NRC 2008-0060, Withdrawal of License Amendment Request 260 Re One-Time Extension of Completion Time for Technical Specification 3.7.5, Auxiliary Feedwater System.

From kanterella
Jump to navigation Jump to search
Withdrawal of License Amendment Request 260 Re One-Time Extension of Completion Time for Technical Specification 3.7.5, Auxiliary Feedwater System.
ML082380149
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 08/21/2008
From: Meyer L
Florida Power & Light Energy Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2008-0060
Download: ML082380149 (2)


Text

FPL Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241 FPL Energy Point Beach Nuclear Plant August 21,2008 NRC 2008-0060 10 CFR 50.90 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Withdrawal of License Amendment Request 260 One-Time Extension of Com~letionTime for Technical S~ecification3.7.5. Auxiliarv Feedwater Svstem

References:

(1) FPL Energy Point Beach, LLC to NRC Letter Dated December 29,2007, License Amendment Request 260 One-Time Extension of Completion Time for Technical Specification 3.7.5, Auxiliary Feedwater System (ML073650392)

(2) FPL Energy Point Beach, LLC to NRC Letter Dated May 15,2008, Response to Request for Additional Information, License Amendment Request 260, One-Time Extension of Completion Time for Technical Specification 3.7.5, Auxiliary Feedwater System (ML081780362)

(3) FPL Energy Point Beach, LLC to NRC Letter Dated May 29, 2008, Response to Request for Additional Information, License Amendment Request 260, One-Time Extension of Completion Time for Technical Specification 3.7.5, Auxiliary Feedwater System (ML081510464)

(4) FPL Energy Point Beach, LLC Letter Dated July 3,2008, Supplemental Response to Request for Additional Information, License Amendment Request 260, One-Time Extension of Completion Time for Technical Specification 3.7.5, Auxiliary Feedwater System (ML081890159)

Via Reference ( I ) FPL Energy Point Beach, LLC submitted a proposed license amendment request for Commission review and approval pursuant to 10 CFR 50.90 for the Point Beach Nuclear Plant (PBNP), Units 1 and 2. The proposed amendment requested the Completion Time for Technical Specification 3.7.5, "Auxiliary Feedwater System" be extended from seven (7) days to 16 days. References 2, 3 and 4 contained responses for requests for additional information regarding Reference 1.

Document Control Desk Page 2 On August 20, 2008, a teleconference was held with representatives of FPL Energy and the NRC. As a result of that teleconference, a decision was made to withdraw License Amendment Request 260 in its entirety at this time, including the Regulatory Commitments made in References (1) through (4) pending resolution of technical concerns. FPL Energy Point Beach plans to resubmit this license amendment request at a future date when these concerns are resolved.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on August 21,2008.

Very truly yours, FPL Energy Point Beach, LLC cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW