MONTHYEARLR-N13-0205, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Base Case Velocity...2013-09-10010 September 2013 Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Base Case Velocity... Project stage: Response to RAI 0CAN091301, Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi..2013-09-12012 September 2013 Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi.. Project stage: Response to RAI LR-N14-0051, PSEG Nuclear Llc'S Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima.2014-03-28028 March 2014 PSEG Nuclear Llc'S Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima. Project stage: Response to RAI 0CAN031404, ANO, Units 1 & 2 - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (Nttf)Review of Insights from the Fukushima2014-03-28028 March 2014 ANO, Units 1 & 2 - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (Nttf)Review of Insights from the Fukushima Da Project stage: Response to RAI ML14092A4172014-03-31031 March 2014 Response to March 12, 2012 Information Request Seismic Hazard and Screening Report (CEUS Sites) for Recommendation 2.1 Project stage: Request RS-14-065, Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of The..2014-03-31031 March 2014 Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of The.. Project stage: Response to RAI LIC-14-0047, Omaha Public Power District - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushi2014-03-31031 March 2014 Omaha Public Power District - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Project stage: Request ML14204A6202014-07-21021 July 2014 Response to Request for Additional Information Regarding Seismic Hazard and Screening Report for Seismic Recommendation 2.1 Project stage: Response to RAI ML14204A6192014-07-21021 July 2014 Response to March 12, 2012 Information Related to the Seismic Hazard and Screening Report for Recommendation 2.1 Project stage: Request NL-14-099, Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights.2014-08-18018 August 2014 Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights. Project stage: Request 0CAN081401, Response to Request for Additional Information (RAI) Associated with Near-Term Task Force (NTTF) Recommendation 2.1, Seismic Hazard and Screening Report2014-08-21021 August 2014 Response to Request for Additional Information (RAI) Associated with Near-Term Task Force (NTTF) Recommendation 2.1, Seismic Hazard and Screening Report Project stage: Response to RAI RS-14-206, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other PLA-7224, Response to March 12, 2012 Information Request - Supplemental Information Related to the Seismic Hazard and Screening Report for Recommendation 2.1 - PLA-72242014-08-28028 August 2014 Response to March 12, 2012 Information Request - Supplemental Information Related to the Seismic Hazard and Screening Report for Recommendation 2.1 - PLA-7224 Project stage: Request RS-14-230, Supplemental Information Related to the Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2, 1 of the Near-Term Task Force Review Of...2014-08-29029 August 2014 Supplemental Information Related to the Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2, 1 of the Near-Term Task Force Review Of... Project stage: Supplement ML14224A5262014-09-22022 September 2014 Screening and Prioritization Results of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Project stage: Other LIC-14-0124, Supplemental Information Related to Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The...2014-10-22022 October 2014 Supplemental Information Related to Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The... Project stage: Supplement LR-N14-0227, Seismic Hazard and Screening Report - Supplemental Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-10-30030 October 2014 Seismic Hazard and Screening Report - Supplemental Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Supplement 0CAN111401, Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-11-0404 November 2014 Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Other NL-14-139, Additional Information Regarding the Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-11-0505 November 2014 Additional Information Regarding the Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Request ML14310A0222014-11-13013 November 2014 Report Regarding Individual Plant Examination of External Events Supporting Information for Seismic Screening Project stage: Other ML14246A4282014-11-21021 November 2014 Screening and Prioritization Results Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident Based on Individual Plant Examination of External Events Project stage: Approval ML14310A0332014-12-15015 December 2014 NRC Response to Licensees Notification of Revised Regulatory Commitments Associated with Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Revie Project stage: RAI ML15329A1812015-12-0808 December 2015 Staff Assessment of Information Provided Pursuant of Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f)Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights.. Project stage: Approval ML15328A2682015-12-15015 December 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review Project stage: Other ML15344A1092015-12-15015 December 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Project stage: Other ML17123A3782016-04-27027 April 2016 