument or Control Power.

24 3.2.4.1.A Equipment cooling - Confirm Started EC 394153, Alternate SX modification has been performed to Supply to 1/2SX04P Pump Suction prevent DDAF pump from FLEX Mod 3, resolves DDAF pump overheating due to cooling water over heating due to SX water Page 29 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 recirculation flow paths within the recirculation within the SX system SX system cycling and overheating by providing an alternate SX the pump within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. supply. 1/2BFSG-2, Alternate AFW/EFW Suction Source provides operators with the necessary guidance to align the alternate SX supply.

25 3.2.4.2.A Ventilation - Equipment Cooling - Calculation BYR13-234/BRW Review licensee's evaluation of loss 0216-M, Auxiliary FW Pump Room of ventilation effects on equipment in Temperature Analysis during and various rooms (DDAF pump room, ELAP Event, (Ref. 13), shows room battery rooms, control room, temperature is maintained within miscellaneous electrical equipment acceptable limits and supplemental rooms) room cooling is not required.

Procedure guidance for the setup of alternate cooling was developed to provide additional options to the operators and is controlled by OBFSG-5, Initial Assessment of FLEX Equipment Calculation BYR13-237/BRW 0219-M, MEER and Battery Room Conditions Following ELAP (Ref.

14), shows battery room can reach 2% hydrogen concentration within 2.52 hours6.018519e-4 days <br />0.0144 hours <br />8.597884e-5 weeks <br />1.9786e-5 months <br /> of re-energizing the battery changer. Hydrogen generation begins when the battery chargers are re-energized. When power is re-established to the battery charger, power is also returned to the battery room vent fan. Operation of the battery room vent fan will prevent hydrogen generation from becoming a concern. 1/2BFSG-5, Initial Assessment and FLEX Equipment Staging, provides operators with the necessary guidance to establish forced ventilation within the battery room. Additionally, this calculation shows the MEER room will require forced ventilation to preserve component availability within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of re-energizing the Page 30 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 battery changers. 1/2BFSG-5 /

OBFSG-5, Initial Assessment of FLEX Equipment, provides operators with the necessary guidance to establish alternate ventilation.

Calculation BYR13-236/BRW 0218-M, Control Room and Auxiliary Electric Equipment Room heat up and Ventilation during an ELAP (Ref. 15) shows the Unit 2 Auxiliary Electric Equipment Room portion of the MCR boundary reaching temperature limits first within approximately 5.15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />.

OBFSG-51, Alternate Control Room Ventilation, provides operators with the necessary guidance to establish alternate ventilation.

26 3.2.4.2.6 A discussion is needed on the Started - Calculation BYR13-extreme high/low temperatures 237/BRW-13-0219-M, MEER and effects of the battery's capability to Battery Room Conditions Following perform its function for the duration ELAP (Ref. 14), shows battery of the ELAP event and hydrogen room can reach 2% hydrogen gas ventilation during recharging concentration within 2.52 hours6.018519e-4 days <br />0.0144 hours <br />8.597884e-5 weeks <br />1.9786e-5 months <br /> of batteries during Phase 2 and 3. re-energizing the battery changer.

Hydrogen generation begins when the battery chargers are re-energized. When power is re-established to the battery charger, power is also returned to the battery room vent fan. Operation of the battery room vent fan will prevent hydrogen generation from becoming a concern. 1/2BFSG-5, Initial Assessment and FLEX Equipment Staging, provides operators with the necessary guidance to establish forced ventilation within the battery room.

Calculation BYR13-237/BRW 0219-M (Ref. 14) assumes a battery room maximum temperature of 138F and a Page 31 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 minimum temperature of 60F during an ELAP event. The temperature effects on the battery capacity were incorporated into this calculation.

