ML18113A530
Person / Time
Site: Point Beach, 05000200
Issue date: 04/23/2018
From: Schultz E
Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2018-0023, RIS 2018-02
Download: ML18113A530 (2)


Text

April 23, 2018 NRC 2018-0023 RIS 2018-02 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Response to Regulatory Information Summary 2018-02 "Preparation and Scheduling of Operator Licensing Examinations" On March 26, 2018 the NRC issued Regulatory Issue Summary (RIS) 2018-02. RIS 2018-02 requests that each licensee provide an update of operator licensing examination information for calendar years 2020 through 2023.

The enclosure to this letter provides the NextEra Energy Point Bach, LLC, response for the Point Beach Nuclear Plant, Units 1 and 2.

The current date of the next Operator Licensing Examination for calendar year 2019 is July 15 and 22, 2019 with an onsite validation scheduled for the week of June 10, 2019.

If there are questions concerning this, please contact Mr. Darren Peterson, Point Beach Nuclear Plant Training Manager, at 920-755-7775.

Sincerely, NextEra Energy Point Beach, LLC Eric Schultz Licensing Manager Enclosure cc: Administrator, Region Ill, USNRC Operations Branch Chief, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC 6610 Nuclear Road, Two Rivers, WI 54241

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMS: NO. 3150-0131 EXPIRES: 11/30/2020 (11-2017)

J.}*1t'Af"G"-*
  • ..,.,*" "'"" ~

OPERATOR LICENSING Estimated burden per response to comply with this voluntal)' information collection request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send

!';i ~ comments regarding burden estimate to the Information Services Branch (T-2 F43), U.S. Nuclear

~ EXAMINATION DATA Regulatol)' Commission, Washington, DC20555-0001, or by e-mail to lnfocollects.Resource@nrc.gov,

'Yi-l,l +<!!"~ and to the Desk Officer, Office of Information and RegulatOJ)' Affairs, NEOB-10202, (3150-0131), Office

  • .'lf-.*+:*1( of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301, Renewed License Nos. DPR-24 and DPR-27 1111 I

A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2020 CY 2021 CY 2022 cy2023 ESTIMATED NUMBER OF LICENSEE-PREPARED 0 1 0 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2020 CY2021 CY2022 CY2023 NUMBER OF REACTOR OPERATORS 0 3 0 3 NUMBER OF SENIOR REACTOR OPERATORS -INSTANT 0 4 0 4 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0 2 0 2 NUMBER OF SENIOR REACTOR OPERATORS- LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE 5/24/21 5/22/23 ALTERNATE DATE 6/28/21 6/26/23 NRC FORM 536 (11-2017)