Reevaluated Seismic Hazard Mitigating Strategies Assessment Report Project stage: Other LIC-16-0039, Ft. Calhoun, Unit 1 - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Accident2016-05-25025 May 2016 Ft. Calhoun, Unit 1 - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Accident Project stage: Response to RAI ML16365A0322016-12-21021 December 2016 Response to March 12, 2012 Information Request, Spent Fuel Pool Seismic Evaluation for Recommendation 2.1 Project stage: Other 0CAN121602, Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information Per Nuclear Energy Institute (NEI) 12-06, Appendix H, Revision 2, H.4.3 Path 32016-12-30030 December 2016 Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information Per Nuclear Energy Institute (NEI) 12-06, Appendix H, Revision 2, H.4.3 Path 3 Project stage: Other 2014-07-21
[Table View] |
|
---|
Category:Letter type:LIC
MONTHYEARLIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update LIC-18-0030, Request for Partial Site Release Phase 22018-11-12012 November 2018 Request for Partial Site Release Phase 2 LIC-18-0028, Letter of Intent to Submit Request for Additional Partial Site Release2018-10-18018 October 2018 Letter of Intent to Submit Request for Additional Partial Site Release LIC-18-0027, Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2018-10-0303 October 2018 Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update LIC-18-0003, License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool2018-09-28028 September 2018 License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool LIC-18-0025, Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 20192018-07-19019 July 2018 Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 2019 LIC-18-0023, Fort Calhoun Station, Unit 1 Request for Partial Site Release2018-06-29029 June 2018 Fort Calhoun Station, Unit 1 Request for Partial Site Release LIC-18-0021, Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan)2018-06-0606 June 2018 Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan) LIC-18-0017, Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy2018-04-26026 April 2018 Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy 2023-08-24
[Table view] |
Text
-~
fjjjjjjj Omaha Public Power Dlslrfct 444 South tffh Street Mall Omaha, NE 68102-2247 10 CFR 50.54(f)
LIC-14-0124 October 22, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285
Subject:
Supplemental Information Related to the Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10CFR 50.54(f} Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident
References:
See Page 4 On March 12, 2012, the Nuclear Regulatory Commission (NRC} issued Reference 1 to all power reactor licensees and holders of construction permits in active or deferred status. Enclosure 1 of Reference 1 requested each addressee located in the Central and Eastern United States (CEUS) to submit a Seismic Hazard Evaluation and Screening Report within 1.5 years from the date of Reference 1. Omaha Public Power District (OPPD} submitted the Seismic Hazard and Screening Report for Fort Calhoun Station Unit No. 1 (FCS) to the NRC in Reference 4. The report provided the basis for FCS to screen out of performing seismic risk evaluations in accordance with the guidance in the SPID (Reference 2) . This screening was based on demonstrating that the plant capacity spectra for FCS from the Individual Plant Examination for External Events (IPEEE) exceed the new ground motion response spectrum (GMRS} for all frequencies. Reference 4 also demonstrated IPEEE adequacy, in accordance with the criteria in the SPID. Consistent with the guidance contained in Reference 3, the Seismic Hazard and Screening Report (Reference 4}
indicated that FCS screens-in for performance of the Expedited Seismic Evaluation Process (ESEP) .
In Reference 1, the NRC requested interim evaluations and actions ".. . to address the higher seismic hazard .... prior to completion of the risk evaluation." Section 1 of the Augmented Approach guidance (Reference 3} states that" ... this report addresses interim evaluations .. .to be implemented prior to performing complete plant seismic risk evaluations." The NRC endorsement of the Augmented Approach guidance (Reference 5), states that the ESEP can demonstrate seismic margin " .. .while more detailed and comprehensive plant seismic risk evaluations are being performed."
U. S. Nuclear Regulatory Commission LIC-14-0124 Page2 Since the new GMRS for FCS has acceptably low spectral amplitudes and seismic risk evaluations are not required (References 4 and 6), OPPD considers that interim evaluations per the Augmented Approach guidance for ESEP, which were intended to address high seismic hazards prior to completion of a seismic risk evaluation, are not warranted. Also based upon Reference 6 the NRC staff determined that FCS screens out of conducting a seismic risk evaluation since the IPEEE demonstrates plant seismic capacity to levels higher than the GMRS in the 1-10Hz range and that OPPD demonstrated that the IPEEE adequacy related screening criteria in the NRC approved industry guidance was met. The NRC also concluded in Reference 6, that FCS screened out of performing a high frequency evaluation because the IPEEE capacity exceeds the GMRS in the frequency ranges greater than 10 Hz range.