27 3.2.4.3.A Heat Tracing - Confirm that potential Started - The site FLEX strategy adverse impacts from a loss of heat has been evaluated for potential tracing and normal heating on any freezing due to loss of heat trace or equipment credited for ELAP other heat sources. Susceptible mitigation are adequately equipment includes the RWST, addressed. In particular, ensure an temporary hoses and pumps RCS inventory and source of deployed outside. A calculation, to borated water is available for a show the effects of freezing on this BDBEE associated with extreme equipment is in progress, BYR14-cold, ice, and snow. 130/BRW-14-0211-M, Evaluation of Tank and Hose Freezing during an ELAP, (Ref .25). The FLEX temporary hoses, routed outside, will be protected from freezing by maintaining positive flow or by draining when not in use. Additional sections of FLEX hose are also available as a replacement in the event a section of the hose freezes.

28 3.2.4.4.A Communications - Confirm that Started - Communications upgrade upgrades to the site's conceptual design is complete.

communications systems have been For the 1st - 2nd refuel outage, completed.

(B2R18), The Site will have 3 Iridium Satellite phones available for the SM/SED in the MCR area.

Additional handheld radios for use on talk-around with batteries staged in the robust FLEX building. The Site will have Sound Powered phones and cords in lockers in the plant with cables as well as Bull Horns for help with notifications.

In Addition, for the 2nd 2nd Refuel outage, (B1 R20), the site will complete the NARS Upgrade satellite communications system.

Detail design will be communicated Page 32 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 in a future 6 month update.

29 3.2.4.6.A Personnel Habitability - Review Complete - Habitability conditions licensee's evaluation of loss of within the MCR and other areas of ventilation effects on personnel the plant will be maintained with a habitability and accessibility, tool box approach limiting the impact of high temperatures with methods such as supplemental cooling, personnel rotation and/or availability of fluids.

30 3.2.4.7.A Water Sources - Justify the time at Complete - Based on WCAP-which SG dryout will occur. 17601-P Table 5.4.1.1-1 Case 2A S/G dryout would occur at 3,670 seconds, (61.16 minutes).

31 3.2.4.8.A Electrical Power Sources I Isolation Started 1/2BFSG-5, Initial and interactions- confirm class lE Assessment and FLEX Equipment equipment is protected from faults in Staging, provides electrical bus portable/FLEX equipment and isolation and ensures multiple multiple sources do not attempt to sources are not simultaneously power electrical buses. connected to buses.

The portable FLEX DG circuit breakers are sized to provide over-current protection downstream of the circuit breakers.

32 3.2.4.9.A Portable Equipment Fuel - Confirm Started - The Units 1 and 2 "B" that complete analysis of fuel usage tanks contain 100,000 gallons of fuel. It is reasonable to assume the requirements has been developed site fuel supply will last until roads after the specific FLEX equipment is can be re-opened and local tanks identified and the fuel usage is can replenish the supply. The site determined. A discussion is needed has an additional 100,000 gallons on maintaining the quality of fuel contained in the "A" train tanks, but stored in the tanks for extended it is not directly available to the Diesel fuel oil transfer pumps. The periods of time site also has 125,000 gallon and 50,000 gallons storage tanks that are not robust but would be used if available. An analysis is planned to show that the refueling capability of our F-750 truck is sufficient to ensure all of the FLEX diesel driven equipment can be kept re-fueled until additional capabilities can be brought to the site.

33 3.2.4.10.A Load reduction to conserve DC Started EC393367, Electrical power- Confirm sizing calculations FLEX Connections to Unit 2 Safety for FLEX generators and details of Related Buses (Bus 232x),

Page 33 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 load shedding. contains FLEX DG sizing calculations.

DC load shedding will be performed in accordance with BFSG-4, ELAP DC Load Shed/Management. Load shedding should start at approximately 35 minutes after the start of an ELAP event and complete within 65 minutes.

BYR14-060/BRW-14-0080-E (Ref.

8) demonstrates the Division 2 DC batteries will last at least 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> with the performance of appropriate load shedding.

7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.

8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.

