Nuclear Management Company - Point Beach Nuclear Power Plant Units 1 & 2 CAL 3-04-001, Revision 1 Engineering Design Control Commitment Status Update
ML062710157
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 07/28/2006
From:
Nuclear Management Co
To:
Region 3 Administrator
References
42 USC 2332, CAL 3-04-001, NRC 2006-0046
Download: ML062710157 (1)


Text

Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC July 28, 2006 NRC 2006-0046 42 USC 2332 Regional Administrator Region Ill U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 License Nos. DPR-24 and DPR-27 CAL 3-04-001, Revision 1 Enqineerinq Desisn Control Commitment Status UDdate

References:

(1) Nuclear Regulatory Commission (NRC) Letter Dated April 14, 2006, Transmitting Confirmation Action Letter CAL 3-04-001, Revision 1 (2) Nuclear Management Company, LLC (NMC) Letter Dated March 31, 2005, Transmitting CAL Commitment Schedule Revisions (3) NMC Letter Dated February I O , 2006, Proposing Additional Regulatory Commitments in the Engineering and Corrective Action Program Areas of Regulatory Concern (41 NMC Letter Dated May 12,2006, Transmittal of Engineering Independent Assessment Plan On April 14,2006, the NRC transmitted Confirmatory Action Letter (CAL) CAL 3-04-001, Revision 1 to NMC via Reference (1). The revised CAL contains two commitments in the Engineering Design Control Area of Regulatory Concern. These two commitments had been proposed by NMC via Reference (3).

In Reference (1) NRC requested that NMC notify the NRC, pursuant to Section 182 of the Atomic Energy Act, 42 USC 2332, if NMC cannot complete the actions within the specified schedule in the March 31 , 2005, and February 10,2006, letters, and advise the NRC of the modified schedule in advance of the change.

In Reference (2) NMC submitted an update on CAL commitments and performance measures. The enclosure of Reference (2) provided a revised completion schedule for the milestones associated with the safety-related calculation project described by Action Plan OP-14-005.

6610 Nuclear Road Two Rivers, Wisconsin 54241 Telephone 920.755.2321