From a seismic safety perspective, the FCS IPEEE was performed using the EPRI Seismic Margin Assessment (SMA) fault based methodology (NUREG/CR-4334). The NRC issued a staff evaluation for the FCS IPEEE (Reference 7), as also noted in Reference 4 Appendix B. The results of the review documented in Reference 4 concluded that the IPEEE was adequate to support screening of the updated seismic hazard for FCS. In addition, the FCS GMRS is conservatively bound in the low and mid-range frequencies by the IPEEE spectra RLE and IHS (0.1 to 10 Hz). In the higher frequency ranges the IPEEE spectra still bound the GMRS (i.e.
greater than 10 Hz). Therefore, a review of components in accordance with the ESEP guidance would not provide a significant increase in safety insight or margin beyond what was already provided by the IPEEE program.
OPPD has therefore concluded that for FCS there is an insignificant safety benefit from the performance of the ESEP since no long-term seismic risk evaluations are required based on the submitted screening results (Reference 4) and FCS has demonstrated seismic capacities above the GMRS.
In accordance with OPPD's commitment to nuclear safety, our resources are focused on activities that provide the most effective safety benefit. Therefore, OPPD does not intend to perform the ESEP for FCS. The commitment to perform a relay chatter review, and spent fuel pool evaluation per the guidance in References 2 and 3, as indicated in the Seismic Hazard and Screening Report (Reference 4), remains unchanged.
This letter contains no new regulatory commitments. This letter provides the basis for cancellation and closure of the interim action OPPD stated would be taken to perform an ESEP from FCS Seismic Hazard and Screening Report (noted in Reference 4 and 6, footnote 2). The commitment stated in Reference 6 (Commitment 4 in Confirmatory Action Letter (CAL) EA 243, dated December 17, 2013) to correct the condition noted remains unchanged.
If you have any questions regarding this report, please contact Bill Hansher at (402) 533-6894.
U.S. Nuclear Regulatory Commission LIC-14-0124 Page3 2/1 I declare under penalty of perjury that the foregoing is true and correct. Executed on October 22, I
Louis P. Cortopassi Site Vice President and CNO LPC/JLB/brh c: W. M. Dean, Director of Office of Nuclear Reactor Regulation N. J. DiFrancesco, NRC Lead Project Manager, Seismic M. L. Dapas, NRC Regional Administrator, Region IV C. F. Lyon, NRC Senior Project Manager S.M. Schneider, NRC Senior Resident Inspector
U. S. Nuclear Regulatory Commission LIC-14-0124 Page 4
References:
- 1. NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012
- 2. EPRI Report 1025287, Seismic Evaluation Guidance, Screening, Prioritization and Implementation Details (SPID) for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1 : Seismic
- 3. EPRI Technical Report 3002000704, "Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Seismic,"
dated May 2013
- 4. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Omaha Public Power District (OPPD) Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 31,2014 (LIC-14-0047)
- 5. NRC Letter, Electric Power Research Institute Final Draft Report XXXXXX, "Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Seismic," as an Acceptable Alternative to the March 12, 2012, Information Request for Seismic Reevaluations, dated May 7, 2013
- 6. Letter from NRC (D. H. Dorman) to OPPD (L. P. Cortopassi), Fort Calhoun Station, Unit 1-Screening and Prioritization Results of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations for Recommendation 2. 1 of the Near- Term Task Force Review of Insights from the Fukushima Dai-lchi Accident (TAG No. MF3735), dated September 22, 2014 (NRC-14-0109)
- 7. Letter from NRC (L. R. Wharton) to OPPD (S. K. Gambhir), Review of Fort Calhoun Station Individual Plant Examination of External Events (/PEEE) Submittal (TAG No. MB3623), dated May 6, 1999, (NRC-99-057)