1. Byron Station, Units 1 and 2, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 28, 2013 (RS-13-017).
2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012.
3. NEI 12-06 Rev. 0, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, dated August 2012.
4. Byron Station's First Six Month Status Report for the Implementation of FLEX, dated August 28th, 2013.
5. Byron Station's Second Six Month Status Report for the Implementation of FLEX, dated February 28th, 2014.
6. Byron Station, Units 1 and 2 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigating Strategies) (TAC NOS. MF0895 AND MF0896), dated December 17, 2013.

Page 34 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014

7. BYR99-010/BRW-99-0017-1 Rev. 2, Documentation of the Basis of the Emergency Operating Procedures (EOP) Setpoints, dated June 2014. DRAFT
8. BYR14-060/BRW-14-0080-E Rev. 0, Unit 1(2) 125 VDC Battery FLEX Coping Calculation Common Calc Beyond Design Basis, dated May 2014. DRAFT
9. BYR13-240/BRW-13-0222-M Rev. 0, Spent Fuel Pool Boil Off Analysis during an ELAP Event, dated March 2014.
10. BYR13-239/BRW-13-0221-M Rev. 0, RCS Boration Analysis during an ELAP Event, dated June 2014. DRAFT
11. Exelon Structural Drawing S-183 Rev. AF, Roadway Plan Plant and Construction Laydown Area, dated 5/2014.
12. BYR13-235/BRW-13-0217-M Rev. 0, Containment Pressure and Temperature Response during an ELAP Event, dated June 2014. DRAFT
13. BYR13-234/BRW-13-0216-M Rev. 0, Auxiliary FW Pump Room Temperature Analysis during and ELAP Event, dated March 2014.
14. BYR13-237/BRW-13-0219-M Rev. 0, MEER and Battery Room Conditions Flowing ELAP, dated June 2014. DRAFT
15. BYR13-236/BRW-13-0218-M Rev. 0, Control Room and Auxiliary Electric Equipment Room heat up and Ventilation during an ELAP, dated June 2014. DRAFT
16. BYR13-026/BRW-13-0031-M Rev. 0, Transient Analysis of SX System Following Loss of A-C Power, dated August 2014.
17. BYR14-046/BRW-14-0058-M Rev. 0, Containment Environment Following an Extended Loss of AC Power During Shutdown, dated June 2014. DRAFT
18. WCAP 17601-P.Rev. 1, Reactor Coolant System Response to the Extended Loss of AC Power Event for Westinghouse, Combustion Engineering and Babcock & Wilcox NSSS Designs, dated January 2013.
19. BYR13-238/BRW-13-220-E Rev. 0, DDAF Pump Battery Duty Cycle and Sizing for a BDBEE, dated January 2014. DRAFT
20. BYR13-144/BRW-13-0160-M Rev. 0, FLEX Pump Sizing and Hydraulic Analysis, dated April 2014. DRAFT
21. Letter to Mr. Jack Stringfellow titled "Boron Mixing Endorsement Letter in Regards to Mitigation Strategies Order EA-12-049," January 8, 2014. (Agency wide Documents Access and Management System (ADAMS) Accession Number ML13276A183)
22. Westinghouse Correspondence LTR-FSE-14-43, Revision O-A, "Exelon Generation Company, LLC Mitigation Strategies Order (EA-12-049) Design ELAP Simulation Parameters," July 16, 2014. DRAFT
23. BYR14-119 UHS Rev 0, Volume Analysis during an ELAP Event dated July 2014
24. Letter to David Flahive, of Westinghouse, titled "Exelon Generation Company, LLC Mitigation Strategies Order (EA-12-049) Open and Confirmatory Item Responses," Letter LTR-FSE-14-61 Rev.0-A dated July 17, 2014 Page 35 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014

25. BYR14-130/BRW-14-0211-M Rev. 0, Evaluation of Tank and Hose Freezing during an ELAP Dated Aug 2014 DRAFT Page 36 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment A Key Parameters Essential Instrumentation Safety Function SG Pressure: RCS pressure boundary and pressure PI-515, PI-516, PI-525, PI-535, PI-545 and control PI-546 SG Level: , RCS pressure boundary and pressure NR - LI-517, LI-519, LI-527, LI-537, LI-547 control and LI-549 WR - LI-502 and LI-503 RCS Temperature: RCS heat removal Cold Leg - TI-413B, TI-423B, TI-433B and TI-443B RCS temperature: Hot leg - TI-413A, TI- RCS heat removal 423A, TI-433A and TI-443A Core Exit Thermocouple (CET) Temperature RCS heat removal RCS Pressure: WR - PI-403 1 RCS pressure boundary and pressure control Pressurizer level: LI-460 RCS inventory Vessel Level Indicating System (RVLIS) LI- RCS inventory RCO20 Containment Pressure: PI-PC005 Containment integrity Containment Temperature: TE-VP030, TE- Containment integrity VP031, TE-VP032, and TE-VP033.

Spent Fuel Pool Level: OLI-FC00 I B and OLI- SFP inventory FC002B.

RWST Level Channel LT-931 RCS inventory Post Accident Neutron Monitor NI-NR006 Reactor core subcriticality AJB DC Bus Voltage _EI-DC002 Battery capacity AFW Flow: FI-AF012A, FI-AF014A, FI- RCS heat removal AF016A and FI-AF018A ...

AFW Suction Pressure PI-AF055 4-RCS heat removal CST level: ILI CD051A RCS heat removal Accumulator Level: LI951, LI953, LI955, and RCS inventory LI 957 Core Exit Thermocouple TI-1T002, Reactor Vessel Level Indicating System LI-RCO20, Post Accident Neutron Monitor NI-NR006 A/B and Spent Fuel Pool Level OLI-FC001B and OLI-FC002B will be re-energized per the site strategy.

Page 37 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment B Phase 3 Equipment PWR Portable Equipment Phase 3 Use and (potential /flexibility) diverse uses Performance Notes Criteria Note: The National SAFER Response Center NRC equipment is being procured at the time of this submittal.

The equipment listed is a generic list provided by the National SAFER Response Center and even though we may not require this equipment in our plan it will be available and could be utilized in the phase 3 time period.

List portable Core Containment SFP Instrumentation Accessibility equipment Medium X X X X X 1 MW output at Backup Voltage 4160 Vac, three equipment Diesel phase Generator Note 1 Low X X X X X 1100 kW output Backup Voltage at 480 Vac, equipment Diesel three phase Generator Note 2 High X 2000 psi shutoff Backup Pressure head, 60 gpm equipment Injection capacity Pumps SG/RPV X 500 psi shutoff Backup Makeup head, 500 gpm equipment Pump max flow Low X X X 300 psi shutoff Backup Pressure / head, 2500 gpm equipment Medium max flow Flow Pump Low X X 150 psi shutoff Backup Pressure / head, 5000 gpm equipment High Flow max flow Page 38 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 PWR Portable Equipment Phase 3 Use and (potential /flexibility) diverse uses Performance Notes Criteria Note: The National SAFER Response Center NRC equipment is being procured at the time of this submittal.

The equipment listed is a generic list provided by the National SAFER Response Center and even though we may not require this equipment in our plan it will be available and could be utilized in the phase 3 time period.

List portable Core Containment SFP Instrumentation Accessibility equipment Cable / X X X Various as Backup Electrical determined by equipment ARE VA document #51-9199717-005 Hose / X X X Various as Backup Mechanical determined by equipment Connections ARE VA document # 51-9199717-005 Lighting X 40,000 lumens Backup Towers equipment Diesel Fuel 500 gallon air- Backup Transfer lift container equipment Diesel Fuel 264 gallon tank, Backup Transfer with mounted equipment Tank AC/DC pumps Portable 60 gpm after Backup Fuel filtration equipment Transfer Pump Electrical 4160 V. 250 Backup Distribution MVA, 1200 A equipment System Page 39 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 PWR Portable Equipment Phase 3 Use and (potential / flexibility) diverse uses Petfortruince Notes Criteria Note: The National SAFER Response Center equipment is being procured at the time of this submittal. The equipment listed is a generic list provided by the National SAFER Response Center and even though we may not require this equipment in our plan it will be available and could be utilized in the phase 3 time period.

List portable Core Containment SFP Instrumentation Accessibility equipment Mobile X X Each mobile Provide Boration boration unit Borated consists of three Water (3) stand-alone Source trailers containing:

  • Main tank, mixers, pumps and control panel on one stand-alone trailer
  • Generator and heater on one stand-alone trailer
  • A main generator on one stand-alone trailer Water X X The water treatment Provide Purification equipment shall Quality have an output flow Water capacity of 250 gpm Source (demineralized water)

Note 1: 1 MW is the individual generator output, and 2 MW is the total standard output to be supplied by the Phase 3 MV generators to satisfy identified load demands. The total output is created by connection of several smaller generators in parallel.

Note 2: The 1100 kW unit is derated to 1000 kW.

Page 40 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment lA Sequence of Events Timeline Time Action Remarks /

Elapsed Time Action Constraint item Applicability Y/N 1 The times to complete actions in the Events Timeline are based on operating judgment, the conceptual designs, and the current supporting analyses. The final timeline will be time validated once detailed designs are completed, procedures are developed, and the results will be provided in a future six (6) month update.

Event Starts, BDBEE occurs, Unit 1 and Unit 2 reactors 1 0 automatically trip and all rods are inserted. NA Unit 1 and Unit 2

@100% power Loss of off-site power (LOOP) affecting both units occurs

/ 1 min Emergency Operating Procedures, (EOPs) and Station Black NA _BCA 0.0, Loss of Out, (SBO), Procedures are entered. All AC Power, action.

3 5-50 mins Verify DDAF Pp is operating properly. Y 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> BCA 0.0, Loss of All AC Power, action. Reference WCAP 17601-P reference.

4 5 - 15 mins MCR closes C & D S/G PORVs to conserve inventory. Y 15 _BCA 0.0, Loss of minutes All AC Power, action. Reference WCAP 17601-P and operator judgment 5 10-30 mins Attempt starting Emergency D/G's NA _BCA 0.0, Loss of All AC Power, action.

6 30 mins ELAP condition recognized and ELAP Procedures are entered. NA _BCA 0.0, Loss of All AC Power, attachment B for ELAP I Instructions: Provide justification if No or NA is selected in the remark column If yes include technical basis discussion as requires by NEI 12-06 section 3.2.1.7 Page 41 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Reference BRW 7 30 mins to 6 hrs Connect FLEX 480V AC generators to ESF bus _32X and verify Y 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 0080-E Rev 0, Unit they are supplying power to Div 2 - 125V DC battery chargers 1(2) 125 VDC Battery FLEX Coping Calculation Common Calc Beyond Design Basis, dated May 2014.

Reference BRW 8 35 mins to 65 mins Operators dispatched to perform DC Bus Load Shed Y- 65 0080-E Rev 0, Unit minutes 1(2) 125 VDC Battery FLEX Coping Calculation Common Cale Beyond Design Basis, dated May 2014.

9 55 mins to 90 mins SX Short Cycle Cooling EC is aligned to cool the B AF Pp Y - 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> _BCA 0.0, Loss of within 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> after pump start. All AC Power, action. Reference BRW-13-0031-M Rev. 0, Transient Analysis of SX System Following Loss of A-C Power.

10 1.5 his Start depressurization of S/Gs to 260 psig at approximately Y -2 hours _BCA 0.0, Loss of 75°F/hr cooldown with SG PORV local/manual operation. SG All AC Power, feed is controlled with Local/Manual operation of AFW flow action. Reference control valves. BRW43-0221-M Rev 0, RCS Boration Analysis during an ELAP Event, dated June 2014.

11 2.25 hrs SI Accumulator borated water begins to inject into the RCS NA Operator Judgment 12 3.5 hrs Maintain SG pressure 260 psig and RCS temperature between NA Reference BRW 420F 410F with SG PORV operation. 0221-M Rev 0, RCS Boration Analysis Maintain SG level, during an ELAP Event, dated June 2014 13 3 5 hrs Set up and establish ventilation in AEER and MCR y _ 5.15 Directed from hours OBFSG-51Alternate MCR Ventillation Reference calculation BYR13-236/BRW-13-0218-M, Control Room and Auxiliary Electric Equipment Room heat up and Ventilation during an ELAP Page 42 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 14 5 7 hrs Isolate SI Accumulators NA 1/2BFSG -10 action 15 6 9 hrs Deploy FLEX DG to SX tower switchgear room and establish Y 17 Reference calculation power to one of the ESF Busses 131Z/132Z for power to a Well hours BYR14-119 UHS Water, (WW), Pump and establish make up flow to the UHS. Volume Analysis during an ELAP Event 16 6 - 10 hrs Deploy all hoses and connections in FHB for alternate SFP Fill Y - 10.94 Directed from strategy before FHB becomes uninhabitable from SFP Boiling hours OBFSG-5 and OFSG-

11. Reference BRW-13-0222-M Rev 0, Spent Fuel Pool Boil Off Analysis during an ELAP Event, dated April 2014.

17 12 16 hrs Stage and connect Phase 2 high pressure FLEX Pumps and Y - 17 Reference WCAP ensure they are available to supply borated make-up to the RCS hours 17601-P and and inject prior to entering Reflux Cooling. Westinghouse Letter LTR-FSE-14-61, Rev. O-A Dated July 2014 18 16 - 20 hrs Stage and connect Phase 2 med head FLEX Pumps and ensure NA 1/2BFSG-5action they are available to supply make-up to the SG's.

19 24 hrs Initiate SFP Make up via OA FC Purification pump as required NA OBFSG-llaction.

for level and temperature control Reference BRW 0222-M Rev 0, Spent Fuel Pool Boil Off Analysis during an ELAP Event, dated April 2014.

20 24 hrs National SAFER Response Center resources begin arriving on NA National SAFER site. Response Center Guide 2I 24 - 72 hrs Continue to maintain critical functions of Core Cooling (via NA End of analytical DDAF), RCS Inventory Control (via FLEX pump injection to simulation RCS) and SFP Cooling (via FLEX pump injection to SIP). Utilize initial National SAFER Response Center equipment and resources.

Page 43 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment 3 Update Mechanical One Line Diagrams c

x 0.1.

.44 I C

I I r.* I .

,Ir Li V

ansr2., 4 HI ID -111.4C FCC.. LL V

HI SO HID tem.  ?.

IRV RD Li rECC RR*.

nms V *1 " I' A Z. I ..

-10.-4LC

..Ht 44.10H4nit r4114 HE, V

110,4 C Th T2' Li

= cc 4CLL LI, *LiDsan Mt r * ** ,r.

J./

u'eft 1,0. L LI I- LIME FLE

  • E I **

'III fl T LTE IE FLE ORS 1.* HER C* I VE Page 44 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment 3 Update Mechanical One Line Diagrams SX "SHORT CYCLE" MOD 1 9;28 DC TRANSFER sys *

-11/1[000.

til r 4#31** t 11#13#411

.441 NNW. 0 liaJP*r_

fs+/-._

I xii.0% *XI. EAR

  1. { i. PIM POKR STATION spour! co F LE x CCSIGn I virIcArioa SMIEGIt s i )

uns lf r..... eyR FLEX Leyhc

- liiiiTh-F-1 i

Page 45 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Electrical Primary Strategy 15C1:11...V17/3' 'Jot 2 DI. 2 12.SVOC Bann 5se 21:x 2.4 lien 2:

22 E.C. CAT e2on 2r...Dc eatery Cnareer NOTE The charger car 310 Ned ose Um:

battery sta *1iti2g DC Crowe a 1.0 RLO AVVG Tref! C.

.1.!tva*; 232.x , DCAR Aseep A Batery Charger Al! CETC R2-.12.

FLEX GENERATOR Tuttersi Osteg Tractray Lout 2, El 40V Elan; trot 2 Wilco 2: 00Aff CaVes VOW0t 3SCAW aSCVAC Sr,I.E.1.--r!X0, vCC 2.22A2 Cti Atcnr..3%1 sz.lttn Va.ves

.Cotro Roo* ugitng

!Deur° Trees* Assert 1 * ** Av,S -.11) Cabe aeovAc MCC 23233 ODAF Duet B. Balery Coale, CR/t6IE Al 13 313'

.ECA2sver CoonKton Aa2e !KA Al 1142r 150VAC 482VAC %ICC 23231 eartl) Itoo, E vr at.s1 Curve AM E 126 C .61 AWC. Ten: CaAe 2 04 AWG Teoto cab*

Fxote F,ex Terve:wary Dosser Lesi !TONI 15,:vAS 23,1 .A A.0 SI Acurr...AI:e s.: att., . es CJI,2 E*

120 2CeVAC t2CVAC Estelslo,COM :Ts, Ma URN DD AA Pune Room u9rA rare 140VAC MCC 23232 AO El 321 1VCR Support taws

2LLIG.A. Si MR 2 DO Ar,Roo Roar WOI Fara !IL
161AS Si L1,2 AF005 Valve lecon L.gisN V:C 490VAC MCC 113V2 le t: z.!..C.10.20 Pull> A AD El an Vet 2 Avow laN. eve, *-* * .P3, - ttt *t* TC l4O*y Page 46 of 47

Byron Station, Units 1 and 2- Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Electrical Alternate Strategy The bar.try 03319*9143Nue2ed10 be Bus 232x Is myrrh] to De unaranaM 314035324 Out to laiS Of Dui 132X.

avt to a Nun or re 64.40e VOW Ns.

Csr11403,32 ON*44., 12 The Unt .2 Dv 2 125VDC Dairy t2s300C 83029 c The ova molar% thypc-Ny 1909*824 30 1251/DC MINN *tea horn tne 1110t 91.2520949300 12502C Ere/

Sem VCC feteler Oreales be OMNI, 31,07I. 0l46321 12 Champs %la IX to sLeN0o1 TM Merry* C1033.g5 essarlg DC Cmste.

430VAC VCC 23241 1.32AF Pv,p A tatters Ctar.;.,

AS el Mr CETCRVLIS 1621, Sa13009*x FLEX GENEKATOR BUG 1325 MAW 23 Tuelant 04:19 ThltelThly 0fr 12 !SF Dr" Rom 12300C Mary rls C LPN 2. ICI' El 424 44, 350511 atOVAC SFP *,

413030A0 MCC 23252 0.2 3 10. 41 ry, 03,e1 Cul, WS 2, 426 2LL43. .00,45 ftOon -gntrg, E Gest DO Transfer Nov

  • c as 3 4WD Temp Cabe fLex GEntelaATOR now* Vag Traoltsmy 431330A0 %ICC 23243 034 1. 131 /Or 29 431E 4132138Y

-Ex Peatr ConrfctOo 350431140VAC Pr,! ;C0

  • 9 10121 440VAC VCC 23203 CuntSal E* 426' 3C ASVG Tensfs CaNe 3C Si MUG Strip cape 290131E FLEX Temporary emir
  • 400 (TPU1 46CVAC MCC 231%2A Cone 1131 2! 11...

1222031VAC 48330A0 %KC 23302 AD!! 426' ANIVAC MCC 13302 AD t, 426

> vCR 35923 *0360 3L111314 B;

,,Looda b 15, afiCVAC VCC 13201

  • 8 21 36.4'

(

Coolcafthenl N1 ,Roar.

ONLY To LAI 1 991133) Snug)

%KC 131420 ADD! Accarvtator idaton Var.'

Page 47 of 47